IFS Shop Order Status Reference

Shop orders are the backbone of IFS manufacturing, and most production issues show up as an order that is in the wrong status. This reference lays out the lifecycle in order, so planners and consultants can check where an order is and what should happen next.

Download:
StepStatus or eventTypeWhat it meansWhat to check
1
Planned
Status
The order exists with a quantity and dates but is not yet released to the floor.
Quantity, dates, structure and routing revision
2
Release
Event
Moves the order from planned to released so work can be organised.
Material availability and capacity before release
3
Released
Status
The order is open for planning and material handling.
Operations, work centers and priorities
4
Material reservation
Event
Component quantities are reserved against stock for the order.
Shortages and substitute parts
5
Reserved
Status
Material has been reserved for the order.
Reservation completeness by component
6
Material issue
Event
Components are issued from stock to the order.
Lot or serial numbers and issued quantity
7
Start
Event
Production begins, usually triggered by first reporting or manual start.
Start date and first operation
8
Started
Status
Production is in progress on the order.
Open operations and reported quantity
9
Operation reporting
Event
Labor, machine time and quantities are reported against operations.
Run time, setup time and scrap
10
Scrap reporting
Event
Rejected quantity is reported with a reason.
Reason code and cost impact
11
Receipt of finished goods
Event
Completed quantity is received into inventory.
Receiving location and quantity
12
Backflush
Event
Components consumed automatically based on reported output.
Backflush settings per component
13
Cost review
Check
Compare reported cost to planned cost before closing.
Variances by material, labor and overhead
14
Close
Event
Finalises the order so no more reporting is allowed.
All operations reported and no open reservations
15
Closed
Status
The order is finished and costs are final.
Variance posting and archive rules
16
Cancel
Event
Stops an order that should not be produced.
Reservations, issued material and any reported time
17
Cancelled
Status
The order was cancelled before completion.
Reason, and stock or demand impact

This is a general lifecycle guide. Status names, available events, and the exact behavior of release, reservation and close depend on your IFS release and site configuration. Confirm against your own system and process documentation.

Ask your IFS data about blocked orders

See how a read-only AI layer can answer which shop orders are blocked and show the query behind the answer.

Optional. The tool and every export work without this. No spam.

How to use the reference

Use the search box to find a status or event by name, or read down the steps in sequence. Each row says what the status means and what to check before moving on. Planners can use it to explain why an order is stuck, and trainers can use it as a one page lifecycle sheet. Export to Excel to adapt the wording to your own process.

  • Search by status or event name
  • Read the steps in order for training
  • Use the check column as a review prompt
  • Export and adapt to your process

Statuses versus events

A status is the state an order is in. An event is the action that changes the state or records progress. Confusing the two leads to wrong conclusions, for example assuming material was issued because the order is released. Releasing allows work to be organised, reserving sets aside stock, and issuing physically moves material to the order. Check each one separately.

Where orders get stuck

Typical blockers are shortages at reservation, missing routing or structure data on planned orders, operations that were never reported, and open reservations that block close. When an order will not close, look for unreported operations and unissued or unreturned material first. When it will not release, check structure, routing and any site specific release conditions.

Common mistakes

Planners often close orders before costs are reviewed, which pushes variances into the wrong period. Others cancel orders with reported time or issued material, leaving stock and cost cleanup behind. Treat close and cancel as final steps with a checklist, and agree who is allowed to perform them in production.

Frequently Asked Questions

Are these the exact IFS status names?

The core statuses such as Planned, Released, Reserved, Started, Closed and Cancelled are widely used in IFS, but the exact set and behavior depend on release and configuration. Verify against your own system.

Why can I not close my shop order?

Common reasons are unreported operations, open material reservations, or unfinished receipts. Review the operations and material tabs of the order and resolve each item before trying to close.

Does release issue material?

Not by itself. Release makes the order available for work. Reservation sets stock aside and issue moves it. Depending on your setup, some of these can be automated, so check your configuration.

Can I export this table?

Yes. The export bar downloads the reference as Excel, CSV or PDF so you can add site specific rules and ownership.