FMEA Severity, Occurrence and Detection Rating Scales
Severity, occurrence and detection ratings are only useful when everyone on the team uses the same scale. This reference shows the familiar 1 to 10 criteria side by side so you can rate consistently, train new engineers and paste agreed scales into your FMEA procedure.
| Rating | Severity level | Severity criteria (summary) | Occurrence level | Example failure rate | Detection level | Detection criteria (summary) |
|---|---|---|---|---|---|---|
10 | Hazardous, no warning | Safety or regulatory effect with no warning | Very high | 1 in 10 or more | Almost impossible | No known control can detect the failure |
9 | Hazardous, with warning | Safety or regulatory effect with warning | Very high | About 1 in 20 | Very remote | Control has very remote chance to detect |
8 | Very high | Loss of primary function, product inoperable | High | About 1 in 50 | Remote | Control has remote chance to detect |
7 | High | Reduced performance, customer very dissatisfied | High | About 1 in 100 | Very low | Control has very low chance to detect |
6 | Moderate | Comfort or convenience item inoperable | Moderate | About 1 in 500 | Low | Control has low chance to detect |
5 | Low | Comfort item at reduced performance | Moderate | About 1 in 2,000 | Moderate | Control has moderate chance to detect |
4 | Very low | Fit, finish or noise defect noticed by most customers | Low | About 1 in 10,000 | Moderately high | Control has a moderately high chance to detect |
3 | Minor | Defect noticed by average customers | Low | About 1 in 100,000 | High | Control has a high chance to detect |
2 | Very minor | Defect noticed only by discriminating customers | Remote | About 1 in 1,000,000 | Very high | Control has a very high chance to detect |
1 | None | No discernible effect | Failure eliminated | Prevented by a proven control | Almost certain | Control will almost certainly detect, or failure prevented by design |
These criteria follow the commonly used 10-point scheme from earlier AIAG FMEA editions, summarised in our own words. Failure rates are examples. Agree your own scales with your customer, document them in your FMEA procedure and use them consistently on every FMEA.
Back occurrence ratings with real data
Optional: see how scrap and defect history in your ERP can support FMEA ratings.
Optional. The tool and every export work without this. No spam.
How to use the scales
Find the rating row that best matches your situation and read across to the three columns. Severity rates the effect of the failure on the customer or next process, and applies to the effect, not the cause. Occurrence rates how often the cause is likely to happen given the prevention controls in place. Detection rates how well current controls would find the cause or failure before it reaches the customer. Rate the three separately and never adjust one to offset another.
- Severity belongs to the effect and does not change with controls
- Only design or process changes can lower severity
- Occurrence needs data such as defect rates, field returns or Ppk
- Detection counts current controls only
Choosing a scale for your company
The scales here are a starting point. Many companies publish their own versions, tuned to their product, such as defects per million for occurrence. Customers like the automotive OEMs publish customer specific tables as well. Keep one controlled set, give it a revision number and apply it across DFMEA and PFMEA. If you serve several customers, map your internal scale to each customer table once and record the mapping.
Examples of consistent rating
A weld that may crack and release a safety critical bracket has severity 9 or 10 even if cracking is rare. If an end-of-line test would always catch an unwelded joint, detection might be 2. A cosmetic scratch noticed by most customers rates around 4 for severity, and if the process scratches one part in a thousand, occurrence sits near 5 or 6 on a rate-based scale. Writing down why you chose each number lets the next reviewer challenge it fairly.
Common mistakes
Teams commonly lower severity after adding a control, which is wrong, rate detection on a control that does not exist yet, or rate occurrence from opinion rather than history. Another mistake is mixing scales between worksheets, which makes RPN comparisons meaningless. Review your ratings after production data accumulates and update occurrence, especially after a customer complaint or a process change.
Frequently Asked Questions
Are these the official AIAG scales?
They follow the familiar 10-point approach used in earlier AIAG editions, summarised in our own words and without copying the publication. For customer submissions use the official handbook or your customer's table.
Can I use a different scale such as 1 to 5?
Yes, if your customer allows it and you apply it consistently. Smaller scales are easier to use but give less resolution, and RPN thresholds must be rescaled accordingly.
Why can't I reduce severity with a control?
Severity describes how bad the effect is if the failure reaches the customer. Controls change how likely or how detectable the failure is, not how bad it is. Only a design or process change that alters the effect lowers severity.
How do I rate occurrence for a new process?
Use data from a similar process, pilot runs or capability studies. If none exists, rate conservatively and plan to update after production launch when real defect data becomes available.
If you want defect rates from your ERP or MES to back your occurrence ratings, Netray can show how to pull them. The scales above are free to use and export.
Related Tools
PFMEA Worksheet with RPN (Excel Export)
Fill a process FMEA row by row. RPN is calculated from S, O and D and the worst risk is summarised for you.
Engineering & PLMDFMEA Worksheet Template (Excel Export)
A design FMEA table that follows the function, failure, effect and cause chain and ranks lines by risk score.
Quality & InspectionAIAG-VDA FMEA Action Priority Reference
A quick lookup of the AIAG-VDA FMEA steps, action priority meaning and how it replaces RPN.
Quality & InspectionFMEA Review Checklist
Check a DFMEA or PFMEA for scope, failure logic, ratings consistency, actions and links to the control plan.
More Quality & Inspection tools
See all- SAP QM Process Capability Cp Cpk Calculator
- SAP QM Lot Rejection Rate, PPM and Sigma Level Calculator
- SAP QM Gauge R&R Study Calculator
- SAP QM Cp and Cpk Capability Calculator
- Job Shop Material Certification Log Worksheet
- Job Shop First Piece Inspection Sign-Off Template
- Job Shop Scrap and Rework Cost Calculator
- Master Data Audit Sample Size Calculator
- Data Quality Sigma Level Calculator
Keep exploring
Free tools
- FMEA Failure Mode Brainstorm WorksheetCapture process steps, functions, failure modes, effects and causes in one structured table before you score severity, occurrence and detection.
- FMEA Prevention and Detection Controls ReferenceA searchable list of common prevention and detection controls, with what each addresses and where it falls short, for use when completing FMEA and control plan columns.
- FMEA Team Kickoff and Scope TemplateA one-page planning document that fixes the FMEA scope, team, boundaries and rating scales before anyone writes a failure mode.