Infor M3 BE Upgrade Modification Retrofit Effort Calculator

This calculator estimates the retrofit and test effort for upgrading an on-prem Infor M3 Business Engine 13.x installation to a later 13.x level when you carry Java modifications made with MAK. It separates modification retrofit from scripts, MEC maps, custom APIs and testing, so you can see what drives the plan.

Your numbers

mods
mods
mods
hours
hours
hours
scripts
hours
maps
hours
APIs
hours
cycles
hours
people
hours

Your results

Total effort
1,143 hrs
Elapsed weeks
8.2 weeks
MAK retrofit hours
640 hrs
Scripts, maps and API hours
143 hrs
Test hours
360 hrs
Share of effort from MAK mods
56%

Hours per object are assumptions; replace them with figures from your last fix or upgrade. Data migration, infrastructure and training are not included.

Free, optional. Reopen it on any device.
Save results:

Total effort (hours) vs complex MAK modifications

Sweeps MAK modifications, complex from 0 to 40, holding your other inputs fixed.

Get your modification inventory reviewed

Send your MAK, H5, MEC and API inventory and we will review the retrofit estimate and which mods could be replaced.

Optional. The tool and every export work without this. No spam.

Was this tool useful?

Why MAK modifications dominate

Modifications built with MAK (the M3 Adaptation Kit) change the M3 Java programs themselves. When the upgrade delivers new versions of those programs, each modified program has to be compared and merged with the new standard code, rebuilt and tested; Lifecycle Manager tracks the fixes and modifications on the installation. H5 scripts, MEC maps and custom list APIs sit outside the standard programs, so they usually only need checking against changed fields, panels and API transactions. That is why a few complex MAK mods often cost more than dozens of scripts.

  • Retrofit = simple x h + medium x h + complex x h
  • Scripts, maps and APIs = H5 x h + MEC x h + APIs x h
  • Total = retrofit + scripts/maps/APIs + test cycles x hours per cycle

How to build the inventory

List the modified programs from MAK and the modification and fix records in Lifecycle Manager for the installation, and classify each by size of change: a few lines in one program is simple, changes across several programs or panels medium, new logic or database changes complex. Export the H5 scripts deployed in H5 administration, the MEC agreements and maps in use, and custom MDBREADMI list transactions or other custom APIs. Count only objects still used in production; retiring dead mods is the cheapest retrofit.

Worked example

20 simple, 10 medium and 4 complex mods at 8, 24 and 60 hours give 640 hours of retrofit. 30 H5 scripts at 2 hours, 25 MEC maps at 3 hours and 15 custom APIs at half an hour add 142.5 hours. Three test cycles of 120 hours add 360. Total about 1,143 hours, about 8.2 weeks for 4 people at 35 hours. MAK mods are 56 percent of the effort; the chart shows each extra complex mod adding 60 hours.

Replacing mods instead of retrofitting

Before retrofitting, ask whether each modification can become an H5 script, an MEC flow, a custom list API or a configuration change. Those survive upgrades with much less work and match the extensibility approach Infor recommends for M3. Replacing a complex mod costs more once but removes it from every future upgrade.

Frequently Asked Questions

What is Infor M3?

Infor M3 is an ERP for manufacturing and distribution, built on the M3 Business Engine (Java) with programs such as MMS001 for items and OIS100 for customer orders. It runs on-prem as M3 13.x or as the Infor-hosted CloudSuite. On-prem installations can carry Java modifications made with MAK.

What does an Infor M3 technical consultant do in an upgrade?

They inventory and retrofit MAK modifications, check H5 scripts, MEC maps and custom APIs against the new level, apply fixes with Lifecycle Manager, and support test cycles. The share of their time spent on MAK retrofit is what this calculator helps you estimate.

How many test cycles should an M3 upgrade plan include?

Plan at least two full cycles plus a final regression before go-live; three is common when modifications are numerous. Each cycle covers order to cash, procure to pay, manufacturing and finance with the integrations running. Use your previous upgrade's hours per cycle if you have them.

Do H5 scripts need rework in an M3 upgrade?

Usually less than MAK mods, but they read panel fields and call APIs, so changed panels, field names or API transactions can break them. Test each script on the target level and fix the ones that fail, which is why a small number of hours per script is included.

If you want users to ask M3 about orders, stock and items in plain English on your own servers, without adding new modifications, we can set that up.

Get Infor M3 alerts

Support and maintenance deadlines, release changes that affect Infor M3 sites, and new free Infor M3 tools. A couple of emails a month at most.

Free. Unsubscribe with one click from any email.

ArchRay builder
Design the on-prem AI stack for Infor M3: model, GPUs, RAG pipeline, guardrails
See memory, speed and cost as you swap parts, then export the diagram. Free, in your browser.
Open the builder

New to Infor M3? Start with the Infor M3 guide and toolkit, or plan with Training Path Builder, Upgrade Path Planner, ERP Table and Field Explorer.

Keep exploring

Free tools

ERP fixes and how-tos

Guides

AI on your ERP

Integrations

Comparisons

Software