Machinery Shipping Crate and Rigging Plan Template

Machines are damaged more often in transit and at the unloading dock than on the production floor. A written crating and rigging plan puts weights, lift points and site constraints on paper before the truck arrives.

Fill in

Live preview
Download:

Machinery Shipping Crate and Rigging Plan Template

Crating and Rigging Plan

Shipper: Northfield Automation Ltd Consignee: Harbor Packaging Inc Machine: CP-12 Case Packer, S/N CP12-0457 Planned ship date: 2026-11-18

Load data

ItemValue
Crated dimensions4.2 m x 2.1 m x 2.4 m
Gross weight6,800 kg
Center of gravityOffset 300 mm toward drive end, marked on crate
Transport modeRoad flatbed
ProtectionClosed wooden crate

Lifting points and equipment

Lift pointMethodRated capacityChecked by
Fork pockets
Crane lugs
Spreader beam

Site access

Dock height 1.2 m, 10 t forklift available, 2.5 m door height at receiving. Mobile crane required for placement.

Preparation checklist

TaskDoneInitials
Fluids drained or secured
Loose parts bolted or boxed
Moving axes locked
Bright surfaces coated with rust preventive
Desiccant and indicator fitted
Tilt and shock indicators fitted
Photos taken before closing crate

Approvals

Shipping coordinator / Date
Installation lead / Date
Customer receiving / Date

A starting point. Lifting must follow a qualified rigger's plan and local regulations. Confirm weights by weighing and verify wood packaging marking requirements such as ISPM 15 for export.

Generate shipping documents from ERP data

Optional review of producing packing and shipping documents directly from your ERP.

Optional. The tool and every export work without this. No spam.

How to use the plan

Fill in the machine, dimensions, gross weight and center of gravity. These numbers drive the choice of crate, trailer and lifting equipment, so use measured values, not drawing estimates. Pick the transport mode and the protection method together, since an ocean container needs vapor protection while a local road move may not. Add the consignee's site access details, such as door height, floor load and crane availability. Complete the preparation checklist at packing and attach photos.

  • Weigh the crated machine when possible
  • Mark center of gravity and lift points on the outside
  • Ask the consignee for door and floor limits early
  • Photograph the machine before the crate is closed

Choosing protection

The right protection depends on the route, duration and climate. Ocean shipments face condensation, so use a sealed barrier with desiccant and a humidity indicator. Machined and ground surfaces need rust preventive. Controllers and drives often travel better removed and boxed separately. For export, wooden pallets and crates normally need heat treatment and marking under ISPM 15, and some countries have extra rules. Check requirements with your forwarder before building the crate.

Rigging and site handover

The rigging table makes sure each lifting method has a rated capacity and a person who checked it. Rated capacity must exceed gross weight with an appropriate safety margin, and the center of gravity may require unequal sling lengths or a spreader beam. At arrival, inspect the tilt and shock indicators before accepting the load and note damage on the delivery document. Record any claim details promptly, because carrier time limits are short.

Common mistakes

Frequent problems are using drawing weights that omit options, forgetting that the site door is too low, and planning a forklift lift for a load that needs a crane. Another is skipping photos, which leaves no evidence for an insurance claim. Share the plan with the installation team so unloading and placement are planned with the same numbers.

Frequently Asked Questions

What is ISPM 15?

ISPM 15 is an international standard for treating and marking solid wood packaging used in international trade to limit the spread of pests. Many countries require the mark on wooden crates and pallets for export.

How do I find the center of gravity?

Use the CAD model for a first estimate, then confirm with scales under each support point or a trial lift. Mark the result visibly on the crate and in the rigging plan.

Who is responsible for unloading?

The contract and the shipping terms decide this. State on the plan who supplies the crane or forklift and who holds the lift plan, so the delivery day does not turn into a dispute.

Does this replace a formal lift plan?

No. It collects the inputs. For critical or heavy lifts a qualified rigger or lift supervisor must prepare and approve the actual lift plan under local regulations.

If shipping data and packing lists come from your ERP, Netray can help generate them consistently from sales and inventory records. Ask for a short review.