Equipment FAT Checklist Template

A factory acceptance test proves, at the builder's site, that the machine meets the contract before it is shipped and installed. This checklist gives you a structured set of checks to adapt to your machine and the customer procedure.

0%

0 of 37 items complete

11 critical items still open - these are the highest-risk gaps.

Download checklist:

Documents and readiness

Mechanical inspection

Electrical, pneumatic and hydraulic

Safety functions

Controls and software

Performance run-off and close-out

Mark each item as passed, or leave it open. Any open critical item should block release for shipment unless the customer signs a documented waiver.

Tie FAT results to the project record

Optional review of how FAT findings and punch list items can be tracked against the project in your ERP.

Optional. The tool and every export work without this. No spam.

How to use this checklist

Treat the checklist as a starting skeleton for the FAT procedure, not a replacement for it. Before the test, agree the acceptance criteria with the customer: cycle time, yield, tolerances, safety performance and what counts as a pass. During the test, tick items as they are demonstrated and note readings beside them. Items marked critical should stop release if they fail. At close-out, convert every open item into a punch list entry with an owner and a due date, and have both parties sign the report.

  • Share the procedure with the customer at least a week before the test.
  • Record serial numbers and revisions of what is being tested.
  • Photograph nameplates, panels and safety labels.
  • Do not change software between test and shipment without a change record.

What a FAT is and is not

A FAT verifies conformance to specification under controlled conditions. It is not a substitute for the site acceptance test, where the machine runs with real product, utilities and operators, and it is not a design validation. The practical value of a FAT is cost: a defect found in your shop costs hours, while the same defect found after installation costs travel, downtime and reputation. Many contracts release a payment milestone on FAT completion, so the quality of the record matters commercially as well as technically.

Performance run-off design

Define the run-off before the test: sample size, product, duration and what is counted as a failure. For a throughput claim, run long enough to include normal micro-stops, not a best-minute burst. For a quality claim, use enough parts to support the capability index you are promising; a handful of parts cannot demonstrate a Cpk of 1.67. Record any adjustment made during the run, because the customer will want to know whether the machine holds its setting or needs operator help.

Common mistakes

Typical FAT failures are not mechanical. They are an unagreed acceptance criterion, test material that does not represent production product, documents still at the wrong revision, and safety verification left until the last day. Another common problem is accepting a long punch list without dates; items without owners tend to arrive at site as the customer's problem. Keep the punch list in a tracker and review it in your next project meeting until closed.

Frequently Asked Questions

Who should attend a FAT?

At minimum the supplier test engineer and project manager. The customer typically sends a quality or operations representative and sometimes a safety specialist. Controls and mechanical engineers should be on call. Agree attendance in the contract, since witnessed tests need travel and schedule planning.

What happens if the machine fails the FAT?

The failures are logged, root cause is found, and the failed test is repeated after correction. Contracts usually say whether a partial retest is allowed. Minor failures can be moved to a punch list with customer agreement, but critical safety or performance failures normally require a full retest.

How is a FAT different from a SAT?

A FAT happens at the supplier site before shipment, with test conditions the supplier controls. A SAT happens at the customer site after installation, with real utilities, product and operators. The SAT confirms the machine still performs after transport and in its working environment.

Do I need a separate checklist per machine?

Yes for items that depend on machine features. Keep the group structure and critical items, then add or remove lines for your equipment, such as robot calibration, vision verification or vacuum leak rates. Version the template so each project records which revision was used.

If you want FAT results, punch list items and serial-level records linked to the project in your ERP, Netray can help set that up as a controlled workflow.