# Non-Conformance Report (NCR)

> Source: https://netray.co/glossary/non-conformance-report
> Publisher: Netray (netray.co), AI and integration engineering for ERP and manufacturing systems.
> Section: Glossary

## Short answer

A non-conformance report (NCR) is the formal record that a part, material, process or document failed a specified requirement. It captures what failed, how many, where, and the disposition decision (use as is, rework, repair, scrap or return to supplier).

## Aliases

- NCR
- nonconformance report
- discrepancy report
- defect report

## Category

manufacturing

## Full Definition

An NCR is the unit of record in a quality system for anything that does not meet drawing, specification, contract or procedure. It is raised by receiving inspection, in-process inspection, final test, a customer return, or an auditor. A good NCR identifies the item and revision, the lot or serial number, the quantity affected, the requirement violated, the measured result, who found it and at which operation.

Disposition is the heart of the document. Typical outcomes are use as is (needs engineering and often customer concession), rework to the original requirement, repair to a different but accepted state (customer approval is usually required in aerospace), scrap, or return to vendor. The NCR also decides whether the stock is quarantined, which stops MRP, picking and shipping from touching it until a disposition is recorded.

In ERPs the NCR lives in the quality module and is linked to inventory. Infor SyteLine records rejects and quality holds through its quality control and inspection functions, and Infor LN ties rejected quantities to inspection orders and warehouse inspection locations. Standalone QMS tools such as MasterControl or ETQ hold the NCR and sync the stock status back to the ERP. The integration point that matters most is the inventory hold: an NCR that does not freeze the lot is only paperwork.

An NCR is not the same as a CAPA. The NCR deals with the affected product now, the CAPA deals with why it happened and stopping recurrence. Many organisations raise a CAPA only when NCRs on the same cause cross a threshold or when severity is high.

## Why It Matters

- Standards such as ISO 9001 clause 8.7 and AS9100 require control of nonconforming outputs, with records of the disposition and who authorised it.
- An NCR that does not quarantine stock in the ERP lets suspect material get issued to a job or shipped to a customer.
- NCR data by supplier, part and cause is the raw material for Pareto analysis, supplier scorecards and CAPA triggers.
- Cost of scrap, rework and concessions is traceable only when each NCR carries a quantity and a cost, which feeds cost of poor quality reporting.

## In Practice

Receiving inspection rejects 40 of 500 machined housings because a bore measures 0.02 mm over tolerance. The inspector raises an NCR, the 40 pieces move to a quarantine location and the ERP shows them as unavailable. The material review board dispositions 30 as rework (re-bore and sleeve) and 10 as return to vendor with a debit memo. Because the NCR holds the lot, MRP does not count those 40 as supply, and the buyer sees the shortfall that day instead of at kitting.

## Faq

### What is the difference between an NCR and a CAPA?

**Answer:** An NCR records and dispositions the specific nonconforming product or event. A CAPA investigates the root cause and puts actions in place so it does not recur. One CAPA often covers many NCRs.

### Who can approve an NCR disposition?

**Answer:** It depends on your quality manual. Rework to print is often approved by quality alone. Use as is or repair usually needs engineering and, for customer-controlled designs, customer approval.

### Should an NCR block inventory in the ERP?

**Answer:** Yes. The NCR should move the affected lot to a quarantine or hold status so planning, picking and shipping ignore it until a disposition is recorded.

### Is an NCR the same as a deviation or a concession?

**Answer:** No. A deviation or concession is permission to accept or ship product that does not meet requirements. It is one possible outcome of an NCR disposition, not the NCR itself.

## Search terms

what is an NCR, non-conformance report meaning, NCR in manufacturing, NCR disposition use as is rework scrap, nonconforming material process, NCR vs CAPA, NCR ERP quality module

---