Welding Nonconformance Report (NCR) Template
A welding NCR has to do two jobs: stop a bad weld from moving downstream and give the quality system enough information to fix the cause. This template captures the facts inspectors need and leaves clean space for disposition and closure.
Fill in
Welding Nonconformance Report Template
Welding Nonconformance Report NCR-W-0387
Company: Northfield Fabrication Ltd Date raised: 2026-10-20 Project / work order: WO-48213 Skid frame assembly
Weld identification
| Weld ID | Welder ID | Process | WPS | Clause |
|---|---|---|---|---|
| W-27 | WLD-044 | GMAW | WPS-008 Rev 2 | Customer spec section 6.3, visual acceptance |
Nonconformance
Type: Undercut
Undercut of 1.2 mm depth over 85 mm length along the toe of fillet weld W-27, exceeding the 0.5 mm limit in the customer specification.
Root cause
Travel speed too high and torch angle not held; welder was new to the fixture position.
Disposition
Repair
Re-inspection after disposition must be recorded against this NCR number. If disposition is use as is, attach the engineering concession or customer approval.
Corrective and preventive action
Refresher training on position 2F, add torch angle sketch to the traveler, increase in-process visual checks for the next five assemblies.
Verification of closure
| Action | Owner | Due date | Verified by |
|---|---|---|---|
| Repair or rework completed | |||
| Re-inspection accepted | |||
| Corrective action implemented |
Approvals
A generic starting point. Align the numbering, severity classes and closure rules with your quality system (for example ISO 9001, ISO 3834 or the customer quality agreement). Not legal advice for contractual rejection or warranty claims.
Track weld NCRs inside your ERP
Ask for a short review of how NCRs could link to work orders, WPS and welder records.
Optional. The tool and every export work without this. No spam.
How to fill it in
Identify the weld, welder, process and WPS so the NCR can be traced to a joint and a person. Quote the clause that the weld failed, not just the defect name, because that is what turns an opinion into a rejection. Describe size and location with measurements. Choose a disposition, then record the root cause in plain words. Export the finished NCR to PDF for the job file, or to Excel if you track NCRs in a log.
- Use measurements, not adjectives, in the description
- Quote the specification clause and the limit
- Record who found it and by what method
- Attach photos or the NDE report
Root cause thinking for welding
Welding defects usually trace to one of the classic variables: procedure, person, material, equipment or environment. Porosity points to shielding gas, contamination or moisture in consumables. Lack of fusion points to heat input, joint preparation or technique. Cracking points to hydrogen, restraint, preheat or the filler. Write the cause at the level where an action can prevent it, such as an uncontrolled electrode oven, rather than blaming the welder. Pair the NCR with a corrective action that changes the process, then verify it on the next lot.
Reading the example
The sample NCR describes undercut on a fillet weld with a measured depth against a customer limit. The disposition is repair, the root cause is technique, and the corrective action adds a visual aid and extra checks. Notice that the action is verifiable: five assemblies is a countable check. Replace the sample text with your own, and use the closure table to track who verifies the repair and the corrective action separately.
Common mistakes
Weak welding NCRs create arguments later. Avoid vague wording and missing links.
- No weld ID, so the joint cannot be found again
- Disposition of use as is without a documented concession
- Closing the NCR when the repair is done but before re-inspection
- Listing training as the only corrective action every time
- Not checking other welds by the same welder or WPS for the same defect
Frequently Asked Questions
What should a welding NCR always include?
Weld or joint ID, welder, process and WPS, the clause or limit that was not met, a measured description, disposition, root cause, corrective action and signatures. Without the clause and a measurement, the rejection is hard to defend.
Who can approve use as is?
That is set by your quality system and the contract. Usually it needs the design authority or the customer, with a written concession attached to the NCR. The inspector alone should not approve it.
Do I raise an NCR for every minor visual defect?
Many shops allow immediate rework of minor in-process defects under a weld repair record and reserve NCRs for defects that escape a hold point, repeat, or are found after acceptance. Follow your procedure and the customer requirement.
Can I export this to Excel?
Yes. Every template exports to PDF, Word, Excel and CSV. Use the Excel export to build a simple NCR log, though a dedicated log worksheet is easier to filter.
If NCRs are still tracked in spreadsheets, we can show how to capture them against work orders in your ERP and surface repeat defect patterns by WPS or welder.
Related Tools
Weld Repair Procedure Template
Document a weld repair from defect location through excavation, rewelding, NDE and sign-off, then export it as a clean controlled document.
Quality & InspectionNDT Weld Inspection Request Template
Request RT, UT, MT or PT on specific weld joints with the standard, acceptance criteria and readiness details the NDT technician needs.
Quality & InspectionWeld Joint Log and NDE Tracking Worksheet
Track each weld joint, its required NDE percentage and result, and see how much weld length still needs examination.
Safety & WorkforceWelder Continuity Log Worksheet
Keep a row-by-row log of welder qualifications, processes used and last weld dates so no qualification lapses unnoticed.
More Quality & Inspection tools
See all- WPS Template (Welding Procedure Specification)
- PQR Template (Procedure Qualification Record)
- Weld Inspection Checklist (Before, During and After Welding)
- Welding Consumables Issue Log Worksheet
- SAP QM Process Capability Cp Cpk Calculator
- SAP QM Lot Rejection Rate, PPM and Sigma Level Calculator
- SAP QM Gauge R&R Study Calculator
- SAP QM Cp and Cpk Capability Calculator
- Job Shop Material Certification Log Worksheet
Keep exploring
Free tools
- NCR Nonconformance Report TemplateFill-in nonconformance report with containment, disposition and approval lines that exports to PDF, Word or Excel.
- Sheet Metal Nonconformance Report TemplateAn NCR form for fabricated parts covering defect description, quantity affected, containment, cause, disposition and corrective action.
- Aerospace MRB Nonconformance Disposition Record TemplateA fill-in record for the material review board: nonconformance details, disposition, customer approval status and sign-offs.
Guides
- How to Estimate Welding Cost for a Fabrication QuoteHow fabricators estimate welding cost: weld volume, deposition rate, arc-on time, filler efficiency, and where AI helps pull actual hours from past jobs.
- AISC Certification Quality System for Steel FabricatorsWhat an AISC certified fabricator's quality system must control: document control, material traceability, welding, nonconformances, and audit readiness.
- SyteLine Non-Conformance Report (NCR) Management ConfigurationConfigure SyteLine non-conformance report tracking and disposition workflows. Set up NCR creation, investigation, and resolution processes in CloudSuite Industrial.
AI on your ERP
- AI for SyteLine Quality: Nonconformance Reports and Inspection DataAI for Infor SyteLine quality: analyse NCR trends, inspection results and supplier defects, draft dispositions for review, and keep quality data private on-prem.
- AI for NCR, CAPA, and 8D Drafting in AS9100 and ISO 9001 Quality SystemsAI drafts NCR, CAPA, and 8D reports from ERP quality data for engineer review, cutting drafting time under AS9100 and ISO 9001 without changing sign-off.