# NetSuite MRP Not Generating Planned Orders: Causes and Fixes

> Source: https://netray.co/erp-help/netsuite-mrp-planned-orders-not-generated-fix
> Publisher: Netray (netray.co), AI and integration engineering for ERP and manufacturing systems.
> Section: ERP Help

## Short answer

When NetSuite Generate Planned Orders returns nothing, the cause is nearly always item setup or demand: the item is not set for supply planning, demand falls outside the planning time fence, existing supply already covers it, or the lead time and lot size settings prevent a suggested order. Check the item's Planning fields first, then the demand source, then the plan itself.

## Kind

error

## System

netsuite

## Erp

Oracle NetSuite

## Module

Supply Planning / Demand Planning

## Query

NetSuite MRP not generating planned orders

## Alternate Queries

- NetSuite supply planning no planned orders
- NetSuite generate planned orders returns nothing
- NetSuite item supply plan empty
- NetSuite planned orders wrong quantity or date

## Applies To

NetSuite with the Material Requirements Planning (Demand Planning and Supply Planning) feature enabled; items set to time-phased replenishment

## Steps

### How to diagnose missing planned orders

**Items:**

- Confirm the features: Setup > Company > Enable Features > Items & Inventory should have Demand Planning and Material Requirements Planning (supply planning) enabled.
- Open the item record and check the Planning subtab: the supply replenishment method must be time-phased, and the item must not be excluded from planning.
- Check lead time, safety stock, lot sizing method and any fixed lot size or multiple. A missing lead time or a lot size larger than the demand horizon can hide orders.
- Check the demand time fence and planning time fence. Demand inside the demand time fence may be ignored, and orders inside the planning time fence are not auto-created.
- Review demand: sales orders, work order component demand, and the item demand plan. Verify the requested ship date, the location, and that the transaction is approved and not closed.
- Review supply already on order: open purchase orders, work orders and firmed planned orders may already cover the demand and the date.
- Verify location settings: items planned per location need planning fields and a replenishment source for each location.
- Run Generate Planned Orders again from the Supply Planning menu and open the item supply plan to read the time-phased netting line by line.
- Firm and release the planned orders into purchase orders or work orders once they look right.

## Sections

### How the netting works

**Body:**

Time-phased planning nets demand against supply by date. For each item and location NetSuite takes the demand (sales orders, dependent demand from work orders, the demand plan), subtracts on-hand and scheduled receipts, and when the projected balance falls below safety stock, it suggests a planned order. The suggested date is back-scheduled by lead time.

That mechanism explains most empty results. If on-hand is large, if a purchase order already lands before the need date, or if the demand is dated after the planning horizon, there is simply nothing to plan. Before assuming a defect, read the item supply plan view for one item and trace the arithmetic by hand.

### Item fields that suppress planning

**Body:**

The Planning subtab of the item record controls almost everything. Items set to reorder point rather than time-phased are handled by Order Items, not Generate Planned Orders. An item with the wrong supply type, for example bought versus built, may produce orders of the type you did not expect. A blank lead time means supply is assumed immediate, which can collapse the plan.

Lot sizing matters too. A fixed lot size plan creates orders in multiples, so demand of 40 against a fixed lot of 500 yields one order of 500 or none depending on the horizon. Lot-for-lot creates exact orders. Check this before changing anything else.

**Code:**

-- SuiteQL: items flagged for time-phased planning with no lead time
SELECT i.itemid, i.leadtime, i.safetystock
FROM item i
WHERE i.isinactive = 'F' AND (i.leadtime IS NULL OR i.leadtime = 0)

### Time fences and the horizon

**Body:**

The demand time fence sets how many days out firm demand is trusted, and the planning time fence sets how many days out the system will not create new planned orders. Inside the planning time fence NetSuite expects planners to act manually. That is intentional, since moving a purchase order two days out is rarely something to automate.

The planning horizon is also finite. Demand dated beyond the horizon is not netted, so a long lead item whose demand sits far out may show no order until the horizon rolls forward. If your lead times are long, check the planning horizon preference before suspecting data.

### Firming and releasing

**Body:**

Planned orders are suggestions. Firm them to protect them from being recalculated, then release them to create the purchase order or work order. If you regenerate without firming, the plan is rebuilt and your edits are lost. Firmed orders still count as supply in later netting, which is also why a stale firmed order can quietly stop new ones appearing.

After release, the real transactions appear in the supply side, and the planned order is consumed. If a released order is later cancelled, regenerate so the demand reappears.

## Pitfalls

- Expecting reorder point items to appear in Generate Planned Orders: they use Order Items instead.
- Leaving lead time blank so supply looks instantly available.
- Not firming orders before regenerating, which discards planner edits.
- Stale firmed planned orders that keep counting as supply and block new suggestions.
- Testing with a location that has no planning fields, while the item is planned per location.

## Ai Angle

A grounded assistant on NetSuite can pull the item's planning fields, open demand and supply lines, and walk the netting arithmetic for one item, explaining why no order was suggested. ERPray shows the query it ran and stays read-only, so the planner still firms and releases. For simple reorder-point replenishment, NetSuite's own Order Items screen is usually enough without any AI layer.

## Faq

### Why does Generate Planned Orders finish with no results?

**Answer:** Usually because supply already covers demand, the demand is outside the horizon or inside a time fence, or the item is not set for time-phased planning. Open the item supply plan for one known item and read the netting to see which applies.

### What is the difference between Order Items and planned orders?

**Answer:** Order Items works from reorder point and preferred stock level and creates purchase or work orders directly. Planned orders come from time-phased supply planning, which nets dated demand and supply and proposes orders you firm and release.

### Do planned orders consider component demand?

**Answer:** Yes for items on a bill of materials: planned or actual work orders create dependent demand for components, which then drives their own planned orders. Make sure components are also set up for planning, or they will not show suggestions.

### Can I rerun planning without losing my edits?

**Answer:** Firm the planned orders you want to keep before regenerating. Unfirmed suggestions are rebuilt from scratch, so manual quantity or date changes on them are lost.