Business Central Implementation Estimate Worksheet (Excel)

A good Business Central estimate lists the work area by area, separates configuration from development, and keeps testing visible. This worksheet gives you that structure in a table you can edit and export to Excel for a quote or an internal business case.

Download:
Functional areaComplexityConfiguration days (days)Development days (days)Test and training days (days)Total daysDay rateCost
15
$13,500
13
$11,700
13
$11,700
23
$20,700
28
$26,600
23
$19,550
19
$18,050
13
$11,700
Total days
147
Total cost
$133,500
Contingency at 15%
$20,025
Budget with contingency
$153,525
Blended day rate
$908

Add one row per module, extension or integration. Typical splits put configuration, development and testing in similar proportions; high development share signals customisation risk. Example numbers are illustrative.

Review my BC estimate

Optional: send your worksheet and we will flag missing areas and unrealistic ratios.

Optional. The tool and every export work without this. No spam.

How to use it

Replace the example rows with your scope. Create one row per functional area, per integration or per extension. Enter configuration, development and test days separately, since they are staffed and priced differently. Set a day rate per row if rates differ between functional consultants, developers and project managers. The sheet totals days and cost and adds a contingency allowance.

The method

Total days per row equal the three phases added together, and cost equals total days times day rate. The summary multiplies total cost by the contingency percentage and adds it to give the budget. The blended rate shows whether cost is dominated by expensive developer time. Keep project management and governance as their own row so it is not hidden inside other lines.

  • Include data migration, which is almost always underestimated
  • Add a row for each AL extension and integration
  • Plan user training and UAT explicitly
  • Add a hypercare period after go-live

Reading the result

If development exceeds configuration across most rows, the project is adapting the product heavily. That is a signal to revisit fit-gap decisions, because custom code adds upgrade and support cost every year. Compare your total against similar projects of the same user count and modules, and treat a number far below your partner's quote as a prompt to find the missing rows.

Common mistakes

Estimating only the happy path, leaving out data cleansing, forgetting customer-side time for decisions and testing, and applying contingency to development only. Another is quoting a fixed price without agreeing the scope baseline and change control. Clear exclusions protect both sides.

Frequently Asked Questions

What contingency should I use?

Ten to twenty percent is common for well-understood scope. Use more where requirements are unclear, customisation is heavy, or data quality is unknown. Record what the contingency covers so it is not spent silently.

Can I add rows?

Yes. Add as many rows as you need for modules, extensions, integrations and reports. Totals and the summary update automatically, and you can export the sheet to Excel.

How do I handle different rates per role?

Create separate rows for functional, technical and project management work, each with its own day rate, or use a blended rate if your quote does.

Does this replace a partner's quote?

No. It structures your thinking and helps you challenge a quote. A partner's estimate also reflects their method, risk allowance and assumptions about your data and people.

If you are modernising from NAV or another ERP, we can help review your estimate and identify migration and integration work that tends to be missed.