Standard Work Combination Sheet Worksheet (Manual, Auto and Walk Time)
The standard work combination sheet shows how a person's manual work, the machine's automatic cycle and the walking fit together in one cycle. This worksheet records those times element by element and totals the operator's cycle so you can compare it with takt time.
| Step | Work element | Type | Manual time (sec) | Machine auto time (sec) | Walk time (sec) | Operator time (sec) | |
|---|---|---|---|---|---|---|---|
10 | |||||||
2 | |||||||
17 | |||||||
11 | |||||||
10 | |||||||
11 |
This sheet assumes machine auto time overlaps with operator work, which is the case in most single-machine cells. Compare operator cycle time with your takt time. If one machine's auto time exceeds the operator's time, the machine paces the cell.
Reconcile observed times with ERP routings
Optional: we can compare observed cycle times with routing standards and flag the largest gaps.
Optional. The tool and every export work without this. No spam.
How to use the worksheet
Time each work element with a stopwatch or video, repeating observations until the numbers are stable. Split every element into manual time, machine auto time, and walk time. The sheet adds manual and walk time into the operator time, since those are what keep the person busy. Classify each element as value-added, necessary non-value-added or waste, and target the waste elements first. The sample rows show a CNC cell where the operator also deburrs and gauges parts while the machine runs.
- Observe at least 10 cycles and use the repeatable minimum, not the best case
- Record walking separately, since it is the first thing layout changes reduce
- Time what the operator does now, not what the routing says
- Include inspections and material handling that appear in the cycle
Operator time versus takt time
Takt time is available time divided by customer demand. If the operator cycle time is below takt, the cell can meet demand with some spare capacity. If it is above, either remove waste, rebalance work among operators or add resources. Machine auto time matters when it exceeds the operator cycle; in that case the machine paces the process and the operator waits. The summary lines show the walk share and any machine wait so you can see which constraint applies.
Reading the sample
In the sample, the operator spends about 44 seconds of manual and walk time while the machine runs a 46-second automatic cycle. The operator cycle is therefore close to the machine cycle, which is a healthy balance. The waste row, searching for a gauge, adds 11 seconds with no value. Removing it with a shadow board would reduce the operator cycle and cut walking as well.
Common mistakes
Copying times from the ERP routing instead of observing, hiding waste inside value-added elements, and using a single best observation are the typical errors. Another is forgetting that standard work is a standard for the current best method, not a fixed limit. After each improvement update the sheet, retrain the operators and then adjust ERP routing times accordingly.
Frequently Asked Questions
What is a standard work combination sheet?
It is a chart that shows, for one operator, the sequence of work elements with manual, machine and walking times, so the combined cycle can be compared with takt time and improved.
How is it different from a work instruction?
A work instruction tells how to do the steps. The combination sheet shows timing and the interaction between the person and the machine. Both belong in standard work.
How do I measure walk time?
Stopwatch the movements between locations or video the cycle. Record walking from where the last task ended to where the next starts. A spaghetti diagram can help you find the distances.
Should auto time be included in the operator cycle?
Not when the operator works while the machine runs. Include auto time as waiting only if the operator has nothing to do. The summary line shows the waiting component.
If you want to compare observed standard work against the routing times in your ERP, we can help you pull and reconcile them.
Related Tools
Spaghetti Diagram Distance Calculator
Convert the distance you measured on a spaghetti diagram into walking time and annual cost, and compare it to an improved layout.
Discrete ManufacturingValue Stream Map Data Worksheet
Fill in the data box for each process step of your current-state map and get total lead time, value-added time and process cycle efficiency.
Discrete ManufacturingTakt Time Calculator
Compute the takt time your line must hit to meet customer demand, plus the required hourly rate for supervisors and schedulers.
Discrete ManufacturingKaizen Event Charter Template
Fill in the fields and generate a one-page charter for a kaizen blitz, with scope, targets, team, timeline and approvals.
More MES & Shop Floor tools
See all- Line Balancing Worksheet
- SMED Changeover Reduction Worksheet
- Finite Capacity Scheduling Worksheet
- Production Schedule Template
- Bottleneck Analysis Calculator
- Drum Buffer Rope Buffer Sizing Calculator
- Production Schedule Adherence Calculator
- Production Schedule Release Checklist
- Daily Production Schedule Board Worksheet
Keep exploring
Free tools
- Standard Work Sheet Template for ManufacturingAn editable standard work sheet with work elements, times, takt, standard WIP and safety or quality points. It totals operator time and compares it to takt.
- Takt Time and Machine Count CalculatorConvert monthly demand, shifts and breaks into takt time, then find how many machines are needed at your cycle time and OEE.
- CNC Setup Sheet TemplateA fill-in CNC setup sheet covering job data, work offsets, workholding, tools and operator notes, with PDF, Word and Excel export.