Manufacturing Process Types and Product-Process Matrix Reference

Choosing how to organise production starts with volume and variety. This reference compares the main process types, from project and job shop to continuous flow, with layout, planning approach and how each is usually represented in an ERP.

Download:
Process typeVolumeProduct varietyTypical layoutFlowExamplePlanning approachTypical ERP setupMain watch-out
Project
One
Unique
Fixed position
None, work comes to the product
Shipbuilding, large press line install
Network scheduling, milestones
Project module with WBS and milestones
Schedule slip and cost overruns on changes
Job shop
Low
Very high
Functional departments
Jumbled
Custom machining, tool and die
Finite scheduling, dispatch lists
Job based routings, engineer to order or make to order
Long queue times, hard to forecast load
Batch
Low to medium
High
Functional or hybrid
Interrupted
Aerospace components, specialty chemicals
MRP with lot sizing, work center capacity
Standard discrete MRP with routings
Setup time and batch size trade-offs
Manufacturing cell
Medium
Medium
Cellular, part families
Short loops
Machine cell for part family
Pull within cell, MRP outside
Cell as work center, labor reporting by cell
Cell balance and cross training
Repetitive
High
Low to medium
Product line
Continuous discrete
Appliances, electronics assembly
Rate based, kanban, line scheduling
Repetitive or rate based module, backflush
Line changeovers and component supply
Assembly line
High
Low
Product line, paced
Line balanced
Automotive final assembly
Takt time, sequence scheduling
Line scheduling, VIN or serial tracking
Line stoppage cost is very high
Continuous or process
Very high
Very low
Product, fixed equipment
Continuous
Petrochemicals, paper, cement
Capacity maximization, campaign planning
Process manufacturing with formulas and co-products
Unplanned shutdown and yield loss
Batch process
Medium
Medium
Vessels and process units
Batch by recipe
Pharmaceuticals, food, paints
Recipe scheduling, campaign sequencing
Formula, lot traceability, potency or grade attributes
Cleaning and changeover between batches
Make to stock
High
Low
Any
Planned to forecast
Standard fasteners
Forecast and replenishment
Forecast driven MRP, safety stock
Obsolete inventory if forecast misses
Assemble to order
Medium
High options, few modules
Final assembly cell
Modules stocked, final to order
Configured industrial equipment
Module forecast, final assembly schedule
Planning BOM, configurator
Option mix forecasting
Make to order
Low to medium
High
Functional or hybrid
Started on customer order
Specified pumps
Order driven MRP, promise date calculation
Sales order linked production, available to promise
Lead time must be competitive
Engineer to order
Low
Unique
Functional or fixed position
Design then build
Custom machinery
Project plans with engineering gates
Project costing, engineering BOM, change control
Design change cost after build starts

Classic product-process matrix logic: moving from job shop toward continuous flow trades flexibility for unit cost. Real plants often mix types, and ERP setup depends on the product in question.

Match ERP to your process mix

Optional: a short discussion on how ERP setups differ by process type.

Optional. The tool and every export work without this. No spam.

Was this tool useful?

How to use the table

Find the row closest to each of your product families and note the planning approach and ERP column. Plants are rarely a single type: a company may run a job shop for prototypes, batch for standard parts and a line for its volume product. Export the table to Excel, add a column for your own families and use it in strategy or ERP selection discussions.

The product-process matrix

The product-process matrix, described by Hayes and Wheelwright, plots process structure against product structure. Low volume, high variety work sits at the job shop end, high volume standard work at the continuous flow end. Staying on the diagonal usually matches cost to need. Off diagonal positions can be deliberate, for instance a niche job shop with premium pricing, but they need a clear reason.

Delivery strategy versus process

Make to stock, assemble to order, make to order and engineer to order describe how far inventory is held ahead of the customer order. They are separate from the physical process. A batch process can be make to stock or make to order. Mixing them up is a common source of ERP configuration mistakes, since planning logic differs for each.

Common mistakes

Applying lean line balancing to a job shop without grouping part families, forcing finite scheduling on a continuous plant, and buying an ERP module designed for a different process type are frequent errors. Check whether the system supports your dominant type natively before relying on customisation.

Frequently Asked Questions

What is the difference between batch and repetitive manufacturing?

Batch work is made in lots with changeovers and varied routings. Repetitive work flows at a set rate on a dedicated line with little variation. Repetitive is higher volume, lower variety and usually planned by rate rather than by order.

Can one plant have several process types?

Yes, and most do. It is common to run different areas as job shop, cell and line. Map each product family separately for planning and costing.

Which process type is the most flexible?

A job shop is the most flexible, as general purpose machines and skilled operators can make many different parts. The trade-off is higher unit cost, longer lead time and harder scheduling.

Does ERP choice depend on process type?

Strongly. Discrete, process (formula based) and project-driven manufacturing need different features. Check that the planning, costing and traceability model fits before you shortlist.

If you are matching an ERP to your process mix, Netray can talk through how common systems handle each type. The reference works without us.

Get ERP alerts and new tools

Support deadlines, release changes and new free tools for the ERP you run. A couple of emails a month at most.

Free. Unsubscribe with one click from any email.

ArchRay builder
Design the on-prem AI stack: model, GPUs, RAG pipeline, guardrails
See memory, speed and cost as you swap parts, then export the diagram. Free, in your browser.
Open the builder

Keep exploring

Free tools

ERP fixes and how-tos

Guides

AI on your ERP