# Cost of Poor Quality (COPQ)

> Source: https://netray.co/glossary/cost-of-poor-quality
> Publisher: Netray (netray.co), AI and integration engineering for ERP and manufacturing systems.
> Section: Glossary

## Short answer

Cost of poor quality (COPQ) is the total cost caused by products or services not being right the first time: internal failure (scrap, rework), external failure (returns, warranty, recalls), and often appraisal and prevention spend in the full cost of quality model.

## Aliases

- COPQ
- cost of quality
- COQ
- quality costs

## Category

manufacturing

## Full Definition

The classic cost of quality model, associated with Feigenbaum and Juran, has four categories. Prevention costs (training, FMEA, process design) and appraisal costs (inspection, testing, calibration, audits) are spent to avoid defects. Internal failure costs (scrap, rework, re-inspection, downtime) occur before shipment. External failure costs (returns, warranty, field service, liability, lost customers) occur after shipment. COPQ usually means the two failure categories.

Counting it is the hard part. Scrap value shows up in the general ledger, but rework labor, expediting, extra setups, line stoppages, customer penalties and reputation rarely have their own accounts. Many plants find the visible scrap line is a minority of the true figure. Six Sigma teams often quote COPQ as a percent of sales, with the common claim that poorly performing operations spend a large share of revenue on it, but real values vary widely by industry and should be measured, not assumed.

The economics change the investment case. A defect found in incoming inspection costs a few dollars, the same defect found in final assembly costs hours, and found at the customer costs a return, a corrective action and potentially a contract. This is the reasoning behind prevention spending such as poka-yoke and SPC.

Capturing it needs reason codes in the ERP. Scrap transactions, rework operations and return material authorisations should all carry coded reasons, cost roll-ups and links to the item, work centre and supplier. SyteLine and LN can book scrap and rework against jobs and report variance, and a quality cost report that joins those with warranty claims gives a real COPQ number.

## Why It Matters

- It converts quality problems into a financial figure leadership can prioritise against other projects.
- It exposes hidden factory cost, such as rework labor and expediting, that standard cost variances bury.
- The category split shows whether to invest in prevention or in better detection.
- A tracked COPQ trend verifies whether CAPA and improvement projects actually paid back.

## In Practice

A plant reports 90,000 dollars a quarter of scrap. A full COPQ study adds 140 hours of rework at 55 dollars an hour, 30 hours of line downtime from rejected lots at 400 dollars an hour, 25,000 dollars of customer returns and 12,000 dollars of expedited freight. Total COPQ is about 146,700 dollars, roughly 1.6 times the scrap line, which changes which projects get funded.

## Faq

### What are the four categories of cost of quality?

**Answer:** Prevention, appraisal, internal failure and external failure. COPQ usually refers to the two failure categories.

### How do you calculate COPQ?

**Answer:** Add scrap, rework, re-inspection, downtime, returns, warranty, expediting and penalties attributable to defects, using coded transactions and labor and machine rates.

### Is COPQ the same as cost of quality?

**Answer:** Not exactly. Cost of quality includes prevention and appraisal spend too. COPQ is the failure cost portion, the waste that better quality would remove.

### Why is COPQ often underestimated?

**Answer:** Because hidden costs like rework hours, extra setups, expedites and lost customers are not booked to a quality account and need deliberate tracking.