# Oracle Fusion SCM Implementation Statement of Work Template

> Source: https://netray.co/tools/oracle-fusion-scm-implementation-sow-template
> Publisher: Netray (netray.co), AI and integration engineering for ERP and manufacturing systems.
> Section: Free Tools

## Short answer

A generic statement of work outline for an Oracle Fusion SCM implementation with scope, phases, assumptions, responsibilities and acceptance.

## Category

oracle

## Erp

Oracle Fusion Cloud SCM

## Audience

- Project manager
- Oracle Cloud consultant
- Procurement
- Delivery partner

## Tool

**Kind:** template

**Output:** document

**Fields:**

#### Client

**Key:** client

**Type:** text

**Default:** Acme Precision Ltd

#### Implementation partner

**Key:** provider

**Type:** text

**Default:** Example Consulting LLC

#### Effective date

**Key:** date

**Type:** date

**Default:** 2026-11-02

#### In-scope modules

**Key:** modules

**Type:** textarea

**Default:** Inventory Management, Procurement, Order Management, Manufacturing, Cost Management

#### Sites in scope

**Key:** sites

**Type:** text

**Default:** Two manufacturing plants and one distribution center

#### Target go-live

**Key:** golive

**Type:** date

**Default:** 2027-04-05

#### Commercial model

**Key:** fee_model

**Type:** select

**Options:**

- Fixed price by phase
- Time and materials with cap
- Time and materials

**Default:** Fixed price by phase

#### Mock data loads

**Key:** mock_loads

**Type:** number

**Default:** 3

#### Client resources committed

**Key:** client_team

**Type:** textarea

**Default:** Project manager at 100 percent, one functional lead per module at 50 percent, one data owner per object.

#### Out of scope

**Key:** outofscope

**Type:** textarea

**Default:** Custom extensions not listed in the signed fit gap, legacy data archiving, end user classroom training beyond train-the-trainer.

**Blocks:**

#### Statement of Work: Oracle Fusion Cloud SCM Implementation

**Body:** Client: {{client}}
Implementation partner: {{provider}}
Effective date: {{date}}
Commercial model: {{fee_model}}

#### 1. Purpose and scope

**Body:** This statement of work describes services to implement Oracle Fusion Cloud SCM for {{client}}.

In-scope modules: {{modules}}

Sites in scope: {{sites}}

Target go-live: {{golive}}

#### 2. Phases and deliverables

**Table:**

**Columns:**

- Phase
- Key activities
- Deliverables

**Rows:**

**0:** Initiate

**1:** Kickoff, governance, environment access

**2:** Project plan, RAID log

**0:** Design

**1:** Process workshops, fit gap, security design

**2:** Signed fit gap and solution design

**0:** Build

**1:** Configuration, extensions, integrations

**2:** Configured test environment

**0:** Data

**1:** Mapping, cleansing, {{mock_loads}} mock loads

**2:** Load results and reconciliations

**0:** Test

**1:** System test and user acceptance test

**2:** Signed test scripts

**0:** Deploy

**1:** Cutover rehearsal, go-live, hypercare

**2:** Cutover runbook, hypercare exit report

#### 3. Client responsibilities

**Body:** {{client_team}}

The client provides timely decisions, access to subject matter experts and ownership of source data quality.

#### 4. Out of scope

**Body:** {{outofscope}}

Anything not listed above is handled through change control.

#### 5. Assumptions

**Body:** Oracle subscriptions and environments are provided by the client. Source data is available in a structured form by the agreed date. Scope changes follow the change control procedure.

#### 6. Acceptance

**Body:** Each deliverable is reviewed within an agreed number of business days. Acceptance is recorded in writing. Deliverables not rejected with reasons in that period are treated as accepted.

#### Approvals

**Signatures:**

- Client sponsor
- Implementation partner
- Client project manager

**Notes:** This is a starting point, not legal advice. Have counsel review it and align it with your master services agreement before signing.

## Content

**Intro:** Most Oracle Fusion SCM overruns trace back to an unclear statement of work. This fill-in outline captures scope, phases, responsibilities and acceptance in plain terms so both sides agree before work starts.

**Sections:**

#### How to use the template

**Body:** Enter the client, partner, modules, sites and commercial model. Review the phase table and edit the deliverables to match what you will actually deliver. List client responsibilities as concretely as the provider's, because delays on the client side are the usual source of disputes. Export to Word to merge into your master agreement.

#### Scope clarity

**Body:** List modules, sites, legal entities, languages and integrations. State how many mock loads, test cycles and training sessions are included, since these drive effort. Write out of scope as clearly as in scope. If extensions are expected, reference the signed fit gap as the baseline rather than describing them loosely.

**Bullets:**

- Name modules and sites
- Count loads and test cycles
- Link extensions to the fit gap
- List integrations individually

#### Commercial models

**Body:** Fixed price by phase gives cost certainty but needs precise scope and change control. Time and materials with a cap shares risk and suits uncertain scope. Pure time and materials is flexible but needs strong governance. Whatever model you choose, define how change requests are raised, estimated and approved.

#### Common mistakes

**Body:** Leaving acceptance criteria vague, forgetting data migration effort, and not committing client resources by role and percentage. Another is describing the target process rather than the services. Keep the statement of work about what the partner does and delivers, and use the solution design for how the system will work.

**Cta:** If you want an independent view of an SCM statement of work, we can review scope, assumptions and data migration effort against your legacy ERP.

**Faq:**

#### Is this a legal contract?

**Answer:** No. It is a generic outline to help structure scope discussions. It is not legal advice. Have counsel review the final document and align it with your master agreement, liability terms and local law.

#### How detailed should the deliverables be?

**Answer:** Detailed enough that someone can tell whether each was delivered. Name the document or outcome, the format and the approver. Vague deliverables such as 'configuration' become disputes at acceptance time.

#### Who is responsible for data quality?

**Answer:** The client owns the source data and its correctness. The partner supplies mapping, tools and load support. State this clearly with a named data owner per object so errors do not become scope disputes.

#### How are changes handled?

**Answer:** Through a written change request that describes the change, the effect on cost and schedule, and the approver. Nothing outside scope should start without approval, even for small items.

## Search terms

oracle fusion implementation sow template, oracle cloud statement of work example, erp implementation sow template, oracle scm project scope document, oracle fusion project assumptions, erp statement of work word, oracle cloud implementation scope

---