SyteLine Purchasing Tables and Columns Reference for PO Reports
This reference lists the SyteLine 9 and 10 columns most purchase order reports need, from po_mst headers down to matltran_mst receipt rows. Each row gives the meaning, typical values, the join and a tip for open, late and received-not-vouchered reports.
| Table | Column | Meaning | Typical values or type | Join to | Report tip |
|---|---|---|---|---|---|
po_mst | po_num | Purchase order number, the header key | nvarchar, zero or prefix padded per your PO prefix setup | poitem_mst.po_num | Always join lines on po_num; never on vendor alone |
po_mst | vend_num | Vendor the PO is placed with | nvarchar vendor code | vendor_mst.vend_num, vendaddr_mst.vend_num | Vendor name is not on po_mst; join vendaddr_mst |
po_mst | order_date | Date the PO was entered or ordered | datetime | - | Use for PO volume by month; use poitem due_date for lateness |
po_mst | stat | Header status | Single-letter code, for example P planned, O ordered, C complete | - | Decode on your database with SELECT stat, COUNT(*) FROM po_mst GROUP BY stat |
po_mst | type | PO type | R regular, B blanket | - | Blanket POs carry releases; filter type when counting regular POs |
po_mst | buyer | Buyer responsible for the PO | nvarchar buyer code | - | Group open lines by buyer for a chase list |
po_mst | terms_code | Payment terms on the PO | Terms code | terms_mst.terms_code | Defaults from the vendor; can differ per PO |
po_mst | whse | Default receiving warehouse | Warehouse code | whse_mst.whse | Lines can override; report the line whse for receiving |
poitem_mst | po_num | PO number of the line | Same as po_mst.po_num | po_mst.po_num | Part of the line key with po_line and po_release |
poitem_mst | po_line | Line number | smallint | - | Key: po_num + po_line + po_release |
poitem_mst | po_release | Release number on the line | smallint, 0 on regular PO lines | - | Leaving po_release out of a join duplicates blanket release rows |
poitem_mst | item | Item ordered | Item code, or a non-inventory item | item_mst.item | LEFT JOIN item_mst so non-inventory lines are not dropped |
poitem_mst | qty_ordered | Quantity ordered in the item stocking U/M | decimal | - | Open qty = qty_ordered - qty_received |
poitem_mst | qty_received | Quantity received to date, stocking U/M | decimal | - | Compare with qty_voucher to find received but not invoiced |
poitem_mst | qty_voucher | Quantity vouchered (invoiced) to date | decimal | - | Received not vouchered = qty_received - qty_voucher |
poitem_mst | u_m | Purchase unit of measure on the line | U/M code | u_m_mst.u_m | qty_ordered is in stocking U/M; the _conv columns hold the purchase U/M values |
poitem_mst | item_cost | Unit cost in stocking U/M, PO currency | decimal | - | Open value = (qty_ordered - qty_received) * item_cost |
poitem_mst | due_date | Date the line is due | datetime | - | Late = due_date < GETDATE() and qty_ordered - qty_received > 0 |
poitem_mst | stat | Line status | P planned, O ordered, F filled, C complete | - | For open lines use stat = 'O'; F means fully received but not closed |
poitem_mst | whse | Receiving warehouse for the line | Warehouse code | whse_mst.whse | Use this, not po_mst.whse, for receiving dock reports |
poitem_mst | ref_type | What the line supplies | I inventory, J job, O customer order (others exist) | - | Drives which table ref_num points to |
poitem_mst | ref_num | Job or customer order the line supplies | Job or order number, blank for inventory | job_mst.job when J, co_mst.co_num when O | Use with ref_line_suf and ref_release for the exact job suffix or order line |
poitem_mst | ref_line_suf | Job suffix or customer order line of the reference | smallint | job_mst.suffix or coitem_mst.co_line | Meaning depends on ref_type |
vendor_mst | vend_num | Vendor code, the vendor key | nvarchar | po_mst.vend_num | One row per vendor |
vendor_mst | curr_code | Vendor currency | Currency code | currency_mst.curr_code | PO costs are in vendor currency; convert before summing across vendors |
vendor_mst | terms_code | Default payment terms | Terms code | terms_mst.terms_code | Default copied to new POs |
vendaddr_mst | vend_num | Vendor code for the address row | nvarchar | vendor_mst.vend_num | Holds the vendor name and address |
vendaddr_mst | name | Vendor name | nvarchar | - | Join po_mst.vend_num = vendaddr_mst.vend_num for the name on reports |
matltran_mst | ref_type | Source document type of the material transaction | P for purchase order rows | - | PO receipts and returns: ref_type = 'P' |
matltran_mst | ref_num | PO number for ref_type P rows | nvarchar | poitem_mst.po_num | Join ref_num = po_num |
matltran_mst | ref_line_suf | PO line for ref_type P rows | smallint | poitem_mst.po_line | Join ref_line_suf = po_line |
matltran_mst | ref_release | PO release for ref_type P rows | smallint | poitem_mst.po_release | Join ref_release = po_release |
matltran_mst | trans_type | Kind of material transaction | Single-letter code | - | Decode receipts vs returns with SELECT trans_type, COUNT(*) FROM matltran_mst WHERE ref_type = 'P' GROUP BY trans_type |
matltran_mst | trans_date | Date of the receipt or return | datetime | - | Use for receipts by day; join to the PO line for due vs actual |
matltran_mst | qty | Quantity moved, stocking U/M | decimal, sign shows direction | - | Sum qty per PO line to reconcile with poitem_mst.qty_received |
Applies to SyteLine 9.x and CSI 10.x on SQL Server, where base tables carry the _mst suffix and site-specific views drop it. Status and type letters vary slightly by release and by user-defined codes, so decode them on your own database before hard-coding a filter. Blanket PO lines live in their own table; find it on your version with SELECT name FROM sys.tables WHERE name LIKE 'po%' before joining. Run report queries against a reporting copy or with a read-only login.
Get your open PO report checked
Send us the SQL or report definition you use for open and late PO lines and we will check the joins and quantity basis against your SyteLine version.
Optional. The tool and every export work without this. No spam.
How to use it
Search by table name to see one table, or by a word such as late, voucher or vendor to see every column involved in that question. The Join to column tells you which key connects the row to the next table. The Report tip column gives the expression you usually need, such as open quantity. Export to Excel and add your own Uf_ user fields so a new report writer has one page for the purchasing schema. Column names here are database names; IDO property names on SLPos and SLPoItems are different (PoNum, VendNum, QtyOrdered and so on), so use those when you build a form, a report on an IDO or a REST load.
The formulas behind common PO reports
Open quantity is qty_ordered minus qty_received, both in the item stocking unit of measure. Open value is open quantity times item_cost, which is in the PO currency, so convert with the vendor curr_code before you add lines from different vendors. A line is late when due_date is before today and open quantity is above zero; filtering on line stat = 'O' removes planned and completed lines. Received but not vouchered is qty_received minus qty_voucher and drives the accrued liability check at month end. For receipt history, matltran_mst rows with ref_type 'P' carry the PO number, line and release in ref_num, ref_line_suf and ref_release.
- Open qty = qty_ordered - qty_received
- Late = due_date < GETDATE() AND open qty > 0
- Unvouchered = qty_received - qty_voucher
- Open value = open qty * item_cost, in PO currency
Worked example: open and late PO lines
Start from poitem_mst p, join po_mst h on h.po_num = p.po_num, then vendaddr_mst v on v.vend_num = h.vend_num for the vendor name. Select p.po_num, p.po_line, p.po_release, p.item, p.due_date, p.qty_ordered - p.qty_received AS open_qty and DATEDIFF(day, p.due_date, GETDATE()) AS days_late. Filter p.stat = 'O' and p.qty_ordered > p.qty_received. Order by days_late descending and you have the expediting list. Add p.ref_type and p.ref_num to show which job or customer order is waiting on each late line, which is the column buyers ask for first.
Gotchas
The most common mistake is joining receipts or lines on po_num only, which multiplies rows when a PO has several lines or releases. Always carry po_line and po_release. The second is reading quantities in the wrong unit: poitem_mst holds stocking U/M values in qty_ordered and qty_received, while the _conv columns hold purchase U/M values shown on the form. The third is querying the base _mst table in a multi-site database without a site_ref filter, which mixes sites. Finally, non-inventory lines have no item_mst row, so use LEFT JOIN when you bring in item descriptions.
Frequently Asked Questions
Which table holds SyteLine purchase order lines?
poitem_mst holds PO lines and releases, keyed by po_num, po_line and po_release. The header is po_mst, keyed by po_num. Receipts and returns against a line are written to matltran_mst with ref_type 'P', carrying the PO number, line and release in ref_num, ref_line_suf and ref_release.
How do I build a custom SyteLine purchase order report?
Write and test the SQL on a reporting copy, or better, base the report on the SLPoItems IDO so it respects site and security. For SSRS or Crystal, join poitem_mst to po_mst and vendaddr_mst with the keys in this table. Register the report in SyteLine through the report options and background task setup if users must launch it from a form.
Where is the vendor name in SyteLine?
The vendor name and address are on vendaddr_mst, not vendor_mst. vendor_mst holds terms, currency and other purchasing defaults. Join both on vend_num. A PO header carries vend_num only, so any report that shows a vendor name needs the vendaddr_mst join.
Why do my PO receipt totals not match qty_received?
Usually the join is missing po_release or ref_line_suf, so rows repeat, or returns are excluded. Sum matltran_mst.qty for ref_type 'P' with all three PO keys and include return transactions. Also check the unit of measure: matltran_mst and qty_received are both in stocking U/M.
If your buyers want to ask SyteLine which PO lines are late and what they hold up, in plain English and on your own servers, we can set that up read-only.
Related Tools
SyteLine Job Tables Columns Reference
Searchable column list for SyteLine production job tables with the composite keys, units basis and the formulas for WIP, shortages and actual hours.
Developer ToolsSyteLine SQL User-Defined Data Types Reference
The SQL Server user-defined data types SyteLine uses for columns and stored procedure parameters, with scripts to read exact lengths from your own database.
Infor SyteLineSyteLine Database Tables Reference
Searchable lookup of the main SyteLine SQL tables, what each holds and its usual business key, for writing queries and reports.
Developer ToolsSyteLine SQL Query Generator for Item, Job and Order Tables
Fill in site, item prefix, job status and date to produce read-only SQL for item master, jobs and open customer order lines.
Infor SyteLineSyteLine IDO Names Reference
Searchable list of common SyteLine IDO names with the underlying tables, to speed up REST integrations and form work.
More Infor SyteLine tools
See all- SyteLine Form Personalization Checklist
- SyteLine User Access Request Form Template
- SyteLine Custom Report Request Template
- SyteLine Data Conversion Mapping Worksheet
- SyteLine UAT Test Script Worksheet
- SyteLine Cutover Plan Worksheet
- SyteLine Change Request Form Template
- SyteLine Cycle Count Variance Worksheet
- SyteLine Database Growth Forecast Calculator
New to Infor SyteLine? Start with the Infor SyteLine guide and toolkit, or plan with Training Path Builder, ERP Certification Study Planner, Upgrade Path Planner.
Keep exploring
Free tools
- SyteLine Job Tables Columns ReferenceSearchable column list for SyteLine production job tables with the composite keys, units basis and the formulas for WIP, shortages and actual hours.
- SyteLine Customer Order Tables Columns ReferenceThe key columns in SyteLine 9/10 customer order tables, what they mean, how they join and how to use them in custom reports.
- SyteLine Database Tables ReferenceSearchable lookup of the main SyteLine SQL tables, what each holds and its usual business key, for writing queries and reports.