Process FMEA Failure Mode Library: Common Failure Modes, Effects and Causes by Process

Starting a PFMEA from a blank sheet wastes the first meeting. This library lists failure modes that recur across common manufacturing processes, with the effect they usually have and the causes that most often turn out to be real. Search by process or keyword, then copy the relevant lines into your own FMEA.

Download:
ProcessTypical stepPotential failure modeTypical effectTypical causes to test
Machining
Turning or milling a critical diameter
Dimension oversize
Rework, or scrap if no material left; fit or function failure
Tool offset error, insert wear, program error
Machining
Turning or milling a critical diameter
Dimension undersize
Scrap; loose fit downstream
Wrong offset, thermal growth, tool breakage mid-cycle
Machining
Finish pass
Surface finish out of specification
Seal leak path, wear, customer rejection
Dull insert, wrong feed or speed, coolant issue
Machining
Edge break
Burr remains
Assembly damage, operator injury, contamination
No deburr step, worn tool, inconsistent manual deburring
Machining
Fixture load
Feature in wrong location
Scrap; interference at assembly
Part loaded in wrong orientation, fixture wear, wrong work offset
Drilling
Drill and tap
Hole missing or incomplete
Assembly stop, wrong or missing fastener
Broken drill, program skip, no tool breakage detection
Drilling
Drill and tap
Hole position out of tolerance
Fit failure, fastener cannot be installed
Spindle runout, fixture movement, drill walk
Welding
Arc weld
Porosity
Reduced joint strength, leak
Shielding gas flow, contaminated base metal, damp filler
Welding
Arc weld
Lack of fusion
Joint failure in service
Low heat input, travel speed too high, wrong joint prep
Welding
Arc weld
Burn-through
Scrap, leak
Excess current, gap too large, thin material
Welding
Fixture and weld sequence
Distortion
Dimensional nonconformance, assembly interference
Heat input, wrong weld sequence, insufficient clamping
Heat treat
Furnace cycle
Hardness out of range
Premature wear or brittle fracture
Wrong recipe, load density, furnace temperature drift
Plating or coating
Bath process
Insufficient coating thickness
Corrosion, early field failure
Bath chemistry, dwell time, current density, masking error
Plating or coating
Pretreatment
Poor adhesion
Peeling or flaking
Inadequate cleaning, contaminated rinse, expired chemistry
Painting
Spray application
Runs or sags
Cosmetic rejection, rework
Film build too heavy, viscosity, booth temperature
Injection molding
Fill and pack
Short shot
Incomplete part, scrap
Low shot size or pressure, blocked vent, cold material
Injection molding
Clamp and eject
Flash
Assembly interference, cosmetic reject
Worn tool parting line, insufficient clamp tonnage
Injection molding
Pack and cool
Sink marks or warpage
Cosmetic or fit failure
Insufficient packing, short cooling time, uneven wall thickness
Casting
Pour and solidify
Shrinkage porosity
Leak, reduced strength
Gating design, pour temperature, insufficient feeding
Stamping
Press stroke
Burr or crack at edge
Operator injury risk, downstream fracture
Die clearance, worn punch, material grade variation
Stamping
Press stroke
Wrinkle or springback
Fit failure at assembly
Blank holder force, material properties, die wear
Assembly
Component selection
Wrong component installed
Functional failure, recall exposure
Similar part numbers, mixed bins, no poka-yoke
Assembly
Component placement
Component missing
Function not delivered; field return
Operator omission, no presence check, kit shortage
Assembly
Fastening
Fastener under-torqued
Loosening in service
Tool out of calibration, operator bypass, wrong torque setting
Assembly
Fastening
Fastener over-torqued
Stripped thread or cracked part
Tool setting, no torque verification, lubricant variation
Assembly
Component placement
Part installed in wrong orientation
Function failure or damage on power-up
Symmetrical part design, no keying feature
Assembly
Cleanliness
Foreign object debris or contamination
Functional failure, hydraulic or optical contamination
Open containers, chips not removed, poor housekeeping
SMT
Solder paste print
Insufficient or excess solder paste
Open joint or solder bridge
Stencil wear or blockage, squeegee pressure, paste age
SMT
Reflow
Tombstoning
Open circuit on small passives
Uneven pad heating, pad size imbalance, placement offset
SMT
Pick and place
Component misaligned or missing
Open or short, functional failure
Nozzle wear, feeder error, vision calibration
SMT
Pick and place
Wrong polarity or wrong value
Board failure, possible damage
Feeder loaded wrong, wrong reel, program error
Cable assembly
Crimp
Crimp height out of specification
Intermittent connection or pull-out
Worn crimp tool, wrong die, wire strand damage
Cable assembly
Insertion into housing
Wire in wrong cavity
Circuit mis-wire, system malfunction
Manual routing, no continuity test, ambiguous drawing
Packaging
Labeling
Wrong or unreadable label
Shipping error, loss of traceability
Wrong label stock, printer fault, no scan verification
Packaging
Pack and ship
Damage in transit
Customer rejection, claims
Inadequate dunnage, wrong carton, stacking height
Test and inspection
Measurement
Gauge out of calibration
Escaped nonconforming parts or false rejects
Missed calibration due date, handling damage
Test and inspection
Functional test
Wrong test program revision
Defects not detected
Revision control gap, local copies, no checksum or lock
Receiving
Incoming inspection
Nonconforming material accepted
Downstream scrap or field failure
Missing certificate check, sampling plan too loose, label mix-up

These are starting prompts for a team brainstorm, not a complete or validated list for your product. Remove what does not apply, add what your history shows, and rate each retained line with your own severity, occurrence and detection criteria.

Build an FMEA starter list from your ERP history

Optional: we can show how NCR, scrap and rework data in your ERP can seed failure modes automatically.

Optional. The tool and every export work without this. No spam.

Was this tool useful?

How to use the library

Filter by the process step you are analysing, for example SMT or welding. Read each failure mode aloud with the team and ask a single question: could this happen on our line, with our equipment and our part? Keep the lines that pass and delete the rest. Then rewrite each retained line in your own words, tied to your specific part number, operation and characteristic. A generic line such as dimension oversize becomes more useful once it names the feature, the tolerance and the operation number.

  • Use the process column to match the step on your process flow diagram
  • Treat the cause column as hypotheses to verify, not conclusions
  • Add failure modes from your own NCR, scrap and warranty history
  • Never copy a line without rating it for your own process

Failure mode, effect and cause: keep them separate

A failure mode is how the process step could fail to deliver its requirement. The effect is what the next operation, the end customer or the regulator would experience. The cause is why the failure mode happens. Teams often mix these, writing scrap as a failure mode when it is an effect, or worn tool as a mode when it is a cause. The AIAG and VDA FMEA Handbook organises the analysis as a failure chain of effect, mode and cause, and rating each link separately keeps severity, occurrence and detection honest.

Where the library helps and where it does not

It helps with completeness: it prompts modes a team may overlook, such as FOD, wrong revision of a test program or a missing presence check. It does not know your tolerances, your customer-specific requirements or your process capability. A library line also says nothing about severity, which depends on your product and its end use. Safety and regulatory effects must be rated by people who know the application. Use the output as a checklist of questions, and let your own data decide which lines matter.

Frequently Asked Questions

Is this list a complete PFMEA?

No. It is a prompt list for brainstorming. A real PFMEA is specific to your part, process steps, equipment and customer requirements, and every retained line must be rated for severity, occurrence and detection by your own cross-functional team.

Can I export the table to Excel?

Yes. The reference table exports to Excel, CSV, PDF and Word. A common approach is to export the rows you need, paste them into your FMEA template and then rewrite them to match your specific operations.

Where should I get real failure modes from?

From your own data first: nonconformance reports, scrap and rework codes, customer returns, warranty claims and lessons learned from similar parts. Industry libraries come second, and they never replace history from your own line.

Does this cover design FMEA?

No, this list is about manufacturing process steps. A DFMEA analyses how a product function could fail by design, which needs a different set of prompts based on the product structure and its functions.

If your NCR, scrap and rework history lives in your ERP, Netray can help pull real failure modes and counts from it so your FMEA starts from evidence rather than memory.