MRP Lot Sizing Rules: Which One Fits (Reference Table)

Choosing the wrong lot sizing rule creates either too many small orders or too much stock. This table summarises the common rules so a planner can pick one by item behaviour rather than by habit.

Download:
Lot sizing ruleAlso calledHow it sizes an orderBest fitWatch out for
Lot for lot
L4L, discrete, as required
Order equals the net requirement of each bucket
Expensive, high-value, make-to-order or low-volume items
Many small orders where setup or order cost is high
Fixed order quantity
FOQ, fixed lot size
Always the same quantity, repeated until the shortage is covered
Items with a natural batch, container or tooling size
Surplus when the requirement is much smaller than the lot
Economic order quantity
EOQ, Wilson formula
Quantity from sqrt(2 x annual demand x order cost / holding cost per unit)
Steady, independent demand with stable cost data
Assumes constant demand, which dependent demand rarely is
Periodic order quantity
POQ, period order quantity
Covers the net requirements of a fixed number of buckets in one order
Dependent demand where an order interval is easier than a quantity
Interval must be reviewed when demand changes level
Fixed period requirements
Fixed period, weekly or monthly grouping
Groups all requirements within a calendar period into one order
Suppliers who ship weekly, or monthly buying cycles
Early arrival of later requirements raises stock
Min-max or reorder level
Order-up-to, replenish to max
When stock falls to the minimum or reorder level, order up to the maximum
Low-value consumables, indirect materials, bin replenishment
Reactive to stock, not driven by BOM demand
Minimum order quantity
MOQ, minimum lot size
Order is at least the minimum, otherwise the net requirement
Vendors with a minimum purchase quantity
Often combined with a rounding multiple
Maximum order quantity
Maximum lot size
Caps order size and splits larger needs into several orders
Capacity, tank, oven or machine batch limits
May create several orders on the same day
Rounding multiple
Order multiple, rounding value
Rounds the order up to a multiple of a unit such as a pallet
Packaged goods, pallets, bar stock lengths
Rounding adds surplus on small requirements
Part period balancing
PPB, part-period algorithm
Combines future buckets while holding cost stays near the setup cost
Lumpy dependent demand with known setup and holding cost
Needs reliable cost data and recalculation when costs change
Least unit cost
LUC
Extends the order while cost per unit keeps falling
Items where setup and holding cost are known
Can overshoot the true optimum
Least total cost
LTC
Chooses the number of buckets where holding cost is closest to setup cost
Similar to part period balancing
Heuristic, not guaranteed optimal
Silver-Meal heuristic
Least period cost
Extends the order while average cost per period keeps falling
Time-varying demand where simplicity matters
Heuristic, may stop early if demand has later peaks
Wagner-Whitin
Dynamic programming lot sizing
Finds the lowest total setup plus holding cost over the whole horizon
Small number of high-value items with stable cost inputs
More computation, and small demand changes can reshuffle the plan

Cost-based rules need setup and holding cost inputs. Many ERPs only offer a subset, so check which rules your system supports before choosing.

Lot size review from your data

Optional: a read-only review of order sizes against recent demand history in your ERP.

Optional. The tool and every export work without this. No spam.

Was this tool useful?

How to choose a rule

Start with the cost of an order against the cost of holding stock. If setup or order cost is tiny, lot for lot is usually right. If a vendor or process imposes a fixed batch or multiple, use fixed quantity with rounding. For steady items with stable cost data, EOQ or a periodic interval works. For lumpy demand with real setup cost, use periodic or a cost-balancing heuristic. Search by your item type in the table to see the closest match.

Quantity rules versus interval rules

Quantity rules such as fixed and EOQ decide how much to order. Interval rules such as periodic and fixed period decide how many buckets of demand one order covers. Interval rules follow dependent demand better because the order quantity floats with the requirement. Limits such as minimum, maximum and rounding can be layered on top of either family.

Common mistakes

Planners often copy one rule across a whole item class without checking cost data.

  • Using EOQ on lumpy dependent demand.
  • Setting a fixed lot far larger than the typical requirement.
  • Forgetting that a rounding multiple adds surplus.
  • Leaving cost-based rules on after setup costs changed.
  • Never reviewing the rule when demand level shifts.

Frequently Asked Questions

What is the simplest lot sizing rule?

Lot for lot is the simplest: each order equals the net requirement of one bucket. It keeps inventory minimal but creates the most orders, so it suits items with low setup or order cost, or items that are expensive to hold.

When is EOQ a poor choice?

EOQ assumes constant independent demand. For components whose demand comes from lumpy parent orders it can create stock that sits for months. Periodic or cost-balancing rules usually serve those items better.

Can I combine rules?

Yes. A base rule such as lot for lot or periodic is often combined with a minimum quantity, a maximum quantity and a rounding multiple. Many ERPs expose these as separate fields on the item planning data.

How often should lot sizes be reviewed?

Review when demand level, setup cost, supplier terms or holding cost change materially, and as a routine at least once or twice a year for high-value items. Stale lot sizes are a frequent hidden source of excess inventory.

If you want lot sizing suggestions tested against your real demand history, we can discuss running that analysis read-only on your ERP data.

Get ERP alerts and new tools

Support deadlines, release changes and new free tools for the ERP you run. A couple of emails a month at most.

Free. Unsubscribe with one click from any email.

ArchRay builder
Design the on-prem AI stack: model, GPUs, RAG pipeline, guardrails
See memory, speed and cost as you swap parts, then export the diagram. Free, in your browser.
Open the builder

Keep exploring

Free tools

ERP fixes and how-tos

Guides