Most distributor go-live problems appear in the order-to-cash path: wrong prices, stock allocated from the wrong place, invoices that do not match the ledger. This checklist lists the tests to run on real scenarios before cutover.

0%

0 of 38 items complete

12 critical items still open - these are the highest-risk gaps.

Download checklist:

Quote and order entry

Pricing and cost

Allocation, pick and ship

Invoicing and receivables

Documents, EDI and integrations

Cutover readiness

Do not go live with any critical item open. Record the tester, date and order number evidence for each completed test.

Independent go-live review

Optional: have your test plan and reconciliation approach reviewed before cutover.

Optional. The tool and every export work without this. No spam.

How to use the checklist

Assign each group to a business owner rather than the project team: customer service for order entry, purchasing for drop ship, the warehouse for pick and ship, finance for invoicing and cash. Run each test with a real customer and item, write down the order number as evidence, and mark the item done only after the result matches the legacy system or the written expectation.

  • One owner per group
  • Record order numbers as evidence
  • Retest after every configuration fix
  • Critical items block go-live

Why pricing and margin come first

Pricing is the highest-risk area because errors are silent. A wrong multiplier or a missing contract price still produces an invoice. Compare gross margin on a handful of recent orders between the old and new systems, and examine every difference. Distributors often find stale contract prices and unit-of-measure errors this way.

Reconciliation at cutover

Open orders, inventory by location and receivables must tie to the legacy system by count and by value on a frozen date. Record who ran each reconciliation and the variance. A small variance that is explained is fine. An unexplained one means the data load needs fixing before users enter new transactions.

Common mistakes

Teams test only happy paths, skip returns and credits, and never test with a restricted user. They also forget printed documents, which customers see first. Add negative tests and run at least one full cycle with each security role.

Frequently Asked Questions

How many test orders should we run?

Cover every distinct scenario at least once rather than chasing a number: stock, special order, drop ship, partial ship, return, tax exempt, contract price, EDI. Most projects end up with a few dozen scripted orders plus parallel runs.

Should we run a parallel period?

Many distributors run a short parallel on a subset of orders to compare totals and margin. It costs staff time, so choose a bounded scope, for example one branch for one week, and define the comparison in advance.

Who should sign off?

Business owners from sales, purchasing, the warehouse and finance, not only IT. Their signature confirms the system supports how they work and that their data tied out.

What if a critical test fails near go-live?

Fix and retest, or delay. A failing pricing, tax or ledger posting test creates errors in every transaction after launch, which are costly to correct. Use your rollback plan if the issue appears after cutover.