Pre-Startup Safety Review (PSSR) Checklist for Chemical Plants

A pre-startup safety review is the last gate before hazardous chemicals enter a new or modified process. For processes covered by OSHA 29 CFR 1910.119, a PSSR is required for new facilities and for modified facilities when the change requires a change in process safety information. This checklist helps teams cover the ground consistently.

0%

0 of 31 items complete

21 critical items still open - these are the highest-risk gaps.

Download checklist:

Design and construction

Procedures

Hazard analysis and change management

Training and readiness

Systems check and authorization

A PSSR passes only when every critical item is closed or has an approved, tracked action with a named owner and due date before hazardous material is introduced. Non-critical open items should be listed with dates.

Startup readiness tracking

Ask for a short review of how PSSR, MOC and training records can be linked to your maintenance and quality systems.

Optional. The tool and every export work without this. No spam.

How to use the checklist

Work through each group with the people who own the evidence: construction, procedures, hazard analysis, training and systems. Mark an item complete only when you have seen the document, test record or the installed equipment. Anything that cannot be closed should become a tracked action with an owner and a date. Critical items are the ones that should block startup if open. Export the completed list to PDF to keep with the project and change records.

  • Attach the evidence reference next to each completed item
  • Walk the plant physically, do not rely on documents alone
  • Include an operator who was not involved in the project

What the regulation expects

OSHA 1910.119(i) says the PSSR must confirm that construction and equipment meet design specifications, that safety, operating, maintenance and emergency procedures are in place and adequate, that a process hazard analysis has been performed and recommendations resolved for new facilities, that management of change requirements are met for modified facilities, and that training is complete. Other jurisdictions and company standards use similar logic, so the structure applies broadly even outside OSHA scope.

Common mistakes

Frequent failures include treating the PSSR as paperwork signed after the fact, running it only after commissioning has already introduced hazardous materials, closing items verbally, and letting the project team review its own work. Keep the review independent enough to challenge, and make the authorization decision explicit. If the schedule is pressuring the review, that is itself a risk to record.

  • Do not introduce process chemicals before the PSSR is approved
  • Include shift operators and maintenance in the review team
  • Keep the signed PSSR with the MOC package

Frequently Asked Questions

When is a PSSR required?

Under OSHA 1910.119, a PSSR is required before startup for new facilities and for modified facilities where the modification requires a change in process safety information. Many companies apply it to a wider set of changes by policy.

Who should sign the PSSR?

The team usually includes operations, maintenance, engineering and process safety, with final authorization by plant management. Sign-off should come from people with the authority to stop the startup.

How is a PSSR different from commissioning?

Commissioning proves that equipment works. The PSSR confirms that the whole process is ready to operate safely with hazardous material, including procedures, training, hazard analysis and emergency readiness. Both are needed.

Can startup proceed with open items?

Only non-critical items with an approved, owned and dated action. Open critical items such as untested interlocks or missing procedures should stop startup until they are closed.

Netray can help connect your PSSR and management of change records to ERP assets, work orders and training records, so startup readiness is visible in one place.