# APQP Plan Template with Filled Example

> Source: https://netray.co/tools/apqp-plan-template
> Publisher: Netray (netray.co), AI and integration engineering for ERP and manufacturing systems.
> Section: Free Tools

## Short answer

Fill in your program details and get a clean APQP plan document with phases, deliverables, owners, gate reviews and a risk register.

## Category

quality

## Industry

Automotive

## Audience

- Program manager
- Quality engineer
- Supplier quality

## Tool

**Kind:** template

**Output:** document

**Fields:**

#### Supplier name

**Key:** company

**Type:** text

**Default:** Acme Precision Components Ltd

#### Customer

**Key:** customer

**Type:** text

**Default:** Example Automotive OEM

#### Program / project name

**Key:** program

**Type:** text

**Default:** Gen 3 Steering Bracket

#### Part number and revision

**Key:** part_no

**Type:** text

**Default:** SB-48213 Rev C

#### Program manager

**Key:** pm

**Type:** text

**Default:** A. Sharma

#### Quality lead

**Key:** quality_lead

**Type:** text

**Default:** R. Patel

#### Kickoff date

**Key:** kickoff

**Type:** date

**Default:** 2026-11-02

#### PPAP submission target

**Key:** ppap_date

**Type:** date

**Default:** 2027-03-15

#### Start of production (SOP)

**Key:** sop

**Type:** date

**Default:** 2027-05-03

#### PPAP submission level

**Key:** level

**Type:** select

**Options:**

- Level 1
- Level 2
- Level 3
- Level 4
- Level 5

**Default:** Level 3

#### Scope and key requirements

**Key:** scope

**Type:** textarea

**Default:** Machined aluminium bracket, annual volume 180,000 pcs. Two special characteristics (bore diameter, flange flatness). Customer requires PPAP Level 3 and a run-at-rate before SOP.

#### Top program risks

**Key:** risks

**Type:** textarea

**Default:** 1. Fixture lead time may delay run-at-rate.
2. Single-source casting supplier.
3. New CMM program needed for flatness.

**Blocks:**

#### APQP Plan

**Body:** Supplier: {{company}}
Customer: {{customer}}
Program: {{program}}
Part: {{part_no}}
Program manager: {{pm}}
Quality lead: {{quality_lead}}
PPAP level: {{level}}

#### Scope and key requirements

**Body:** {{scope}}

#### Key dates

**Table:**

**Columns:**

- Milestone
- Target date

**Rows:**

**0:** Program kickoff

**1:** {{kickoff}}

**0:** PPAP submission

**1:** {{ppap_date}}

**0:** Start of production

**1:** {{sop}}

#### Phase deliverables

**Table:**

**Columns:**

- Phase
- Key deliverables
- Owner
- Status

**Rows:**

**0:** 1 Plan and define

**1:** Voice of customer, design goals, preliminary BOM, preliminary process flow, preliminary special characteristics, product assurance plan

**2:** {{pm}}

**3:** Open

**0:** 2 Product design and development

**1:** DFMEA, design verification, drawings and specifications, gauge and equipment requirements, team feasibility commitment

**2:** Engineering

**3:** Open

**0:** 3 Process design and development

**1:** Process flow, floor plan, PFMEA, pre-launch control plan, MSA plan, preliminary capability study plan, packaging specification

**2:** {{quality_lead}}

**3:** Open

**0:** 4 Product and process validation

**1:** Production trial run, MSA, capability study, PPAP submission, production control plan, quality planning sign-off

**2:** {{quality_lead}}

**3:** Open

**0:** 5 Feedback, assessment, corrective action

**1:** Reduced variation, customer satisfaction review, delivery review, lessons learned

**2:** {{pm}}

**3:** Open

#### Gate reviews

**Table:**

**Columns:**

- Gate
- Entry criteria
- Decision
- Date

**Rows:**

**0:** G1 Program approval

**1:** Feasibility commitment signed

**0:** G2 Design freeze

**1:** DFMEA closed, drawings released

**0:** G3 Process readiness

**1:** PFMEA and control plan approved, tooling ordered

**0:** G4 PPAP submission

**1:** Trial run data, MSA and capability reviewed

**0:** G5 SOP release

**1:** PSW approved, containment plan agreed

#### Top risks

**Body:** {{risks}}

#### Approvals

**Signatures:**

- Program manager
- Quality manager
- Engineering manager
- Customer representative

**Notes:** This is a generic plan structure aligned with the five APQP phases. Check your customer's own APQP and gate requirements, and adjust owners and dates to your program.

## Content

**Intro:** This APQP plan template turns the five Advanced Product Quality Planning phases into a single document you can send to your customer or review in a kickoff. It is pre-filled with a realistic example so you can see how a finished plan reads.

**Sections:**

#### How to use the template

**Body:** Replace the example values with your own program name, part number, owners and dates. The phase table and gate table are pre-built, so you only edit the cells that matter. Export to Word if you want to add drawings or customer logos, to PDF to send for approval, or to Excel to track it as a live plan. Review it at the kickoff with design, tooling, quality and purchasing in the room.

#### What the five phases cover

**Body:** APQP is a structured way to plan a new product so quality problems are prevented, not found late. The phases run from planning and defining the program, through design and process development, to validation and then feedback and corrective action after launch. PPAP, the production part approval process, is the evidence package that closes phase 4.

**Bullets:**

- Phase 1: customer needs, design goals, preliminary special characteristics
- Phase 2: DFMEA, design verification, equipment and gauge requirements
- Phase 3: process flow, PFMEA, control plan, MSA plan
- Phase 4: trial run, capability, PPAP submission
- Phase 5: variation reduction and lessons learned

#### Common mistakes

**Body:** The most common failure is treating APQP as paperwork completed right before PPAP. A plan only helps if gates have real entry criteria and owners. Another is missing the long-lead items: fixtures, gauges and CMM programs often decide whether you hit the run-at-rate date. Put those on the plan in phase 2 and review them at every gate. Also keep the plan version controlled so the customer and your team see the same dates.

**Cta:** If your APQP and PPAP data lives in your ERP and quality system, Netray can add a private AI layer on top that answers status questions from your own data, on-prem if needed.

**Faq:**

#### What is an APQP plan?

**Answer:** An APQP plan is the schedule and responsibility document for Advanced Product Quality Planning. It lists the five phases, the deliverables in each, who owns them, the target dates and the gate reviews, so a new product launches with quality built in.

#### Does the AIAG manual require this exact format?

**Answer:** No. The AIAG APQP manual describes the phases and expected outputs but not one mandatory form. Many customers accept any clear plan that covers the phases, owners and timing. Always check your customer-specific requirements before you submit.

#### How is APQP different from PPAP?

**Answer:** APQP is the whole planning process from concept to launch. PPAP is the set of evidence you submit to show the production process can consistently meet requirements. PPAP is one deliverable inside APQP phase 4.

#### Can I use this outside automotive?

**Answer:** Yes. Aerospace suppliers use similar planning under AS9145, and any supplier launching a new part can use the same phase structure. Adjust the deliverables to match the standard or customer you work with.

## Search terms

apqp plan template, apqp form template, apqp format template, apqp example template, apqp forms and templates, apqp project plan, advanced product quality planning template, apqp plan example

---
Talk to an engineer: https://netray.co/contact?intent=erp_ai | Machine catalog: https://netray.co/agent/catalog.json
