Dynamics GP to Business Central Cutover Runbook Template

A cutover from Dynamics GP to Business Central is mostly a sequencing problem: freeze, extract, load, reconcile, decide. This runbook puts the sequence, the owners and the go/no-go tests on one document you can print or share.

Fill in

Live preview
Free, optional. Reopen it on any device.
Download:

GP to Business Central Cutover Runbook Template

Cutover Runbook

Company: Northfield Components Inc. Source: Dynamics GP company NFC Target: Business Central Production (Online) Freeze start: 2026-12-18 Go-live: 2027-01-04 Cutover lead: Dana Whitfield

Scope

Open AR, open AP, on-hand inventory by location and lot, open sales and purchase orders, GL opening balances by period, 3 years of history summarised.

Cutover Steps

StepTaskOwnerStartDurationDone
1Announce transaction freeze to all GP users
2Post and close all open batches (GL, RM, PM, IV, SOP)
3Run final reconcile: AR and AP aging to GL control accounts
4Take full SQL backup of the GP company and system databases
5Extract final master data and open transactions
6Load to Business Central via configuration packages or the migration tool
7Post opening balances journal and verify trial balance
8Validate inventory, AR, AP and open orders against GP
9Business sign-off on go/no-go
10Open Business Central to users; set GP to read-only

Go/No-Go Criteria

CriterionThresholdResultPass
Trial balance varianceZero by account
AR aging varianceZero by customer
AP aging varianceZero by vendor
Inventory value varianceAgreed tolerance
User access testedAll key roles

Rollback Plan

If go/no-go fails, GP remains the system of record. Decision deadline: 2027-01-03 18:00 local. After that point, any transaction entered in Business Central must be re-keyed into GP or the rollback is abandoned.

Approvals

Cutover lead / Date
Finance controller / Date
Operations manager / Date
IT manager / Date

Starting-point template. Adjust steps to your migration method (Microsoft migration tooling, configuration packages or a partner tool) and to your fiscal calendar.

Cutover reconciliation review

Optional: send us your runbook and we will suggest reconciliation checks that can be automated from your GP data.

Optional. The tool and every export work without this. No spam.

Was this tool useful?

How to use the runbook

Fill in the header fields, then print or export to Word and add your own rows to the step table. Give every step a single named owner and a start time, not a date range. Run the document as a rehearsal first: a dry-run cutover into a sandbox exposes the steps you forgot, such as unposted batches or inactive vendors with open balances.

  • Rehearse at least once in a sandbox
  • One owner per step
  • Time-box the freeze window
  • Keep the GP backup until after the first month close

What belongs in the freeze

GP does not close sub-ledgers automatically, so every open batch in General Ledger, Receivables, Payables, Inventory and Sales Order Processing needs to be posted or deleted before the final extract. Open sales and purchase orders are usually migrated as open documents, not history, so confirm the received-not-invoiced and shipped-not-invoiced positions with accounting before the load.

Go/no-go and rollback

Choose tests that are binary. A trial balance that differs by one account is a fail, not a rounding discussion. Set the rollback deadline before the freeze, because the cost of rolling back rises with every transaction entered in the new system. After the deadline, fix forward.

Common mistakes

Teams most often skip the dry run, forget currency revaluation or intercompany balances, and load inventory without lot or serial detail. Others leave GP writable after go-live, so users post to both systems.

Frequently Asked Questions

Do I need to close the fiscal year before cutover?

Not always, but many teams cut over at a period or year end because balances are cleaner. Decide with your auditors whether you load history, summarised balances by period, or only opening balances.

What stays in GP after go-live?

Usually a read-only copy for audit and history lookups. Keep SQL backups and decide how long the GP server and licences must remain available for statutory retention.

Can this runbook be used for AX 2012 cutovers?

The structure transfers, but the extract and load steps differ. AX cutovers typically use data management entities and a longer reconcile phase, so adapt the step table.

Is this tied to a specific migration tool?

No. The steps describe the work, not the tool. Replace step 5 and 6 with the specifics of whichever migration method you chose.

If you want opening balances, open documents and inventory reconciled automatically against your GP data before cutover, we can build that check for you.

Get Microsoft Dynamics NAV and Business Central on-prem alerts

Support and maintenance deadlines, release changes that affect Microsoft Dynamics NAV and Business Central on-prem sites, and new free Microsoft Dynamics NAV and Business Central on-prem tools. A couple of emails a month at most.

Free. Unsubscribe with one click from any email.

ArchRay builder
Design the on-prem AI stack for Microsoft Dynamics NAV and Business Central on-prem: model, GPUs, RAG pipeline, guardrails
See memory, speed and cost as you swap parts, then export the diagram. Free, in your browser.
Open the builder

New to Microsoft Dynamics NAV and Business Central on-prem? Start with the Microsoft Dynamics NAV and Business Central on-prem guide and toolkit.

Keep exploring

Free tools

ERP fixes and how-tos

AI on your ERP

Integrations

Comparisons

Software