Infor LN Project-Based Manufacturing Configuration

Short answer

Project-based manufacturing in Infor LN integrates the Project Control System (PCS) with production, procurement, and finance modules to manage engineer-to-order and complex discrete manufacturing. Session tpppc1100m (Projects) establishes the project framework, while WBS (Work Breakdown Structure) elements in tpppc1110m link budgets, purchase orders, production orders, and revenue milestones into a unified project cost and schedule control system.

PCS Project Structure and WBS Setup

The Infor LN Project Control System uses a hierarchical WBS defined in session tpppc1110m to decompose complex projects into manageable work packages. Each WBS element can hold budgets, generate procurement and production demands, accumulate actual costs, and trigger billing milestones. The WBS structure typically mirrors the project's product breakdown structure, enabling cost and schedule tracking at the component or subsystem level.

  • Create project definitions in tpppc1100m with project type, classification, and organizational assignment to project managers
  • Build hierarchical WBS structures in tpppc1110m linking engineering deliverables, procurement packages, and manufacturing activities
  • Configure WBS budget elements with cost categories for material, labor, subcontracting, overhead, and contingency reserves
  • Set up project-linked production orders that inherit BOM and routing from item master while posting costs to the parent WBS element
  • Define project procurement by creating purchase requisitions linked to WBS elements for direct material and subcontracted services

Project Budget Control and Cost Tracking

Project budget control in Infor LN enforces spending limits at the WBS element level through session tpppc2600m. The system tracks committed costs (open purchase orders and production orders), actual costs (received invoices and completed production), and estimated costs at completion. Budget checking can be configured to warn or block when cumulative spending exceeds authorized WBS budgets.

  • Configure project budget checking in tpppc2600m with enforcement levels: warning, soft stop, and hard stop per WBS element
  • Track cost categories across planned, committed, actual, and estimated-at-completion to monitor project margin in real time
  • Set up automatic budget reforecasting triggered when actual costs deviate beyond configurable variance thresholds
  • Enable project change order management to formally authorize budget increases with audit trail and approval documentation

Earned Value Management and Revenue Recognition

Earned Value Management (EVM) in Infor LN provides objective measurement of project performance by comparing planned value, earned value, and actual cost at each reporting period. Session tpppc3100m calculates CPI (Cost Performance Index), SPI (Schedule Performance Index), and EAC (Estimate at Completion) metrics. Revenue recognition for project-based manufacturing follows percentage-of-completion or milestone methods compliant with ASC 606 and IFRS 15.

  • Configure earned value calculation methods in tpppc3100m: weighted milestones, physical percent complete, or cost-ratio-based
  • Generate CPI, SPI, EAC, and TCPI metrics per WBS element and project level for executive project portfolio dashboards
  • Set up milestone-based billing with automatic invoice generation when project deliverables reach completion criteria

Try it here, free

Infor LN Production Tables Reference (tisfc001, tibom010, tirou102)

Open full tool

Field-level map of the LN 10.x tables behind production orders, operations, estimated and actual material and hours, BOMs, routings, work centers and machines.

Master project-based manufacturing in Infor LN—engage Netray for PCS implementation expertise.

Get Infor LN and Baan alerts

Support and maintenance deadlines, release changes that affect Infor LN and Baan sites, and new free Infor LN and Baan tools. A couple of emails a month at most.

Free. Unsubscribe with one click from any email.

ArchRay builder
Design the on-prem AI stack for Infor LN and Baan: model, GPUs, RAG pipeline, guardrails
See memory, speed and cost as you swap parts, then export the diagram. Free, in your browser.
Open the builder

New to Infor LN and Baan? Start with the Infor LN and Baan guide and toolkit, or plan with Training Path Builder, Upgrade Path Planner, ERP Table and Field Explorer.

Keep exploring

Free tools

ERP fixes and how-tos

Guides

AI on your ERP

Comparisons