Dynamics GP implementation project plan: tasks, timing and an exit milestone
A Dynamics GP project plan today is rarely for a new customer; it is for existing GP users adding a company, a module or a cleaner chart of accounts, while support runs out at the end of 2029. A sound plan covers setup in GP Utilities, module configuration, data loads, testing on a copy of the company and a final milestone that prepares data for a later move to Business Central.
When this makes sense
- You acquired a business and need a new GP company set up alongside the existing ones.
- You are adding Fixed Asset Management, Analytical Accounting or Payroll to an existing GP system.
- Your chart of accounts needs restructuring and you are considering PSTL or a full re-implementation.
- An auditor or new CFO asked for a documented project plan for GP changes.
- You want any GP work you fund now to make the later migration easier.
What the engagement covers
Lifecycle decision
Confirm the GP version, the published end of support dates and whether this work should be done in GP or folded into a move to Business Central.
Company setup
New company creation in GP Utilities, fiscal periods, account format, posting setup, multicurrency and intercompany setup.
Module configuration
General Ledger, Payables, Receivables, SOP, POP, Inventory, Bank Reconciliation, Fixed Assets and Payroll, with posting accounts and batch approvals.
Data loads
Master records, open transactions and balances through eConnect or an integration tool, with reconciliation against source totals.
Chart of accounts changes
Account restructuring with Professional Services Tools Library where suitable, and its effect on Management Reporter and SmartList.
Testing and rollout
Test company refreshed from live, user acceptance scripts, security tasks and roles, and a rollback plan.
Exit readiness milestone
Clean masters, closed historical years and documented add-ons, so the future migration starts from good data.
How it runs
- 1
Initiate (1-2 weeks)
- Confirm scope against GP lifecycle
- Assign owners
- Create test company from live
- 2
Configure (2-4 weeks)
- Company and module setup
- Posting and approval setup
- Security roles
- 3
Load and test (2-4 weeks)
- Master and open item loads
- Reconciliation
- User acceptance testing
- 4
Go live (1-2 weeks)
- Cutover at period start
- First close support
- Exit readiness checklist
What you get
- Project plan with tasks, owners and dates
- Company and module setup document
- Data load templates and reconciliation reports
- UAT scripts and sign-off record
- Updated Management Reporter and SmartList reports
- Exit readiness checklist for a later migration
What drives cost and effort
| Scope type | A new company copy is small; a full chart of accounts restructure touches every report and integration. |
| Third-party products | Each ISV add-on must be checked for version compatibility and configured in the new company. |
| Data volume | Open transactions and history loads add mapping and reconciliation. |
| Reporting | Management Reporter row and tree definitions must be updated after account changes. |
| Version currency | Older GP versions may need an upgrade before new work can start. |
Fixed-price small project
A new company, module add or defined account change.
Block of hours
Ongoing GP work with small changes over a few months.
GP work plus migration planning
Companies that want current GP changes and a Business Central roadmap in one engagement.
Questions to ask any Microsoft Dynamics GP consultant
Should this work be done in GP or deferred into a migration?
Spending on GP close to end of support may be wasted.
Which add-ons do we run, and do they support our GP version?
ISV compatibility breaks GP projects more often than GP itself.
How will Management Reporter and SmartList be updated?
Reports silently break after account changes.
How will you test on a copy of live before touching production?
GP changes such as PSTL account tools are hard to reverse.
What will you leave us that helps the later migration?
Clean data and documentation lower future migration cost.
Score candidate partners side by side with the free Implementation Partner Scorecard
Where these projects go wrong
Account restructuring breaks reports and integrations.
Inventory every report and interface using accounts and test them in the test company.
Work started without a backup and test copy.
Restore live to a test company first and rehearse the change.
Add-on not updated for the GP version.
Check every ISV product before planning dates.
Investment in GP just before migration.
Compare the cost of the change with bringing the migration forward.
If your migration to Business Central or another ERP is less than a year away, consider doing the restructure in the new system instead of in GP. Small changes such as a new user or a new posting account can be handled by your internal GP administrator without a project plan.
Frequently asked questions
Can I still implement Dynamics GP?
Microsoft no longer sells GP to new customers, so new implementations are rare. Existing customers still add companies, modules and changes until end of support.
What does a GP implementation project plan include?
Scope and lifecycle check, company and module setup, data loads, testing on a copy of live, go-live at a period start and a close-out checklist.
How long does a GP new company setup take?
A new company with standard modules commonly takes three to six weeks including data loads and testing.
What is PSTL used for?
Professional Services Tools Library provides tools for tasks such as account modifier and combiner and other master record changes. Use it only after testing on a copy of the company.
Should I upgrade GP or move to Business Central?
Upgrade if you need GP for a few more years and the upgrade is small. Plan a move if support end is close or you need cloud features.