# Compressed Air Leak Cost Calculator

> Source: https://netray.co/tools/compressed-air-leak-cost-calculator
> Publisher: Netray (netray.co), AI and integration engineering for ERP and manufacturing systems.
> Section: Free Tools

## Short answer

Convert a leak rate into lost compressor energy and annual cost, then test the payback of an ultrasonic leak survey and repair.

## Category

maintenance

## Industry

Process and Discrete Manufacturing

## Audience

- Maintenance manager
- Utilities engineer
- Energy manager

## Tool

**Kind:** calculator

**Currency:** $

**Inputs:**

#### Average air demand (compressor output)

**Key:** cap_cfm

**Type:** number

**Default:** 1000

**Min:** 1

**Step:** 10

**Unit:** cfm

**Help:** Use the metered average flow, not the nameplate capacity.

#### Leakage as share of output

**Key:** leak_pct

**Type:** slider

**Default:** 25

**Min:** 0

**Max:** 60

**Step:** 1

**Unit:** %

**Help:** Surveys often find 20 to 30 percent in plants with no leak program.

#### Specific power

**Key:** spec_kw

**Type:** number

**Default:** 18

**Min:** 5

**Max:** 40

**Step:** 0.5

**Unit:** kW per 100 cfm

**Help:** Roughly 16 to 22 for a well loaded compressor at about 100 psig.

#### Compressor running hours per year

**Key:** hours

**Type:** number

**Default:** 7000

**Min:** 0

**Max:** 8760

**Step:** 100

**Unit:** h

#### Electricity price

**Key:** rate

**Type:** number

**Default:** 0.09

**Min:** 0

**Step:** 0.01

**Unit:** per kWh

#### Share of leakage repaired

**Key:** fix_pct

**Type:** slider

**Default:** 80

**Min:** 0

**Max:** 100

**Step:** 5

**Unit:** %

#### Survey and repair program cost

**Key:** program

**Type:** number

**Default:** 12000

**Min:** 0

**Step:** 500

**Help:** Detector, labour and parts.

**Outputs:**

#### Leak flow

**Key:** leak_cfm

**Expr:** cap_cfm * leak_pct / 100

**Format:** decimal

#### Power wasted by leaks

**Key:** leak_kw

**Expr:** leak_cfm * spec_kw / 100

**Format:** decimal

#### Annual energy lost

**Key:** leak_kwh

**Expr:** leak_kw * hours

**Format:** integer

#### Annual cost of leaks

**Key:** leak_cost

**Expr:** leak_kwh * rate

**Format:** currency

**Primary:** true

#### Annual saving after repairs

**Key:** saved

**Expr:** leak_cost * fix_pct / 100

**Format:** currency

**Primary:** true

#### Simple payback

**Key:** payback

**Expr:** if(gt(saved, 0), program / saved * 12, 0)

**Format:** months

**Chart:**

#### Annual leak cost versus leakage share

**Type:** line

**X:** leak_pct

**From:** 0

**To:** 50

**Steps:** 25

**Series:**

- leak_cost
- saved

**Disclaimer:** Specific power varies with compressor type, load and control method, so use measured kW and cfm if you can. Savings assume demand falls and compressors unload or stop accordingly.

## Content

**Intro:** Compressed air is one of the most expensive utilities in a plant and a large part of it can simply leak away. This calculator turns a leakage share into kilowatts, kilowatt hours and money so you can justify a leak program.

**Sections:**

#### How to use the calculator

**Body:** Start with the average air flow from a flow meter or from compressor load logs. Estimate leakage as a percentage of output, either from a shutdown test where you run the compressor with all production off, or from a survey count. Enter the specific power of your compressors in kW per 100 cfm, your running hours and your tariff. The result shows leak flow, wasted power and annual cost. Enter the repair program cost and the share you expect to fix to see payback.

**Bullets:**

- Shutdown test: leak flow equals compressor output with production stopped
- Ultrasonic detector surveys find individual leak locations
- Tag each leak and log the repair in your CMMS
- Re-survey every six to twelve months

#### The method behind the numbers

**Body:** Leak flow is output times leakage share. Power is leak flow multiplied by specific power, since a typical industrial compressor needs roughly 0.16 to 0.22 kW per cfm delivered. Energy is power times operating hours, and cost is energy times tariff. The result is a simple estimate. In reality compressors run partly unloaded, and saving depends on whether the control system actually reduces compressor output when leaks are closed.

#### Making savings real

**Body:** Fixing leaks only saves energy if the compressors respond. With a fixed speed machine on load unload control, reduced demand means more unloaded time, which still draws some power. Variable speed compressors or sequencing controls turn lower demand into larger savings. Lowering header pressure after repairs gives an extra saving, since each reduction in discharge pressure cuts power by roughly a percent per few psi.

#### Common mistakes

**Body:** Treating nameplate capacity as actual flow overstates the cost. Another is repairing leaks without tagging and tracking them, so they return. Counting artificial demand, such as open blowoffs, as leaks mixes two different problems. Finally, many plants forget that leaks also drop pressure at the point of use and may encourage operators to raise the setpoint, which increases the waste further.

**Cta:** If you want leak tags, repair work orders and compressor energy data tied together in your ERP or CMMS, Netray can help scope that reporting.

**Faq:**

#### How much does one compressed air leak cost?

**Answer:** It depends on hole size and pressure. A leak of around 10 cfm wastes about 1.8 kW at 18 kW per 100 cfm, which is roughly 12,600 kWh a year at 7,000 hours, or about 1,100 at 0.09 per kWh. Use the calculator for a plant total.

#### What percentage of compressed air is typically lost to leaks?

**Answer:** Plants without a leak program commonly lose 20 to 30 percent of output, and well managed plants can keep losses below 10 percent. Your own number is best found by a shutdown test or a flow meter reading during non-production time.

#### How do I find compressed air leaks?

**Answer:** The most practical tool is an ultrasonic leak detector, which hears the high frequency noise of escaping air even in a loud plant. Soapy water works for small accessible joints. Tag each leak, record its estimated size and track repairs.

#### How often should I survey for leaks?

**Answer:** Many plants survey every six to twelve months, and more often if leakage returns quickly. Fittings, hoses, quick couplings and filter regulators lubricators are the usual sources. Track the leakage percentage over time to see if the program holds.