What Is Dispatch List?

Also known as: dispatching list, work center queue, shop floor dispatch, priority list

Definition

A dispatch list is a prioritized list of the operations waiting at a work center or machine, in the order they should be run, generated from the schedule and updated as jobs arrive, finish or change priority.

Dispatch List Explained

While the master schedule tells planners what will happen over weeks, the dispatch list tells a supervisor or operator what to do next on a particular machine. It typically shows the job number, part, operation, quantity, due date, priority or critical ratio, expected setup and run hours, and whether the material and tooling are ready.

The order comes from a priority rule: earliest due date, critical ratio (time remaining divided by work remaining), slack time, or the finite scheduler's computed sequence. A well-run dispatch list also accounts for operations that are not yet physically at the work center, so operators do not start something whose material is still two stations upstream.

In Infor SyteLine, work center queues and job operation lists serve this purpose and are refreshed as job transactions are posted. Infor LN provides shop floor control sessions that list planned production orders by work center. In an MES the dispatch list is usually a screen at the terminal, filtered to the operator's machine and updated live.

Why It Matters

  • It turns the plan into a clear next action for each machine, reducing supervisor firefighting.
  • Consistent priority rules reduce arguments about which job is hot.
  • Real-time updates mean rush orders appear on the right machine without verbal relays.
  • It exposes queue length per work center, a leading indicator of future late deliveries.

In Practice

Work center WC-20 has six operations waiting. The list ranks them by critical ratio: job 5107 has a ratio of 0.6 (behind schedule), job 5120 has 1.4 (comfortable). Without the list, the operator ran 5120 because the material was staged at the machine. With the list, the supervisor sees 5107 is overdue and its material is 20 minutes away, so the operator runs a short job first and then 5107.

Frequently Asked Questions

What is critical ratio?

Critical ratio is the time remaining until the due date divided by the work time remaining. A value below 1 means the job is behind schedule, 1 means on schedule, above 1 means ahead.

Who uses the dispatch list?

Production supervisors and operators use it daily to choose the next job. Planners use it to see queue lengths and spot overloaded work centers.

How is it different from a production schedule?

The schedule covers the whole plant over a horizon. The dispatch list is the work-center-level, current-shift view derived from it.

Working with Dispatch List in a live environment? Our engineers do this every day - and our AI agents automate most of it.

Try it here, free

Critical Ratio Dispatch List Python Script Generator

Open full tool

Get a small Python script that turns an ERP export of open operations into a ranked dispatch list by critical ratio.

Get ERP alerts and new tools

Support deadlines, release changes and new free tools for the ERP you run. A couple of emails a month at most.

Free. Unsubscribe with one click from any email.

ArchRay builder
Design the on-prem AI stack: model, GPUs, RAG pipeline, guardrails
See memory, speed and cost as you swap parts, then export the diagram. Free, in your browser.
Open the builder

Keep exploring

Free tools

ERP fixes and how-tos

Runs with your ERP

Guides

AI on your ERP

Integrations

Software