Customer Furnished Material in Infor LN: Ownership, Cost and Receiving
customer furnished material in infor ln
Also searched as
- free issue material infor ln
- customer owned inventory infor ln
- customer supplied material job work erp
- CFM handling infor ln defense
Short answer
Customer furnished material (CFM, also called free issue or customer supplied) is stock your customer owns but you hold and consume on their job. In Infor LN you must keep it out of your own inventory value, receive and issue it with full traceability, and be able to prove quantities on hand. The exact mechanism depends on the LN functionality you adopt, so decide the pattern first and test it end to end.
Applies to: Infor LN 10.x for job-work, aerospace and defense manufacturers. Specific sessions and parameters depend on your version and enabled packages; confirm in your LN documentation.
Set up a CFM pattern
- 1Write down the contract requirement: who owns the material, how it must be segregated, what records the customer or government inspector expects.
- 2Pick the pattern: a dedicated item flagged as customer-owned, a dedicated warehouse or location for customer stock, or LN's consignment or customer-owned stock functionality if it fits.
- 3Make sure the stock carries zero or no ownership value in your cost and balance sheet, so inventory valuation excludes it.
- 4Receive the material against a document that records the customer, contract and quantity, with lots or serials if the part is controlled.
- 5Issue it to the production order through the normal bill of material so consumption is recorded against the job.
- 6Handle scrap, yield loss and return of unused material with defined transactions and approvals.
- 7Reconcile CFM balances per customer on a schedule and be ready to produce the report for audits.
The three questions every CFM design must answer
Who owns it: the customer, so it must never inflate your inventory value or be sold. How is it kept apart: by location, warehouse or ownership attribute, so no one issues it to another customer's job. How is it consumed: through the bill of material, so job records show real usage without a purchase cost.
If a design cannot answer all three in LN's sessions and reports, adjust it before go-live. Retrofitting CFM after mixed stock exists is painful.
Costing treatment
Customer material should enter a job at no cost to you, but the job still needs visibility of its value for pricing and for the customer's own records. A common approach is to hold a reference value separately from your standard or actual cost, so margins are not overstated or understated.
Agree the treatment with finance before configuration. Whether and how to show the value of free-issue material on invoices and cost reports is a contract and accounting decision, not a system default.
Defense and aerospace specifics
Contracts often require that government or customer property be identified, protected and reportable, and many also restrict who can see data about it. Netray does not certify compliance. Your design should let you meet your own contract clauses: segregation, traceability to lot or serial, and an auditable trail of every receipt, issue and return.
Plan a reporting view: all CFM on hand by customer, contract and location, with age. Auditors ask for it first.
CFM reconciliation checklist Received - issued - scrapped - returned = on hand On hand by location matches physical count No CFM item has inventory value in valuation report Every issue ties to a production order
Try it here, free
Infor LN Batch Job Schedule Register
An editable register of scheduled and batch jobs in Infor LN with owner, frequency, dependencies and last run status.
Common pitfalls
- !Receiving CFM as normal purchased stock, which inflates inventory value and may mix with your own stock.
- !Using the same item code for owned and customer-owned material without an ownership separator.
- !No process for yield loss and scrap, so balances drift from the customer's records.
- !Cost rolls that treat free-issue material as zero value and misprice quotes.
- !Forgetting to restrict who can transact customer-owned stock.
How an ERP-grounded AI assistant handles this
CFM audits turn into hunts across receipts, issues and counts. A private assistant over your LN data can list balances by customer and contract, flag items where valuation is not zero, and show each issue linked to its job, read-only and on your premises. It is useful for defense and aerospace sites that cannot send data to a public cloud.
Frequently asked questions
What is customer furnished material?
It is material the customer owns and supplies to you for use on their order, also called free issue or customer supplied material. You hold and consume it, but it is not your asset and must not be valued in your inventory.
Does Infor LN have a built-in CFM feature?
LN offers functionality such as consignment and customer-owned stock and flexible warehouse and item settings that can be combined to support CFM. The right pattern depends on your version and needs, so test the options and confirm with Infor documentation.
How do I keep CFM out of inventory value?
Use an ownership attribute, a dedicated item or a segregated warehouse so valuation reports exclude the stock, then verify with the valuation report after a test receipt. Agree the treatment with finance before configuring.
How should unused CFM be returned?
Use a defined return transaction that reverses the on-hand quantity and references the customer and contract, with approval and shipping documents. Reconcile after the return so the balance is zero or accurately reported.
Related
Infor LN 10.4 Lot Tracking: Setup and Traceability
Lot tracking in Infor LN 10.4 starts at the item: mark the item as lot controlled (and serialized if needed) in item data, then every receipt, issue and transfer must carry a lot. Traceability reports then follow a lot forward to customers and backward to suppliers. Switch tracking on before stock exists, because changing it on an item with inventory needs a controlled conversion.
How-toHow to calculate item cost prices in Infor LN
Infor LN calculates an item's cost price by rolling up material, labor, machine, subcontract and overhead costs defined against cost components, using the item's bill of material and routing as the calculation base for manufactured items and purchase price for bought items. The calculation can run in simulation mode to preview the result or in update mode to actually change the item's standard cost, which then drives inventory valuation and variance reporting going forward.
How-toHow to process inbound and outbound warehousing orders in Infor LN
Infor LN Warehousing splits every physical movement into inbound (goods arriving, mainly from purchase orders) and outbound (goods leaving, mainly for sales orders), each driven by its own warehouse order type. Inbound runs through intake, inspection if required, and put-away; outbound runs through order release, picking, packing and shipment confirmation, with each stage updating the order status other modules watch.
Error fixInfor LN bshell Process Stuck at 100% CPU: How to Diagnose and Fix It
A bshell process pinned at 100% CPU on the Infor LN application server almost always means one session is stuck in a 4GL loop, scanning an unindexed table, or waiting on a database lock. End the session from the Sessions Monitor first, then kill the OS process only if that fails, and check for a blocking database transaction before assuming it is a bug.
Error fixInfor LN Not Authorized to Run This Session: How to Fix It
Infor LN refuses to open a session with a not authorized message when the logged-in user's assigned role does not include that session, or when the session is blocked for the company they are logged into. Grant the session through Common > Authorization Management > Roles, or check the user's role and company context, and the session opens on retry. In most cases this is a permissions configuration issue, not a bug.
Error fixInfor LN DAL Out of Sync After a Custom Field: Cause and Fix
Infor LN throws a DAL, or table, out of sync error, or simply drops a new custom field silently, when a table's dictionary definition is changed but the generated DAL and dependent forms are not regenerated afterward. Running the standard sequence, table compile, DAL generation, then session/form compile, in Tools > Development after every dictionary change resolves it. Skipping any one of the three steps is what causes the mismatch.
AI for ERPAI for Infor LN in Aerospace and Defense Manufacturing
AI grounded on Infor LN project, contract, and configuration management data for aerospace and defense manufacturers, with on-prem deployment for ITAR.
AI for ERPAI for Infor LN: Sessions, BODs, and Engineer-to-Order Work
Add grounded AI to Infor LN 10.x or CloudSuite: natural-language answers over sessions and BODs, agents for project and engineer-to-order work, on-prem options.
Stuck on Infor LN?
Talk to engineers who work inside Infor LN every week, and who build private AI that answers these questions from your own ERP data.
New to Infor LN and Baan? Start with the Infor LN and Baan guide and toolkit, or plan with Training Path Builder, Upgrade Path Planner, ERP Table and Field Explorer.
Keep exploring
Free tools
- Infor LN Batch Job Schedule RegisterAn editable register of scheduled and batch jobs in Infor LN with owner, frequency, dependencies and last run status.
- Consignment Inventory Agreement Outline TemplateA clause outline for consignment or vendor-managed stock held at your plant, including when ownership passes, how stock is counted and who carries obsolescence.
- Infor LN and Baan Customization Inventory WorksheetEditable worksheet to list every Baan or LN customization with type, owner, effort and a retire, keep or replace decision.
ERP fixes and how-tos
- How Sales Schedules Work in Infor LN: Releases and Cumulative QuantitiesHow sales schedules work in Infor LN: releases, firm versus planned quantities, cumulative received and shipped, and how to fix a schedule that does not match.
- Additional cost setup in Infor LN, including machine costHow additional costs and machine cost rates are set up in Infor LN costing and how they flow into item cost, operation cost and order cost.
- Price Book Session in Infor LN: Setup and Order PricingHow price books work in Infor LN sales pricing: where they are maintained, how they link to price lists and order lines, and how to troubleshoot a price not found.
Runs with your ERP
- Infor Factory Track with Infor LN: barcode inventory, labor and lot or serial traceabilityFactory Track covers barcode inventory, job material, labor and lot or serial traceability for Infor LN and SyteLine. Setup, pitfalls and a private AI layer.
- Vertex with Infor LN: sales and use tax and VAT calculationHow Vertex indirect tax software works with Infor LN, SyteLine, M3 and other Infor ERPs for sales and use tax and VAT, with setup steps, pitfalls and AI use.
- Avalara AvaTax with Infor LN and Other Infor ERPsAvalara AvaTax connectors for Infor products: real-time sales tax on invoice lines, exemption certificates and filing. What is known for LN and what to verify.
Guides
- Infor LN Production Order Management and Control SetupConfigure Infor LN production control with production order types, routing setup, material issuing methods, and shop floor integration for manufacturing.
- Infor LN Batch Jobs Optimization GuideOptimize Infor LN batch jobs for performance. MRP scheduling, financial posting, report generation, and batch processing best practices.
- Infor LN Batch Jobs: Scheduling and Optimization GuideOptimize Infor LN batch job scheduling including MRP runs, GL posting, data replication, and job queue management for maximum throughput and reliability.
AI on your ERP
- AI for Infor LN in Aerospace and Defense ManufacturingAI grounded on Infor LN project, contract, and configuration management data for aerospace and defense manufacturers, with on-prem deployment for ITAR.
- AI for Infor LN: Sessions, BODs, and Engineer-to-Order WorkAdd grounded AI to Infor LN 10.x or CloudSuite: natural-language answers over sessions and BODs, agents for project and engineer-to-order work, on-prem options.
Integrations
- How to add an AI chatbot to Infor LNHow to add an AI chatbot to Infor LN for planners, buyers and customers, grounded in ERP data and documents, deliverable inside Infor OS or a portal, and runnable on-prem.
- How to add AI agents to Infor LNHow to add AI agents to Infor LN: a tool layer over ION API and BODs, read-only reporting first, approval before writes, and fully on-prem model hosting.