Shop Floor Dispatching Rules Reference (FIFO, SPT, EDD, Critical Ratio and More)

Every dispatch list is sorted by some rule, even when nobody chose it on purpose. This table lists the standard dispatching and sequencing rules, what each one sorts by and where it breaks, so a scheduler can pick a rule deliberately.

Download:
RuleAbbreviationSequence jobs byTends to improveKnown weakness
First in, first out
FIFO / FCFS
Arrival time at the work center, earliest first
Fairness, predictable waiting
Ignores due dates and job length
Shortest processing time
SPT
Operation time, shortest first
Average flow time, WIP count, throughput of jobs
Long jobs can starve and go very late
Longest processing time
LPT
Operation time, longest first
Makespan balance across parallel machines
Raises average flow time
Earliest due date
EDD
Job due date, earliest first
Maximum lateness (minimizes it on one machine)
Can still make many jobs late when the load is heavy
Earliest operation due date
ODD
Due date assigned to each operation, earliest first
Due date performance in multi-operation routings
Needs sensible operation due dates
Slack time
STR / SLACK
Due date minus today minus remaining processing time
Avoiding jobs that are about to become late
Ignores how many operations remain
Slack per remaining operation
S/RO
Slack divided by number of operations left
Multi-operation jobs with uneven queue exposure
Sensitive to wrong routing data
Critical ratio
CR
Time remaining until due divided by work time remaining, lowest first
Dynamic priority, flags late jobs (CR below 1)
Needs reliable remaining lead time estimates
Least work remaining
LWR
Total processing time still to be done, smallest first
Finishing jobs that are nearly done, lowering WIP
Delays big jobs
Most work remaining
MWR
Total processing time still to be done, largest first
Protecting long jobs from late finish
Raises WIP and average flow time
Fewest operations remaining
FOPNR
Count of operations still to do, fewest first
Clearing jobs close to completion
Ignores due dates
Next queue
NQ
Length of the next work center queue, shortest first
Keeping downstream resources fed
Needs queue visibility across work centers
Weighted shortest processing time
WSPT
Job weight divided by processing time, highest first
Weighted flow time, customer priority
Weights must be set and maintained
Shortest setup time
SST
Sequence-dependent setup time from the current job, shortest first
Lower changeover loss on a bottleneck
Can push important jobs back
Preferred customer or priority code
PCO
Priority flag, then another rule as tiebreak
Expedite and key account handling
Too many flagged jobs defeats the rule
Random
RAND
Random selection
Used as a simulation baseline
No planning value
Johnson's rule
Johnson
Two-machine flow shop: jobs with shorter first-machine time go first, others go last by longest second-machine time
Minimum makespan for a two-machine flow shop
Only exact for two machines, no sequence-dependent setups
Moore-Hodgson algorithm
Moore
EDD order, then remove the longest job each time a job would be late
Minimum number of tardy jobs on one machine
The removed jobs finish last and can be very late
Apparent tardiness cost
ATC
Weighted index mixing weight, processing time and slack
Total weighted tardiness on one machine
Needs a tuned look-ahead parameter

Rules are heuristics. Which one wins depends on load, due date tightness and setup structure, so test a rule on a copy of your real queue before changing your dispatch policy.

Want a rule-based priority score from your ERP data?

Share how your dispatch list is sorted today and we will suggest an approach. Optional, the reference above stays free.

Optional. The tool and every export work without this. No spam.

How to use this reference

Type a rule name, an abbreviation or a goal such as lateness into the search box to filter the table. Read the sort column first, because that is the field your ERP or scheduling tool must hold for the rule to work. Then read the weakness column. A rule that needs remaining lead time cannot be run until routings and queue times are credible. Export the filtered rows to Excel to attach them to a scheduling policy or an ERP configuration request.

  • Search by goal: lateness, flow time, makespan, setup.
  • Check the data the rule needs before you configure it.
  • Use a tiebreak rule, usually EDD, behind any primary rule.

Which rule for which goal

Classic scheduling theory gives a few firm results for a single machine. SPT minimizes average flow time. EDD minimizes maximum lateness. Moore-Hodgson minimizes the number of tardy jobs. For two-machine flow shops Johnson's rule minimizes makespan. Real shops have several machines, setups and changing queues, so these results become guidance rather than guarantees. Most planners end up with a hybrid: critical ratio or slack for the main dispatch list, SPT or SST on a bottleneck where changeover loss is high, and a priority code override for expedites.

Rules inside ERP and APS systems

Most ERP shop floor modules offer a small set of built-in dispatch sort options, typically start date, due date and priority, and only an advanced planning module offers true rule based sequencing. Before assuming your system uses critical ratio, check what the dispatch list or work center queue screen really sorts by. Sorting by operation start date, for example, behaves like a forward looking EDD variant and not like CR. If your rule needs data the ERP does not store, an export to a spreadsheet or script is the usual workaround.

Common mistakes

The most common mistake is changing the rule to fix a capacity problem. No rule creates capacity, it only decides who is late. The second is using SPT everywhere and ignoring starvation: long jobs wait until they are very late. The third is mixing rules between shifts so operators see a different order each time. Publish one rule, one tiebreak and one expedite process, and measure on time delivery and average flow time for a month before changing anything.

Frequently Asked Questions

What is the best dispatching rule?

There is no single best rule. SPT is strong for average flow time, EDD for maximum lateness and critical ratio for dynamic due date control. The right choice depends on your goal, load and setup structure. Compare two rules on a copy of your real queue before deciding.

What does a critical ratio below 1 mean?

Critical ratio is time remaining until the due date divided by work time remaining. Below 1 the job cannot finish on time at normal speed, equal to 1 it is exactly on schedule, and above 1 it has slack. Rank jobs from lowest to highest.

Is FIFO a good rule for production?

FIFO is fair and easy to explain, and it works when due dates are loose and job lengths are similar. It performs poorly under heavy load or mixed priorities because it ignores due dates and operation length entirely.

Can I run these rules in my ERP?