# Equipment FAT Checklist Template

> Source: https://netray.co/tools/equipment-fat-checklist-template
> Publisher: Netray (netray.co), AI and integration engineering for ERP and manufacturing systems.
> Section: Free Tools

## Short answer

A factory acceptance test checklist for custom machinery covering documents, mechanical, electrical, safety, controls and run-off tests before shipment.

## Category

industry-templates

## Industry

Industrial Machinery

## Audience

- Test engineer
- OEM project manager
- Customer quality engineer
- Buyer

## Tool

**Kind:** checklist

**Scoring Note:** Mark each item as passed, or leave it open. Any open critical item should block release for shipment unless the customer signs a documented waiver.

**Groups:**

#### Documents and readiness

**Items:**

**Text:** Approved FAT procedure and acceptance criteria are agreed with the customer in writing

**Critical:** true

Machine specification and contract scope are available to the test team

Electrical drawings, pneumatic and hydraulic diagrams are released at the current revision

Bill of materials matches the as-built machine

Test samples, product or gauge materials are on hand

Measurement equipment calibration is current and recorded

#### Mechanical inspection

**Items:**

Frame, base and levelling feet are inspected for welds, finish and dimensions

Fasteners are torqued and marked per assembly instruction

Lubrication points are filled and labelled

Guards, doors and covers fit and open without interference

Moving axes travel the full stroke without binding or unusual noise

**Text:** Key dimensions are checked against the layout drawing

**Critical:** true

#### Electrical, pneumatic and hydraulic

**Items:**

**Text:** Insulation resistance and ground continuity are measured and recorded

**Critical:** true

Main supply voltage, phase sequence and frequency match the specification

Panel wiring, labels and terminal markings agree with drawings

Air supply pressure, leaks and regulator settings are checked

Hydraulic pressure, relief setting and leak check are recorded

Motor current and drive parameters are logged for each axis

#### Safety functions

**Items:**

**Text:** Emergency stop circuits stop all hazardous motion and require reset

**Critical:** true

**Text:** Door interlocks and light curtains stop motion when opened or broken

**Critical:** true

**Text:** Safe stopping time or distance is measured and recorded

**Critical:** true

Lockout points and stored energy release are verified

Warning labels, safety signs and pictograms are fitted

Safety function test results match the risk assessment performance levels

#### Controls and software

**Items:**

**Text:** PLC, HMI and drive software versions are recorded and backed up

**Critical:** true

All operating modes are demonstrated: manual, setup and automatic

Alarm and fault messages are triggered and displayed correctly

Recipe or part number changeover is demonstrated

User levels and passwords function as specified

Communication to line equipment, MES or ERP is tested where in scope

#### Performance run-off and close-out

**Items:**

**Text:** Cycle time is demonstrated against the contracted rate

**Critical:** true

**Text:** Capability or yield run is completed on the agreed sample size

**Critical:** true

Product quality checks meet drawing tolerances

**Text:** Punch list of open items is written, owned and dated

**Critical:** true

Spare parts list, manuals and training plan are confirmed

Crating, shipping and rigging instructions are reviewed

**Text:** FAT report is signed by supplier and customer representatives

**Critical:** true

## Content

**Intro:** A factory acceptance test proves, at the builder's site, that the machine meets the contract before it is shipped and installed. This checklist gives you a structured set of checks to adapt to your machine and the customer procedure.

**Sections:**

#### How to use this checklist

**Body:** Treat the checklist as a starting skeleton for the FAT procedure, not a replacement for it. Before the test, agree the acceptance criteria with the customer: cycle time, yield, tolerances, safety performance and what counts as a pass. During the test, tick items as they are demonstrated and note readings beside them. Items marked critical should stop release if they fail. At close-out, convert every open item into a punch list entry with an owner and a due date, and have both parties sign the report.

**Bullets:**

- Share the procedure with the customer at least a week before the test.
- Record serial numbers and revisions of what is being tested.
- Photograph nameplates, panels and safety labels.
- Do not change software between test and shipment without a change record.

#### What a FAT is and is not

**Body:** A FAT verifies conformance to specification under controlled conditions. It is not a substitute for the site acceptance test, where the machine runs with real product, utilities and operators, and it is not a design validation. The practical value of a FAT is cost: a defect found in your shop costs hours, while the same defect found after installation costs travel, downtime and reputation. Many contracts release a payment milestone on FAT completion, so the quality of the record matters commercially as well as technically.

#### Performance run-off design

**Body:** Define the run-off before the test: sample size, product, duration and what is counted as a failure. For a throughput claim, run long enough to include normal micro-stops, not a best-minute burst. For a quality claim, use enough parts to support the capability index you are promising; a handful of parts cannot demonstrate a Cpk of 1.67. Record any adjustment made during the run, because the customer will want to know whether the machine holds its setting or needs operator help.

#### Common mistakes

**Body:** Typical FAT failures are not mechanical. They are an unagreed acceptance criterion, test material that does not represent production product, documents still at the wrong revision, and safety verification left until the last day. Another common problem is accepting a long punch list without dates; items without owners tend to arrive at site as the customer's problem. Keep the punch list in a tracker and review it in your next project meeting until closed.

**Cta:** If you want FAT results, punch list items and serial-level records linked to the project in your ERP, Netray can help set that up as a controlled workflow.

**Faq:**

#### Who should attend a FAT?

**Answer:** At minimum the supplier test engineer and project manager. The customer typically sends a quality or operations representative and sometimes a safety specialist. Controls and mechanical engineers should be on call. Agree attendance in the contract, since witnessed tests need travel and schedule planning.

#### What happens if the machine fails the FAT?

**Answer:** The failures are logged, root cause is found, and the failed test is repeated after correction. Contracts usually say whether a partial retest is allowed. Minor failures can be moved to a punch list with customer agreement, but critical safety or performance failures normally require a full retest.

#### How is a FAT different from a SAT?

**Answer:** A FAT happens at the supplier site before shipment, with test conditions the supplier controls. A SAT happens at the customer site after installation, with real utilities, product and operators. The SAT confirms the machine still performs after transport and in its working environment.

#### Do I need a separate checklist per machine?

**Answer:** Yes for items that depend on machine features. Keep the group structure and critical items, then add or remove lines for your equipment, such as robot calibration, vision verification or vacuum leak rates. Version the template so each project records which revision was used.

## Search terms

FAT checklist template, factory acceptance test checklist, equipment FAT procedure, machine FAT template excel, factory acceptance test protocol, FAT report format, pre shipment machine inspection checklist, customer witness FAT checklist

---