# ERP Cutover Runbook Template for Infor VISUAL and XA Migrations

> Source: https://netray.co/tools/visual-cutover-runbook-template
> Publisher: Netray (netray.co), AI and integration engineering for ERP and manufacturing systems.
> Section: Free Tools

## Short answer

A fill-in go-live weekend runbook with freeze time, task sequence, rollback criteria, contacts and approvals.

## Category

erp-migration

## Erp

Infor VISUAL

## Audience

- Project manager
- ERP consultant
- IT manager

## Tool

**Kind:** template

**Output:** document

**Fields:**

#### Company name

**Key:** company

**Type:** text

**Default:** Northfield Machine Works

#### Project name

**Key:** project

**Type:** text

**Default:** VISUAL to CloudSuite Industrial go-live

#### Legacy freeze date and time

**Key:** freeze

**Type:** text

**Default:** 2026-11-13 18:00

#### Go-live date and time

**Key:** golive

**Type:** text

**Default:** 2026-11-16 06:00

#### Cutover lead

**Key:** lead

**Type:** text

**Default:** A. Morgan

#### Support contact

**Key:** support

**Type:** text

**Default:** Hypercare desk, extension 4100

#### Rollback decision deadline

**Key:** rollback_by

**Type:** text

**Default:** 2026-11-15 20:00

#### Go or no-go criteria

**Key:** criteria

**Type:** textarea

**Default:** Trial balance ties to legacy within agreed tolerance. Open work orders and inventory counts reconcile. Key interfaces pass test messages. Users can sign in and print shipping documents.

**Blocks:**

#### Cutover runbook

**Body:** Company: {{company}}
Project: {{project}}
Cutover lead: {{lead}}
Legacy freeze: {{freeze}}
Go-live: {{golive}}
Support: {{support}}

#### Go or no-go criteria

**Body:** {{criteria}}

#### Task sequence

**Table:**

**Columns:**

- Step
- Task
- Owner
- Start
- Duration
- Done

**Rows:**

**0:** 1

**1:** Announce freeze and stop new transactions

**3:** {{freeze}}

**0:** 2

**1:** Back up legacy database

**0:** 3

**1:** Extract and load final master data

**0:** 4

**1:** Load open orders, work orders and balances

**0:** 5

**1:** Reconcile inventory and financial balances

**0:** 6

**1:** Test interfaces and printing

**0:** 7

**1:** Go or no-go decision

**3:** {{rollback_by}}

**0:** 8

**1:** Open system to users

**3:** {{golive}}

#### Rollback plan

**Body:** If criteria are not met by {{rollback_by}}, the cutover lead calls a rollback. The legacy system is restored from the backup taken in step 2 and users are told when to resume. Record every transaction keyed into the new system for reentry later.

#### Approvals

**Signatures:**

- Project sponsor
- Cutover lead
- Finance
- Operations
- IT

**Notes:** A planning template. Replace the sample tasks with your own detailed steps, durations and dependencies.

## Content

**Intro:** A cutover weekend fails when the plan lives in someone's head. This runbook template gives you a single document with freeze time, ordered tasks, owners, go or no-go criteria and a rollback line that everyone has agreed in advance.

**Sections:**

#### How to use the template

**Body:** Fill in the header fields with real dates and names, then agree the criteria with the sponsor before the weekend, not during it. Expand the task table to cover every step, including small ones like printer setup. Export the document and keep a printed copy with the cutover lead.

**Bullets:**

- Rehearse the sequence at least once with real data volumes
- Give every task one owner, not a team
- Set the rollback deadline while there is still time to execute it

#### Why go and no-go criteria matter

**Body:** Without written criteria, the decision becomes emotional by Sunday night. Measurable tests such as trial balance agreement, inventory reconciliation and interface test messages keep it factual. Rollback has a cost, but it is much smaller than operating on bad balances. Decide the tolerance for differences up front.

#### Common mistakes

**Body:** Common failures include an unrehearsed data load that takes twice as long as planned, no one assigned to the printed documents the floor needs, and unclear communication to customers and suppliers about the switchover.

**Bullets:**

- Load time never measured
- Shipping documents and labels not tested
- No hypercare staffing for the first week

**Cta:** If you want a second pair of eyes on a cutover plan or scripts for reconciliation, talk to us. The template is free and works alone.

**Faq:**

#### Is this tied to a specific ERP?

**Answer:** No. It is written for moves away from Infor VISUAL or XA but the structure works for any ERP cutover. Replace the task rows with the steps from your own implementation plan.

#### How long should a cutover take?

**Answer:** It depends on data volume, number of interfaces and how well rehearsed it is. Many mid-size shops plan a weekend, but your rehearsals should give the real durations.

#### Who decides to roll back?

**Answer:** The project sponsor and cutover lead, using criteria agreed in advance. Write the names on the document so nobody has to guess in the moment.

#### What is hypercare?

**Answer:** A period after go-live, often one to four weeks, with extra support staff on call to fix issues quickly. Plan its staffing and exit criteria before go-live.

## Search terms

erp cutover runbook template, go live plan template erp, erp cutover checklist weekend, erp migration rollback plan, visual migration cutover plan, xa migration go live, cutover plan word template, go no go criteria erp

---