# Prophet 21 Order to Cash Go-Live Test Checklist

> Source: https://netray.co/tools/prophet-21-order-to-cash-go-live-test-checklist
> Publisher: Netray (netray.co), AI and integration engineering for ERP and manufacturing systems.
> Section: Free Tools

## Short answer

A test script outline for the order-to-cash cycle in Prophet 21 before cutover, from quote to cash application.

## Category

epicor

## Erp

Epicor Prophet 21

## Industry

Wholesale Distribution

## Audience

- Project manager
- P21 administrator
- Finance lead
- Customer service lead

## Tool

**Kind:** checklist

**Groups:**

#### Quote and order entry

**Items:**

**Text:** Create a quote for a stock item and convert it to an order

**Critical:** true

Enter an order for a non-stock or special-order item

Confirm customer ship-to and bill-to defaults load correctly

**Text:** Test credit hold on an over-limit customer

**Critical:** true

**Text:** Test tax by jurisdiction and a tax-exempt customer

**Critical:** true

Enter an order with a customer-specific part number or cross reference

Enter a drop-ship order and confirm the purchase order is created

Test order entry with a salesperson who has restricted security

#### Pricing and cost

**Items:**

**Text:** Verify list price, multiplier and contract price on sample items

**Critical:** true

Test quantity breaks at, below and above each break

Test a price override and confirm approval rules fire

**Text:** Compare gross margin on five orders to the legacy system

**Critical:** true

Check unit of measure conversion on price and quantity

Test an expired contract price and confirm the fallback

#### Allocation, pick and ship

**Items:**

**Text:** Allocate stock from the correct location

**Critical:** true

Create a backorder and confirm it releases on receipt

Print or reprint a pick ticket

Ship a partial order and ship the remainder later

Test lot or serial tracked item shipment if used

Test a branch transfer and confirm quantity in both locations

Confirm carrier, freight charge and tracking number flow to the invoice

#### Invoicing and receivables

**Items:**

**Text:** Invoice a shipped order and check totals against the order

**Critical:** true

**Text:** Confirm revenue, tax, freight and COGS postings to the ledger

**Critical:** true

Test a credit memo and a return to stock

Apply a customer payment to an invoice and to account

Run customer statement and aging, compare to legacy

Test terms discount calculation on a paid invoice

#### Documents, EDI and integrations

**Items:**

Print order acknowledgement, pick ticket, packing list and invoice with correct branding

**Text:** Send and receive a test EDI purchase order and invoice

**Critical:** true

Check e-commerce or portal orders arrive with correct pricing

Test email delivery of invoices

Verify tax engine or freight rating connections if used

#### Cutover readiness

**Items:**

**Text:** Open sales orders loaded and reconciled to legacy by count and value

**Critical:** true

**Text:** Inventory balances loaded and reconciled by location

**Critical:** true

**Text:** Receivable balances loaded and reconciled to the ledger

**Critical:** true

Users trained and security roles tested

Rollback plan written and agreed

Sign-off recorded by sales, purchasing, warehouse and finance

**Scoring Note:** Do not go live with any critical item open. Record the tester, date and order number evidence for each completed test.

## Content

**Intro:** Most distributor go-live problems appear in the order-to-cash path: wrong prices, stock allocated from the wrong place, invoices that do not match the ledger. This checklist lists the tests to run on real scenarios before cutover.

**Sections:**

#### How to use the checklist

**Body:** Assign each group to a business owner rather than the project team: customer service for order entry, purchasing for drop ship, the warehouse for pick and ship, finance for invoicing and cash. Run each test with a real customer and item, write down the order number as evidence, and mark the item done only after the result matches the legacy system or the written expectation.

**Bullets:**

- One owner per group
- Record order numbers as evidence
- Retest after every configuration fix
- Critical items block go-live

#### Why pricing and margin come first

**Body:** Pricing is the highest-risk area because errors are silent. A wrong multiplier or a missing contract price still produces an invoice. Compare gross margin on a handful of recent orders between the old and new systems, and examine every difference. Distributors often find stale contract prices and unit-of-measure errors this way.

#### Reconciliation at cutover

**Body:** Open orders, inventory by location and receivables must tie to the legacy system by count and by value on a frozen date. Record who ran each reconciliation and the variance. A small variance that is explained is fine. An unexplained one means the data load needs fixing before users enter new transactions.

#### Common mistakes

**Body:** Teams test only happy paths, skip returns and credits, and never test with a restricted user. They also forget printed documents, which customers see first. Add negative tests and run at least one full cycle with each security role.

**Cta:** If you are planning a Prophet 21 cutover and want an independent review of your test scripts and data reconciliations, we can discuss it.

**Faq:**

#### How many test orders should we run?

**Answer:** Cover every distinct scenario at least once rather than chasing a number: stock, special order, drop ship, partial ship, return, tax exempt, contract price, EDI. Most projects end up with a few dozen scripted orders plus parallel runs.

#### Should we run a parallel period?

**Answer:** Many distributors run a short parallel on a subset of orders to compare totals and margin. It costs staff time, so choose a bounded scope, for example one branch for one week, and define the comparison in advance.

#### Who should sign off?

**Answer:** Business owners from sales, purchasing, the warehouse and finance, not only IT. Their signature confirms the system supports how they work and that their data tied out.

#### What if a critical test fails near go-live?

**Answer:** Fix and retest, or delay. A failing pricing, tax or ledger posting test creates errors in every transaction after launch, which are costly to correct. Use your rollback plan if the issue appears after cutover.