Quality & InspectionFree templatePDF, Excel, Word exportOil and Gas Equipment

Hydrostatic Test Report Template for Vessels and Piping

A hydrostatic test report is the record that a vessel, pipe spool or valve held pressure without leakage. This template captures the data auditors and customers ask for, and produces a clean document you can print or attach to the data book.

Fill in

Live preview
Free, optional. Reopen it on any device.
Download:

Hydrostatic Test Report Template for Vessels and Piping

Hydrostatic Test Report

Manufacturer: Gulf Coast Fabrication LLC Customer: Example Energy Partners PO or job: PO-448210 / J-7731 Equipment: V-101 Separator Serial number: SN-2026-0412 Test date: 2026-10-20

Test Parameters

ItemValue
Design codeASME VIII Div 1
Design or MAWP150 psig at 300 F
Test pressure225 psig
Basis of test pressure1.5 x MAWP x stress ratio per code
Test mediumPotable water, chloride below 50 ppm
Water and metal temperature18 C
Hold time at test pressure60 minutes

Instruments

Calibrated gauges used: PG-114, 0-400 psig, cal due 2027-02-15 PG-115, 0-400 psig, cal due 2027-02-15

Gauge range should be about 1.5 to 4 times the test pressure. At least one gauge directly on the item, one at the pump.

Pressure Log

TimePressureEventInitials
Start pressurizing
Reached test pressure
End of hold
Depressurized

Result and Remarks

Result: Accepted, no leakage or pressure drop

Visual examination at test pressure reduced to design pressure. No weeping at nozzle welds or gasketed joints.

Signatures

Test technician / Date
Quality inspector / Date
Customer or third party witness / Date

A starting point to adapt to your written test procedure and the governing code. Confirm test pressure, hold time, temperature limits and venting rules against the code edition and customer specification. Not legal or engineering advice.

Test records linked to your ERP

Optional: a walkthrough of attaching hydrotest records to production orders.

Optional. The tool and every export work without this. No spam.

Was this tool useful?

How to use the template

Complete the header with job, tag and serial number, then enter the code, design pressure, test pressure and its basis. Add the medium and temperature, gauge IDs with calibration due dates and the hold time. Fill the pressure log by hand during the test and sign. Export to PDF or Word for the manufacturing data book. Save a separate copy per serial number.

  • Record gauge IDs, not just model
  • Note ambient and water temperature
  • Record who witnessed the test
  • Attach the sketch of blind and test points if needed

What a good report proves

It shows the right pressure was applied for the right time with calibrated instruments and that someone qualified examined the item for leaks. Under ASME Section VIII Division 1 the standard hydrostatic test is generally 1.3 times MAWP adjusted by stress ratio, while ASME B31.3 piping uses 1.5 times design pressure adjusted by stress ratio. Other codes differ, so state the basis on the report.

Common mistakes

Frequent findings are expired gauges, undefined test medium, chlorides in the water for stainless equipment, no record of venting trapped air, and a report with no witness signature. Water temperature matters because carbon steel can be at risk of brittle fracture when test water is much colder than the minimum design metal temperature.

  • Vent all high points before pressurizing
  • Control pressurization rate
  • Drain and dry stainless after the test
  • Never test with unrestrained blinds or unsupported spools

ERP and quality records

In SAP, Oracle, Infor or Epicor, store the report as a document linked to the production order or inspection lot, and keep test pressure and result as inspection characteristics. That lets quality pull all tests for a serial number on demand and prevents shipment without a recorded pass.

Frequently Asked Questions

What should a hydrostatic test report include?

Equipment identification, code, design and test pressure, test medium and temperature, hold time, calibrated gauge IDs, observations, result and signatures from the tester, quality inspector and any witness.

How long is the hold time?

It depends on the code and procedure. Many codes require holding for at least a set minimum time and then inspecting at a reduced pressure. Follow your code and customer specification and record the actual time.

Which gauge range should I use?

Codes such as ASME VIII generally call for a gauge range of about 1.5 to 4 times the test pressure. Record the gauge ID and calibration due date on the report.

Is this report accepted by third party inspectors?

Acceptance depends on the inspector and contract. Use this as a base, align it with your procedure and the customer's inspection and test plan, and add their required fields.

If you want hydrotest results to block shipment automatically in your ERP, Netray can discuss how that could be wired up. The template is free either way.

Get ERP alerts and new tools

Support deadlines, release changes and new free tools for the ERP you run. A couple of emails a month at most.

Free. Unsubscribe with one click from any email.

ArchRay builder
Design the on-prem AI stack: model, GPUs, RAG pipeline, guardrails
See memory, speed and cost as you swap parts, then export the diagram. Free, in your browser.
Open the builder

Keep exploring

Free tools

Guides

AI on your ERP

Manufacturing hubs