Infor on-premises to CloudSuite migration: what changes and how to plan it
Moving an on-premises Infor ERP to CloudSuite is less a hosting change than a redesign of how you customise, integrate and report, because multi-tenant tenants do not allow direct database access or code changes to the core. The work centres on replacing modifications with Infor OS extension points, rebuilding integrations on ION, and moving reporting to the Data Lake and Birst. For some companies the same analysis shows that switching ERP is the better path.
When this makes sense
- An LN, M3, SyteLine or VISUAL customer whose on-premises version is nearing end of support.
- An IT team that no longer wants to run SQL Server, application servers and backups for the ERP.
- A company offered commercial incentives by Infor to move to CloudSuite and wanting an independent view of the real effort.
- A business with heavy modifications that suspects the cloud move will break them.
- A leadership team weighing a move to Infor cloud against switching to a different ERP vendor.
What the engagement covers
Source estate assessment
Document the current product and version (LN, M3, CSI, VISUAL, Lawson), modifications, database-level objects, reports, integrations, users and data volumes.
Target option selection
Compare multi-tenant CloudSuite, single-tenant or hosted options where offered, a same-product move versus a cross-product move (for example VISUAL to CloudSuite Industrial), and leaving Infor for another ERP.
Customisation redesign
Replace core modifications with supported extension routes: Mongoose for CSI, LN extensibility for LN, H5 scripts and M3 extensibility for M3, plus ION workflows and ION API.
Integration rebuild
Move point-to-point database links and file drops to ION connection points, BODs and ION API, and settle firewall, VPN and single sign-on setup with Infor OS early.
Reporting and analytics
Replace direct SQL reports with Infor Data Lake queries through Compass, Birst dashboards or the product's own reporting, and plan historical data archiving.
Data migration and cutover
Run trial migrations, reconcile balances and open transactions, rehearse the cutover and plan the first close in the cloud.
Update readiness
Set up a regression test pack and process for Infor's regular multi-tenant updates, which customers cannot postpone indefinitely.
How it runs
- 1
Assessment and option analysis (3-6 weeks)
- Inventory modifications, reports and integrations
- Score cloud, stay and switch options
- Build a cost and risk comparison
- 2
Design (4-8 weeks)
- Map each modification to an extension route or retirement
- Design ION integrations
- Plan reporting and archiving
- 3
Build and trial migrations (2-5 months)
- Build extensions and integrations
- Run two or more trial migrations
- Regression and user testing
- 4
Cutover and stabilisation (2-6 weeks)
- Final migration and reconciliation
- Hypercare
- First update cycle with regression pack
What you get
- Source estate inventory and modification register
- Option analysis: Infor cloud, stay on-premises, or switch ERP
- Extension and integration design
- Reporting and archive plan
- Trial migration reconciliation results
- Cutover runbook and update regression pack
What drives cost and effort
| Modification depth | Core code changes and database objects must be redesigned; light configuration-only estates move faster. |
| Cross-product moves | VISUAL to CloudSuite Industrial or Lawson to CloudSuite Financials are reimplementations with data conversion, not upgrades. |
| Integration count | Every interface moves to ION or ION API and must be retested end to end. |
| Reporting estate | Hundreds of SQL reports take real effort to rebuild on the Data Lake or Birst. |
| Historical data | Bringing years of history into the cloud costs more than archiving it in a read-only store. |
| Internal capacity | Key users needed for testing are also running the business, which stretches timelines. |
Independent migration assessment
Companies that want a neutral comparison of cloud, stay and switch options before engaging Infor or a partner on delivery.
Phased migration programme
Estates with significant modifications and integrations that need staged redesign and multiple trial runs.
Post-migration managed service
Customers who want ongoing help with Infor updates, ION monitoring and extension maintenance.
Questions to ask any Infor CloudSuite consultant
Which modifications in our estate cannot exist in multi-tenant, and how will you replace each?
This list is the core of the effort and should be specific, not generic.
Have your consultants moved our exact product and version to CloudSuite before?
An LN migration and a VISUAL to CSI move require different skills.
How will our SQL reports and data extracts work after the move?
Loss of direct database access surprises many teams after go-live.
What is your regression process for Infor's regular updates?
Without one, every update becomes a mini project.
Would you advise us to switch ERP instead, and why or why not?
Advice that never considers alternatives is sales, not consulting.
Score candidate partners side by side with the free Implementation Partner Scorecard
Where these projects go wrong
Modifications rebuilt one for one without questioning need.
Challenge each modification against current standard functionality before redesigning it.
Reporting gap after go-live.
Rebuild critical reports and extracts before cutover and test them with finance.
Network and identity issues delay integrations.
Set up ION connection points, VPN and identity early in the project.
Update fatigue after migration.
Automate a regression pack and assign ownership for each update cycle.
If your on-premises Infor system is stable, supported and lightly modified, there may be no urgent reason to move, and staying put while planning carefully is a valid choice. If you are deeply modified and dissatisfied with Infor, the same assessment effort should include other ERPs; switching is a bigger project but sometimes the right one. And if Infor is offering to deliver the migration with its own services, compare that with a partner rather than assuming one is better.
Frequently asked questions
Can we keep our modifications in Infor CloudSuite?
Not as core code or database changes in multi-tenant. They need to be redesigned on supported extension routes such as Mongoose, LN extensions, M3 H5 scripts, ION workflows and APIs, or retired in favour of standard function.
Is moving VISUAL to CloudSuite an upgrade?
No. VISUAL and CloudSuite Industrial are different products, so it is a reimplementation with data conversion and process redesign.
How long does an Infor cloud migration take?
A lightly modified same-product move can take a few months, while cross-product moves or heavily modified estates commonly take six months to a year or more.
How do we report without database access?
Infor Data Lake with Compass SQL, Birst analytics and product reports replace direct SQL. Plan and test the rebuild before cutover.
Should we switch away from Infor instead?
Possibly, if the product no longer fits your business or you are unhappy with the vendor. Compare total cost, fit and risk of both paths before deciding, not just the migration price.