Equipment SAT Checklist and Report Template

The site acceptance test is the formal moment when a machine, installed and running at the customer, is judged against the contract. This template builds a clean SAT report you can fill in on site and export to PDF or Word for signature.

Fill in

Live preview
Download:

Site Acceptance Test (SAT) Report Template

Site Acceptance Test Report

Supplier: Northfield Automation Ltd Customer: Harlan Components Inc. Machine: Automated ultrasonic welding and leak test cell Serial number: NA-2026-0417 Purchase order: PO-77105 Location: Plant 2, Line 4 Test date: 2026-11-12

Acceptance criteria

Contracted rate: 14 parts per minute Required yield: 98.5 percent or better over 4 hours Criteria are as defined in the contract and the agreed SAT procedure. Any change must be recorded and signed by both parties.

Site and utilities readiness

ItemRequirementMeasuredPass
Electrical supplyVoltage and phase sequence per drawing
Compressed airPressure and dryness per specification
Floor and anchoringLevel and fixed per layout
Network connectionAddress and ports per IT plan
OperatorsTrained and available for test

Functional and performance results

TestAcceptance criterionResultPass or fail
Safety functionsE-stops, interlocks and guards verified
Operating modesManual, setup and automatic run
ChangeoverRecipe change within agreed time
Throughput runMeets contracted rate with production product
Quality runMeets required yield and tolerances
Line integrationUpstream and downstream handshakes

Outcome

Overall result: Accepted with punch list

Punch list: 1. Replace damaged HMI cable gland (supplier, due 2026-11-19). 2. Add second label to guard door (customer, due 2026-11-16).

Sign-off

Supplier commissioning engineer / Date
Customer representative / Date
Customer quality or safety representative / Date

This is a starting point, not a legal document. Check payment and warranty start conditions in your contract before signing, because acceptance often triggers both. Adapt the tables to your machine.

Link acceptance to warranty and billing

Optional review of how SAT acceptance can start warranty and trigger invoicing inside your ERP.

Optional. The tool and every export work without this. No spam.

How to use the template

Fill in the header fields before arriving on site: serial number, purchase order, contracted rate and yield. On the day, record measured values in the tables and mark each test pass or fail. Describe any open item in the punch list field with an owner and a due date. The report then assembles into a document with signature lines. Print or export it, collect signatures on site, and attach photographs and raw data as appendices.

  • Bring the agreed procedure; the report records its results, it does not replace it.
  • Use production product where possible, not substitute samples.
  • Record the software versions installed at acceptance.
  • Never sign with unresolved safety items.

What acceptance triggers

In most machinery contracts SAT acceptance starts the warranty period and releases a payment milestone, often the final one or a retention release. That is why the wording of the overall result matters. Accepted with punch list should mean the machine is usable and the listed items do not affect safety or contracted performance, with dates for closure. If the contract has no clear definition, agree one in writing before the test, not during an argument at the end of it.

Making the performance test meaningful

Specify duration, product, operator skill level and permitted interventions. A four-hour run with only planned stops measures something different from an eight-hour run with natural variation. Log downtime reasons by category so that disputes about availability can be settled with data. If the customer line is not ready, document the limitation in the report instead of silently moving to a simulated test; the later difference is where claims come from.

Common mistakes

Frequent problems are signing the report before the quality run completes, leaving utilities problems unrecorded so they become supplier issues, and accepting verbal promises instead of a dated punch list. Another is forgetting training: operators who have not been trained during commissioning generate warranty calls in the first month. Close the SAT by confirming spare parts handover, manuals, backups of programs and contact points for support.

Frequently Asked Questions

Who signs a SAT report?

Normally the supplier commissioning lead and a customer representative with authority to accept the machine. Many customers add quality, safety or maintenance sign-offs. Check the contract so the right people sign, because the acceptance date can start the warranty clock and release payment.

Can acceptance be partial?

Yes. Accepted with punch list is common: the machine is accepted subject to closing listed items by agreed dates. Some contracts hold back a small retention until closure. Make sure the items are specific, owned and dated, and that none affect safety or contracted performance.

What if the machine passes FAT but fails SAT?

Investigate the difference: transport damage, utilities, operator practice, product variation or environmental conditions. Record the finding in the report. Responsibility depends on the contract, so keep evidence such as logs and photographs and agree corrective actions and a retest date.

How long should a SAT take?

It depends on complexity. A simple stand-alone machine may need one day, while an integrated line can need a week with ramp-up. Plan the performance run, operator training and punch list review as separate blocks so none are squeezed out by schedule pressure.

If you want SAT sign-off to update warranty start, billing milestones and installed-base records in your ERP automatically, Netray can design that workflow.