# AQL and Acceptance Sampling

> Source: https://netray.co/glossary/aql-acceptance-sampling
> Publisher: Netray (netray.co), AI and integration engineering for ERP and manufacturing systems.
> Section: Glossary

## Short answer

Acceptance sampling inspects a random sample from a lot and accepts or rejects the whole lot based on the number of defects found. AQL (acceptance quality limit) is the worst defect rate considered acceptable as a process average in that plan.

## Aliases

- AQL
- acceptable quality limit
- acceptance quality limit
- ANSI Z1.4
- ISO 2859-1
- sampling plan

## Category

manufacturing

## Full Definition

Checking every piece is slow, costly and, for visual work, not even reliable. A sampling plan picks a sample size n from a lot of size N and an accept number c. If the sample has c or fewer defects the lot is accepted, otherwise it is rejected or screened. The tables in ANSI/ASQ Z1.4 (equivalent to ISO 2859-1) and ISO 2859 family, and MIL-STD-105E before them, give plans by lot size, inspection level and AQL.

The procedure: choose the inspection level (general level II is the default, levels I and III give less or more discrimination), find the sample size code letter from lot size, then read n, accept and reject numbers for the chosen AQL. Typical AQLs are 0.65 for major defects and 2.5 or 4.0 for minor ones, with critical defects usually 0 tolerated. Switching rules move you between normal, tightened and reduced inspection based on recent lot history.

Sampling has limits. An AQL of 1.0 does not mean the shipped product is 1 percent defective in every lot, and an accepted lot can still contain defects. The operating characteristic (OC) curve shows the probability of acceptance at each true defect rate. For safety critical parts, or when a process is capable, 100 percent inspection, skip-lot arrangements or SPC-based acceptance are usual alternatives, and zero-accept plans (c=0) are common in aerospace and medical.

In ERP receiving inspection, the sampling plan is attached to the item, supplier or inspection plan. SyteLine and LN let you define inspection plans with sample size rules and acceptance criteria at receipt or in process, and the ERP then holds the lot until the inspector records the result and the lot is accepted, rejected or sent to the MRB.

## Why It Matters

- It balances inspection cost against the risk of accepting bad lots, which matters when inspecting every unit is impractical or destructive.
- Customer and supplier agreements often define AQL in purchase terms, so disputes are settled by the agreed plan rather than opinion.
- A well tuned plan, with tightened inspection after failures, gives suppliers a reason to improve.
- Wrong assumptions about AQL lead to shipping defects that the contract allowed but the customer did not expect.

## In Practice

A lot of 1,200 molded housings arrives. Using ANSI Z1.4 general level II, code letter L gives a sample of 200. At AQL 1.0 for major defects the plan accepts at 5 and rejects at 6. The inspector finds 4 cracked housings, so the lot is accepted, but the supplier scorecard logs a 2 percent sample defect rate. If the next lot fails, switching rules move the supplier to tightened inspection.

## Faq

### What does AQL 2.5 mean?

**Answer:** It is the maximum defect rate, 2.5 percent, treated as acceptable as a process average in the sampling scheme. Individual accepted lots can contain more or fewer defects than that.

### What is the difference between AQL and LTPD?

**Answer:** AQL is the quality level the plan accepts most of the time. LTPD (lot tolerance percent defective) is the poor quality level the plan rejects most of the time, protecting the buyer.

### What is a zero acceptance number plan?

**Answer:** A plan where the lot is rejected if any defect is found in the sample (c=0). It is common for critical characteristics in aerospace and medical devices.

### Can ERP automate sampling?

**Answer:** Yes, most ERP quality modules can assign a sample size rule per item or supplier at receipt and hold the lot until the result is entered, although the sampling tables themselves are set up by quality.

## Search terms

what is AQL, acceptance quality limit explained, acceptance sampling plan, ANSI Z1.4 sampling table, ISO 2859-1 AQL, AQL critical major minor defects, OC curve acceptance sampling

---
Talk to an engineer: https://netray.co/contact?intent=erp_ai | Machine catalog: https://netray.co/agent/catalog.json
