HAZOP Guide Words and Deviations Reference Table

A HAZOP study works by applying guide words such as no, more and less to process parameters such as flow, pressure and temperature, then asking what could cause that deviation and what would follow. This reference lists the standard combinations with chemical plant examples, so facilitators and team members always have prompts at hand.

Download:
Guide wordParameterDeviationExample causeExample consequence
No / None
Flow
No flow
Blocked line, closed valve, pump trip, empty source tank
Reactor starved of feed, loss of cooling, pump running dry
More
Flow
More flow
Control valve fails open, wrong pump speed, bypass left open
Overfilling, off-ratio feed, exotherm from excess reagent
Less
Flow
Less flow
Partial blockage, fouled strainer, worn pump
Poor mixing or heat removal, off-spec product
Reverse
Flow
Reverse flow
Check valve failure, pressure higher downstream
Contamination of upstream equipment, reaction in wrong vessel
Other than
Flow
Wrong material
Incorrect hose connection, mislabeled tote
Unplanned reaction, toxic release, product loss
More
Pressure
High pressure
Blocked outlet, runaway reaction, external fire, blocked vent
Vessel overpressure, relief device lifts, loss of containment
Less
Pressure
Low pressure or vacuum
Condensing vapors, pump-out with blocked vent, steam condensation after cleaning
Vessel collapse, air ingress into flammable systems
More
Temperature
High temperature
Cooling failure, heater control failure, fouled exchanger
Runaway reaction, decomposition, boil-over
Less
Temperature
Low temperature
Heating failure, cold ambient, wrong utility
Freezing, crystallization or blocked line, reaction accumulation
More
Level
High level
Level transmitter fault, outlet blocked, overcharge
Overflow, carry-over into vent or downstream equipment
Less
Level
Low level
Leak, drain left open, instrument fault
Pump cavitation, heater exposed, loss of liquid seal
More
Concentration
High concentration
Overcharge of reagent, evaporation, dosing pump fault
Faster reaction, corrosion, exotherm
Less
Concentration
Low concentration
Dilution with water, dosing failure, wrong recipe
Incomplete reaction, off-spec product, unreacted raw material
As well as
Composition
Contamination or extra component
Cross-connection, residual from previous batch, water ingress
Side reaction, quality failure, hazardous byproducts
Part of
Composition
Component missing
Charging step skipped, empty hopper, ratio controller fault
Incomplete reaction, unstable intermediate
More
Reaction
Faster or larger reaction
Catalyst overcharge, accumulation then sudden start, agitator restart
Thermal runaway, gas evolution, overpressure
Less
Agitation
Poor mixing
Agitator motor trip, shaft or coupling failure
Stratification, hot spots, delayed reaction then surge
No / None
Utilities
Loss of cooling water, steam, nitrogen or instrument air
Utility header fault, power failure
Loss of temperature control, loss of inerting, valves moving to fail position
Early / Late
Time or sequence
Step too early or too late
Operator action, batch controller logic, delayed sample result
Wrong addition order, incomplete hold time, reaction accumulation
Other than
Operating mode
Startup, shutdown or maintenance state
Procedure not followed, bypassed interlock, abnormal operation
Exposure to hazards not present in normal operation

Guide words are prompts, not a complete list of deviations. Tailor parameters and causes to your node, and record safeguards, risk ranking and actions in your own HAZOP worksheet.

Action tracking from your HAZOP

Tell us how HAZOP actions are tracked today and we will suggest how to route them into ERP work orders and quality records.

Optional. The tool and every export work without this. No spam.

Was this tool useful?

How to use it in a session

Divide the process into nodes, such as a reactor with its feed lines and vent, then walk each node with the table open. Filter by parameter, read the deviation aloud and ask the team for credible causes. Record the consequence, existing safeguards and any actions in your HAZOP worksheet. The examples in the table are starting points. Not every combination is meaningful for every node, and discarding a combination with a reason is part of a good study.

  • Filter by parameter when working through a node line by line
  • Use the 'Other than' and 'Early / Late' rows to cover startup and batch sequence
  • Export to Excel to build your study template

Where HAZOP fits in process hazard analysis

HAZOP is one of the accepted methods for process hazard analysis, alongside what-if, checklists and FMEA. In the United States, OSHA process safety management for covered processes requires a hazard analysis that is revalidated at least every five years. HAZOP suits continuous processes and complex batch units well because it is systematic. For simple utility systems a what-if review may be enough, so match the method to the risk and the available process knowledge.

Common mistakes

Studies fail when the team lists only the normal operating mode, accepts 'operator will notice' as a safeguard, or skips batch sequencing and human factors. Another common problem is stopping at the consequence without judging whether safeguards are independent and adequate. Keep the drawings current, include operations and maintenance staff, and track every action to closure.

  • Do not count alarms as independent of the control system they depend on
  • Review the P&IDs against the plant before the session
  • Track actions to closure in a system, not an email thread

Frequently Asked Questions

What are the standard HAZOP guide words?

The commonly used set is no or none, more, less, as well as, part of, reverse and other than. Many teams add early, late, before and after for timing and sequence deviations. They combine with parameters such as flow, pressure, temperature and level.

How often should a HAZOP be repeated?

For processes covered by OSHA 29 CFR 1910.119 the hazard analysis must be updated and revalidated at least every five years. Changes to the process, incidents and new information may require earlier review under your management of change procedure.

Is HAZOP suitable for batch processes?

Yes, but add time-based prompts and sequence steps because many hazards come from the wrong order or timing of additions. Treat each recipe phase as a node or use a sequence-based variant of the method.

Do I need a facilitator?

A trained facilitator and a dedicated scribe greatly improve quality and speed. The facilitator manages the method and discussion while the scribe records causes, consequences, safeguards and actions.

Netray can help link HAZOP actions and management of change items to maintenance and quality records in your ERP so that follow-up does not depend on spreadsheets.