Planned Order Offset and Start Date Calculator
MRP back schedules a made-in-house order from the due date using a lead time offset. If that offset is too short orders start late; too long, you build early and hold stock. This calculator builds the number from its parts.
Your numbers
Share of scheduled hours that are productive.
Your results
A simplified single operation model. Real routings sum several operations, overlap them, and use calendar rules. Validate against your ERP scheduling.
Total offset vs order quantity
Sweeps Order quantity from 10 to 500, holding your other inputs fixed.
Check routing lead times against history
Optional: ask about comparing planned offsets with actual job durations.
Optional. The tool and every export work without this. No spam.
How to use it
Enter the order quantity, setup hours and run hours per unit from your routing. Set efficiency, the hours the work centre really runs per day, and the non-touch time: queue before the operation and move or wait time after it. Add any safety lead time you apply. The result is the offset in days and the share of that time spent actually working, which is often much smaller than people expect.
The formula
Process hours equal setup plus quantity times run time, divided by efficiency. Process days are process hours divided by work hours per day. Total offset is queue plus move plus process days plus safety. The chart sweeps quantity so you can see how a larger lot raises run time while setup stays fixed. Queue and move typically dominate small orders, which is why shortening them often beats speeding up the machine.
- Process hours = (setup + qty x run) / efficiency
- Offset = queue + move + process days + safety
- Round up if your ERP stores whole days
Mistakes and ERP notes
Do not double count: if your ERP routing already adds queue and move per operation, enter them once here. Do not use theoretical run times with no efficiency. For multi-operation routings, sum the operations or use the ERP's scheduling run; SAP computes lead time scheduling in routing and production order scheduling, and Epicor and SyteLine schedule from the job routing. Review fixed lead times on items that are made at different lot sizes.
Frequently Asked Questions
Is offset the same as lead time?
In practice yes for planning: it is the time between the start and the due date of an order. Some systems split it into in-house production time and processing time, so check your ERP's definition.
Why include efficiency?
Standard times assume ideal performance. If a cell typically delivers 85 percent of scheduled hours, dividing by that factor gives a more realistic duration.
Should I add safety lead time?
Only to cover real, measured variability. Hidden padding in every field adds up and inflates the lead time, which pushes MRP to release earlier and carry more work in process.
Does this replace finite scheduling?
No. It is an infinite capacity estimate. Use your scheduler for load aware dates.
Netray can compare the offsets in your ERP with actual job start and finish history, read-only.
Related Tools
Planned Order Release Schedule Worksheet
Track planned and firm planned orders to convert or release, with quantities, dates and extended cost. Edit rows and export to Excel.
Supply Chain & InventoryItem Planning Parameter Review Worksheet
Audit lot sizing, lead time and safety stock per item and see safety stock in days of cover. Edit rows and export to Excel.
Supply Chain & InventorySupplier Lead Time Variance Worksheet
Compare the lead time in your ERP with the last three actual receipts, and see the gap in days and percent. Export to Excel.
Supply Chain & InventoryMRP Planner Workload Calculator
Estimate planner hours and headcount from active items, exception rate and time per action. See load percent and a what-if chart.
More Discrete Manufacturing tools
See all- OEE Calculator (Overall Equipment Effectiveness)
- Scrap Rate Cost Calculator
- Takt Time Calculator
- Cycle Time & Capacity Calculator
- Inventory Carrying Cost Calculator
- Economic Order Quantity (EOQ) Calculator
- MRP Nervousness Assessment
- Production Scheduling Maturity Assessment
- Shop Floor Digitization Scorecard