# Injection Mold Qualification Report Template

> Source: https://netray.co/tools/injection-mold-qualification-report-template
> Publisher: Netray (netray.co), AI and integration engineering for ERP and manufacturing systems.
> Section: Free Tools

## Short answer

A fill-in IQ, OQ and PQ style report for qualifying a new or transferred injection mold, with process window and capability tables.

## Category

quality

## Industry

Plastics and Injection Molding

## Audience

- Quality engineer
- Process engineer
- Validation engineer
- Supplier quality

## Tool

**Kind:** template

**Output:** document

**Fields:**

#### Company name

**Key:** company

**Type:** text

**Default:** Acme Plastics Ltd

#### Mold ID

**Key:** mold_id

**Type:** text

**Default:** M-2041

#### Part number and revision

**Key:** part_no

**Type:** text

**Default:** PN-48213 Rev C

#### Number of cavities

**Key:** cavities

**Type:** text

**Default:** 4

#### Resin and grade

**Key:** resin

**Type:** text

**Default:** ABS, general purpose, natural

#### Press ID and clamp

**Key:** press

**Type:** text

**Default:** Press 12, 200 metric ton

#### Qualification date

**Key:** date

**Type:** date

**Default:** 2026-10-20

#### Reason for qualification

**Key:** reason

**Type:** select

**Options:**

- New mold
- Mold transfer to a new press
- Mold transfer to a new site
- After major repair
- Resin change

**Default:** New mold

#### Scope and acceptance criteria

**Key:** scope

**Type:** textarea

**Default:** Qualify the mold and process to produce parts meeting drawing requirements over the defined process window. Capability requirement: Cpk of 1.33 or higher on critical dimensions.

#### Conclusion

**Key:** conclusion

**Type:** textarea

**Default:** Mold and process are qualified for production within the validated process window, subject to the open actions listed.

**Blocks:**

#### Injection Mold Qualification Report

**Body:** Company: {{company}}
Mold ID: {{mold_id}}
Part: {{part_no}}
Cavities: {{cavities}}
Resin: {{resin}}
Press: {{press}}
Date: {{date}}
Reason: {{reason}}

#### 1. Scope and acceptance criteria

**Body:** {{scope}}

#### 2. Installation qualification (IQ)

**Table:**

**Columns:**

- Item
- Requirement
- Result
- Pass/Fail

**Rows:**

**0:** Mold drawing and build records on file

**1:** Match current revision

**0:** Mold fits press (tie bars, daylight, locating ring)

**1:** Per press datasheet

**0:** Water circuits flow and pressure test

**1:** No leaks, flow per spec

**0:** Hot runner controller and zone wiring

**1:** All zones reach setpoint

**0:** Ejector, slides and core pulls function

**1:** No binding, full stroke

**0:** Calibration of key equipment and gauges

**1:** In date

**0:** Resin lot and drying records

**1:** Per supplier data sheet

#### 3. Operational qualification (OQ) - process window

**Table:**

**Columns:**

- Parameter
- Low setting
- Nominal
- High setting
- Parts acceptable?

**Rows:**

**0:** Melt temperature

**0:** Mold temperature

**0:** Injection speed or time

**0:** Hold pressure and time

**0:** Cooling time

**0:** Shot size / cushion

#### 4. Performance qualification (PQ) - capability run

**Table:**

**Columns:**

- Critical characteristic
- Specification
- Sample size
- Mean
- Std dev
- Cpk

**Rows:**

**0:** Characteristic 1

**0:** Characteristic 2

**0:** Characteristic 3

**0:** Weight

#### 5. Cavity-to-cavity comparison

**Table:**

**Columns:**

- Cavity
- Part weight
- Key dimension
- Cosmetic result
- Note

**Rows:**

**0:** 1

**0:** 2

**0:** 3

**0:** 4

#### 6. Conclusion

**Body:** {{conclusion}}

#### 7. Approvals

**Signatures:**

- Process engineer
- Quality engineer
- Toolroom
- Production manager
- Customer approval, if required

**Notes:** A starting-point template, not a regulatory form. Your customer, quality system or industry (for example medical, automotive or aerospace) may require specific forms, sampling plans and validation protocols. Adjust the table rows to your part and process.

## Content

**Intro:** Before a new or transferred mold goes into production, a molder needs documented evidence that the tool, press and process make good parts consistently. This template structures that evidence as installation, operational and performance qualification.

**Sections:**

#### How to use the template

**Body:** Enter the mold, part, resin and press details, state why you are qualifying, and write the acceptance criteria up front. Print or export the report to Word to add rows for your characteristics and attach measurement data. Complete the IQ table first, then run the process window study for OQ, and finish with a production-length run for PQ. Signatures close the report. Save one per mold and per qualification event.

#### IQ, OQ and PQ explained

**Body:** Installation qualification checks that the mold, press, auxiliaries and instruments are set up as intended and in calibration. Operational qualification finds the process window: low, nominal and high settings for the main variables, with parts evaluated at each corner. Performance qualification proves that at nominal settings the process makes capable parts over a run long enough to see normal variation, often judged by Cpk on the critical characteristics. The wording comes from validation practice in regulated industries but works well for any demanding molded part.

#### Choosing sample sizes and criteria

**Body:** Use your customer's requirements first. Without one, many shops use capability studies of at least 30 consecutive parts per cavity or a stratified sample across several hours, and a target Cpk of 1.33 for critical dimensions, higher for safety characteristics. Measure cavity-to-cavity variation separately, because a multi-cavity tool is several processes at once. Keep gauge repeatability in mind: if the measurement system is poor, the capability result is unreliable.

**Bullets:**

- State acceptance criteria before the trial.
- Record the settings used for every sample.
- Include lot numbers of resin and colorant.
- Measure after the part has stabilized.

#### Common mistakes

**Body:** Qualifying at a single set of conditions leaves the plant blind to how the process behaves when conditions drift. Measuring parts immediately after molding without allowing time to stabilize can show dimensions that change later, especially for nylon. Skipping a transfer qualification when a mold moves to another press is common and risky, since different presses have different screw, nozzle and control behavior. Also remember to freeze and document the validated settings on the set-up sheet.

**Cta:** If you want qualification records and approved process settings tied to the mold and part master in your ERP, we can help design that. Ask for a short walk-through.

**Faq:**

#### What is mold qualification in injection molding?

**Answer:** It is documented evidence that a mold and process, run on a defined press and resin, make parts that meet specification consistently. It typically covers installation, process window and a capability run.

#### When must a mold be re-qualified?

**Answer:** Common triggers are a new mold, a transfer to another press or site, a major repair or modification, and a change in resin grade or supplier. Your customer or quality system may add others.

#### What Cpk do I need for a molded part?

**Answer:** Many customers ask for 1.33 or higher on critical characteristics, and some ask for 1.67. Always use the customer requirement where one exists.

#### Is this the same as PPAP?

**Answer:** No. PPAP is a customer approval package, mostly used in automotive. A mold qualification report can be one input to PPAP, supplying process window and capability evidence.

## Search terms

mold qualification checklist, injection mold validation template, IQ OQ PQ injection molding, mold qualification report, process validation molding, mold trial report template, mold transfer qualification

---