Supplier Lead Time Variance Worksheet
MRP trusts the lead time in the item or vendor record. If suppliers really take ten days longer, every planned order is released late. This worksheet compares the number in your ERP with what actually happened.
| Part number | Supplier | ERP lead time (days) | Receipt 1 actual (days) | Receipt 2 actual (days) | Receipt 3 actual (days) | Average actual | Longest actual | Variance (days) | Variance (%) | |
|---|---|---|---|---|---|---|---|---|---|---|
41.6667 | 45 | 6.6667 | 19% | |||||||
12 | 13 | 0 | 0% | |||||||
23.3333 | 26 | 2.3333 | 11.1% | |||||||
7.3333 | 8 | 0.3333 | 4.8% | |||||||
36 | 40 | 8 | 28.6% |
Measure lead time from PO release or order date to receipt into stock, in calendar days, the same way your ERP defines it. Three receipts is a minimum; use more history when you have it. Consider the longest actual for critical parts.
Compute lead times from receipt history
Optional: ask about a read-only analysis of actual versus planned lead times in your ERP.
Optional. The tool and every export work without this. No spam.
How to use it
For each part, enter the lead time in your ERP and the actual days for the last three receipts, measured from order date to receipt. The sheet gives average actual, longest actual and variance in days and percent. Sort by variance to find the parts where the ERP is most wrong, then decide whether to update the lead time, change the safety lead time, or talk to the supplier.
- Use the same start and end definitions as your ERP
- Exclude one-off events with a known cause
- Update critical long lead items first
- Re-check after you change a value
Reading the variance
A small positive variance can be absorbed by safety lead time. A large and consistent positive variance means the planning lead time is simply wrong and should be updated; planned orders and release dates will move accordingly. A wide spread between receipts means the supplier is erratic, so look at safety stock or a second source rather than only changing the average. Negative variance means you may be releasing too early and holding stock.
Mistakes and ERP notes
Do not copy the supplier's quote without checking receipts. Do not overwrite lead times on many items without reviewing the demand impact, because longer lead times create immediate past due exceptions. In SAP see planned delivery time in the material master and the info record; in Epicor and SyteLine check the vendor part lead time; in Oracle the item or supplier lead time. Update in controlled batches.
Frequently Asked Questions
How many receipts should I use?
At least three, and ideally six to twelve months of history. Fewer receipts give noisy averages. For infrequent items use what exists and treat the result with caution.
Average or longest actual?
Use the average for the planning lead time and cover the spread with safety stock or safety lead time. For critical items where a stop is costly, many planners look at the longest actual as well.
What if my ERP uses working days?
Enter the actual in the same unit as the ERP value so the comparison is fair, and convert the whole row consistently.
Will changing lead times cause exceptions?
Yes, for lengthened lead times MRP will show past due orders until demand and supply are re-planned. Plan the change with buyers and communicate it.
Netray can help calculate actual lead times from your ERP receipt history, read-only, and flag the parts where the planning value has drifted.
Related Tools
Item Planning Parameter Review Worksheet
Audit lot sizing, lead time and safety stock per item and see safety stock in days of cover. Edit rows and export to Excel.
Discrete ManufacturingPlanned Order Offset and Start Date Calculator
Add setup, run, queue, move and safety time to get the lead time offset MRP should use to back schedule a made-in-house order.
Supply Chain & InventorySupplier Expedite Request Template
A clear expedite request to send a supplier: PO line, quantity, required date, reason and what you need back. Free PDF and Word export.
Supply Chain & InventoryPlanned Order Release Schedule Worksheet
Track planned and firm planned orders to convert or release, with quantities, dates and extended cost. Edit rows and export to Excel.
More Supply Chain & Inventory tools
See all- Oracle Fusion Inventory Turns and Carrying Cost Calculator
- Distribution ERP Fill Rate Calculator
- Distributor Rebate Tracking Worksheet
- Branch Transfer Planning Worksheet
- Distributor Slow-Moving Inventory Review Worksheet
- Distributor Vendor Performance Scorecard Worksheet
- Distributor GMROI Calculator
- Distributor Backorder Cost and Fill Rate Calculator
- EOQ with Vendor Minimum Order Calculator