# ERP User Acceptance Test (UAT) Script Template

> Source: https://netray.co/tools/eu-erp-user-acceptance-test-script-template
> Publisher: Netray (netray.co), AI and integration engineering for ERP and manufacturing systems.
> Section: Free Tools

## Short answer

A structured UAT script for one end-to-end business scenario, such as order to cash or make to stock, with steps, expected results and sign-off lines.

## Category

erp-operations

## Region

Europe

## Industry

Discrete Manufacturing

## Audience

- ERP key user
- Test lead
- ERP project manager

## Tool

**Kind:** template

**Output:** document

**Fields:**

#### Project

**Key:** project

**Type:** text

**Default:** ERP Replacement Programme

#### Scenario ID

**Key:** scenario_id

**Type:** text

**Default:** UAT-PRD-004

#### Scenario name

**Key:** scenario

**Type:** text

**Default:** Make to order with subcontract operation

#### Tester

**Key:** tester

**Type:** text

**Default:** M. Schmidt

#### Test date

**Key:** date

**Type:** date

**Default:** 2026-11-24

#### Environment

**Key:** environment

**Type:** select

**Options:**

- Test
- Quality
- Pre-production

**Default:** Quality

#### Preconditions and test data

**Key:** precond

**Type:** textarea

**Default:** Item FG-2210 with released BOM and routing. Customer 100245 active with credit limit set. Subcontractor 300118 with approved status.

#### Overall result

**Key:** result

**Type:** select

**Options:**

- Passed
- Passed with defects
- Failed
- Blocked

**Default:** Passed with defects

**Blocks:**

#### UAT Script

**Body:** Project: {{project}}
Scenario: {{scenario_id}} {{scenario}}
Tester: {{tester}}
Date: {{date}}
Environment: {{environment}}

#### Preconditions and test data

**Body:** {{precond}}

#### Test steps

**Table:**

**Columns:**

- Step
- Action
- Expected result
- Actual result
- Pass / Fail
- Defect ref

**Rows:**

**0:** 1

**1:** Enter sales order for 40 pcs of FG-2210

**2:** Order saved, price and delivery date proposed

**0:** 2

**1:** Run planning for the item

**2:** Planned production order and subcontract purchase request created

**0:** 3

**1:** Release production order

**2:** Operations and material reservations visible

**0:** 4

**1:** Receive subcontract goods

**2:** Stock posted, subcontract cost allocated

**0:** 5

**1:** Post production completion

**2:** Finished goods in stock, WIP cleared

**0:** 6

**1:** Ship and invoice

**2:** Delivery note and invoice produced, VAT correct

#### Defects found

**Table:**

**Columns:**

- Ref
- Description
- Severity
- Owner
- Status

**Rows:**

**0:** D1

**0:** D2

#### Outcome

**Body:** Overall result: {{result}}

#### Sign-off

**Signatures:**

- Tester
- Process owner
- Test lead

**Notes:** A starting-point script. Replace the example steps with your own process and use one script per scenario so results can be tracked separately.

## Content

**Intro:** User acceptance testing proves that the business can run its real processes in the new ERP. A script gives every tester the same steps, expected results and a place to record what actually happened, which is what turns opinions into evidence at sign-off.

**Sections:**

#### How to use the script

**Body:** Write one script per end-to-end scenario, for example quote to cash, procure to pay, make to stock, subcontracting or period close. Set the preconditions and test data first, since most failed tests in UAT are caused by missing data rather than defects. Testers run each step, record the actual result, mark pass or fail and raise a defect reference for failures. The process owner signs after reviewing the open defects.

**Bullets:**

- Use realistic data from the migrated set, not made-up records
- Test with the actual end users, not only the project team
- Log every failure with a reference, even small ones
- Retest fixed defects in the same script version

#### Scenarios for a manufacturing ERP

**Body:** At least cover sales order entry with pricing and credit check, material planning and purchase proposals, production order release and backflushing, subcontracting, goods receipt with incoming inspection, shipping with documents, invoicing with correct VAT treatment, intercompany if relevant and month-end close. Include negative paths such as a rejected lot or an order change after release, because these expose real gaps.

#### Defect severity and exit criteria

**Body:** Agree severity levels before testing starts. A common scheme is critical for no workaround, high for a workaround that is not acceptable at volume, medium for an acceptable workaround and low for cosmetic issues. Typical exit criteria are no open critical or high defects, a pass rate above an agreed threshold on must-have scenarios and sign-off from each process owner.

#### Common mistakes

**Body:** Testing too late leaves no time to fix findings. Using the consultant as tester hides usability problems that users will meet on day one. Another trap is running a happy-path only test. Finally, do not close defects verbally; track every defect to a retest and a recorded result.

**Cta:** If you want help turning your process descriptions into scripts for your ERP, we can draft a first set for your team to correct. Optional.

**Faq:**

#### How many UAT scenarios does a mid-size plant need?

**Answer:** A typical single-plant project ends up with 25 to 60 scenarios across sales, purchasing, planning, production, inventory, quality and finance. Multi-entity or highly regulated environments need more. The test of coverage is whether every critical business process has at least one scenario.

#### Who should execute the UAT scripts?

**Answer:** The business users who will do the work after go-live, supported by key users who know the new system. Consultants should observe and help but not drive. Their presence changes what gets noticed.

#### Is UAT the same as system integration testing?

**Answer:** No. Integration testing checks that the systems and interfaces work technically. UAT checks that the process works for the business with its own data and roles. Both are needed, and UAT should start only after integration testing is stable.

#### What if a defect cannot be fixed before go-live?

**Answer:** Record an agreed workaround, an owner and a target fix date, and obtain explicit acceptance from the process owner. It becomes a known issue in the go-live decision, not a surprise on the first day.

## Search terms

erp uat test script template, user acceptance testing template erp, erp test case template, uat sign off template, erp test script excel, erp acceptance test plan

---