SMED Changeover Improvement Checklist
SMED, single minute exchange of die, is a method for cutting changeover time by separating work that must happen with the machine stopped from work that can be done while it runs. This checklist follows the classic stages so a workshop team does not miss steps.
0 of 32 items complete
10 critical items still open - these are the highest-risk gaps.
Stage 0: Prepare and observe
Stage 1: Separate internal and external work
Stage 2: Convert internal work to external
Stage 3: Streamline remaining internal and external work
Stage 4: Standardize and sustain
Aim to complete every critical item before declaring the workshop finished. Changeover is measured from last good part to first good part, which includes the adjustment time.
Compare actual changeovers with ERP setup times
Optional: we can outline a read-only comparison of real changeover durations versus planning standards.
Optional. The tool and every export work without this. No spam.
How to use the checklist
Work through the stages in order during a one to three day workshop. Print the PDF and tick items as the team completes them. Critical items are those that most changeover projects fail without: a clear definition of the endpoint, a video of the real changeover, a proper internal versus external split, and updated planning data afterward. Export to Excel if you want to add owners and due dates for follow-up actions.
The method behind SMED
Shigeo Shingo developed SMED at Toyota supplier plants. The idea is simple: record the changeover, classify every element as internal or external, move as much as possible from internal to external, and then simplify what remains. Many sites achieve substantial reductions from the first two stages alone, simply by preparing tools and material before the machine stops. Later stages require small engineering changes such as quick clamps and fixed stops.
- Internal work needs the machine stopped.
- External work can be done while the machine runs.
- Adjustment and trial runs are usually the largest hidden time.
Why changeover time matters for planning
Short changeovers allow smaller lots, which reduces inventory and lead time and supports leveled scheduling. When the improvement is real, update the setup time in the routing and the lot size rules in the ERP, otherwise planning continues to assume old values and the benefit disappears into larger batches. Record changeover durations in your MES or shop floor system so the numbers are credible.
Common mistakes
Teams often skip the video and argue from memory. Others stop measuring at the first piece produced rather than the first good piece, which hides adjustment waste. Another mistake is buying expensive quick change hardware before doing the free work of preparing tools and material. Finally, gains vanish when the standard is not trained or audited, so schedule the 30 day review in advance.
Frequently Asked Questions
What does SMED stand for?
SMED stands for single minute exchange of die. The goal is to bring changeovers into the single digit minutes, meaning under ten, although many sites use the method to simply halve their changeover time without reaching that target.
What is the difference between internal and external setup?
Internal setup is work that can only be done when the machine is stopped, such as removing a die. External setup can be done while the machine is running, such as fetching and preparing the next tooling. SMED moves work from internal to external.
When does a changeover end?
A changeover is normally measured from the last good part of the previous run to the first good part of the next run. Counting only until the machine restarts hides the adjustment and trial time that often make up a large share.
Does SMED need new equipment?
Not at first. Preparing tools, material and paperwork before the stop, and organizing a changeover cart, cost very little. Quick clamps, fixed stops and presetting equipment come later and should be justified by the measured gain.
If setup times in your ERP no longer reflect reality, we can help compare actual changeover data with routing standards and flag where planning is out of date.
Related Tools
OEE Six Big Losses Reference Table
Each of the six big equipment losses mapped to its OEE factor, with examples, where the data comes from and how to attack it.
Developer ToolsLean KPI SQL Query Generator (OEE Downtime Pareto)
Fill in your own table and column names to get a downtime Pareto query and an availability query you can run against an MES or ERP reporting database.
Discrete ManufacturingLean Manufacturing Maturity Self-Assessment
Ten questions that place your plant on a simple lean maturity scale and suggest where to focus next.
Discrete ManufacturingSeven Wastes of Lean (Muda, Mura, Muri) Reference Table
A searchable lookup of the classic wastes with floor examples, the ERP data that exposes each one, and the usual countermeasure.
More MES & Shop Floor tools
See all- Oracle Fusion OEE Work Center Calculator
- Infor VISUAL Shop Labor Ticket Log Worksheet
- VISUAL Shop Load Versus Capacity Calculator
- VISUAL Shop Resource Capacity and Load Calculator
- IFS Shop Order Status and Lifecycle Reference
- Plex Smart Manufacturing Data Source Request Template
- Plex Production Scheduling Checklist
- Plex Downtime Reason Log and OEE Worksheet
- Plex Go-Live Readiness Sign-Off Template