Changeover Sequence Planning Worksheet
Changeovers are paid time with no output. This worksheet lets a scheduler lay out a running order, enter the changeover and run minutes for each job and compare sequences by the share of time lost.
| Run order | Job | Part family | Changeover min | Run min | Units | Total min | Min per unit incl. setup | |
|---|---|---|---|---|---|---|---|---|
220 | 0.7333 | |||||||
130 | 0.65 | |||||||
205 | 2.5625 | |||||||
285 | 4.75 | |||||||
135 | 0.9 |
Make a copy of the sheet for each candidate sequence. In the example, running the third small shaft job straight after the first two would cut its changeover.
Changeover data from your ERP
Optional: help extracting real changeover history from your ERP or MES.
Optional. The tool and every export work without this. No spam.
How to use it
Enter jobs in the order you plan to run them. For each, record the changeover minutes from the previous job, not a generic routing setup, because a change within the same part family is far shorter than a change across families. Compare two or three sequences and keep the one with the lowest changeover share that still meets due dates. Export to Excel to keep the winning sequence with the schedule.
Sequence logic
Sequence-dependent setups mean the best order is rarely first-in first-out. Group by family, tooling or material, and run from light to heavy or small to large when that avoids cleaning or re-fixturing. Then check the due dates. A grouped sequence that makes the most urgent job late is not an improvement. Use the summary to quantify the gain so the trade-off is explicit.
- Group by fixture, tooling or material first.
- Move urgent jobs forward only as far as needed.
- Review changeover actuals each week.
Reading the results
The share of changeover time shows where improvement effort pays. If the share is high, a SMED effort on the worst family pair usually beats trying to run faster. Minutes per unit including setup shows why very small lots are expensive: the same 40 minute setup spread over 40 pieces adds a full minute to each.
Common mistakes
Do not use the routing setup time for every job. Do not forget teardown or first piece approval, which many shops leave out of the number. Also avoid optimizing the sequence on a non-bottleneck machine; the saved minutes there may not become output.
Frequently Asked Questions
Is this a SMED worksheet?
No. It plans the order of jobs and totals changeover time. SMED reduces the length of each changeover. Use both: sequence first for quick gains, then reduce the worst changeovers.
What counts as changeover time?
From the last good piece of the previous job to the first good piece of the next, including teardown, setup, adjustment and first piece approval.
How do I record sequence-dependent setups?
Enter the changeover minutes for the actual pair of jobs in the sequence. Keep a separate matrix of family to family times if you plan often.
Can it sequence automatically?
No, it is a manual comparison sheet. Automatic sequencing needs an optimizer or an APS that holds the setup matrix.
If sequence-dependent setups are central to your scheduling, we can help extract changeover history from your ERP or MES and model better sequences.
Related Tools
Daily Production Schedule Board Worksheet
An editable job board that totals setup and run hours per line so a scheduler can see whether the day fits the shift.
MES & Shop FloorOvertime vs Added Shift Cost Calculator
Compare the weekly cost of covering a machine-hour shortfall with overtime against running an extra shift.
MES & Shop FloorSchedule Adherence Tracking Worksheet
Record planned and actual units per day with the miss reason to measure schedule attainment and find the biggest cause of misses.
MES & Shop FloorHot Job Expedite Request Form Template
Make expedites a decision with a cost: record the job, the reason, which jobs get delayed and who approved it.
More MES & Shop Floor tools
See all- Line Balancing Worksheet
- SMED Changeover Reduction Worksheet
- Finite Capacity Scheduling Worksheet
- Production Schedule Template
- Bottleneck Analysis Calculator
- Drum Buffer Rope Buffer Sizing Calculator
- Production Schedule Adherence Calculator
- Production Schedule Release Checklist
- Shift Handover Production Log Template