ITP Inspection and Test Plan Worksheet with Hold Points
An inspection and test plan sets out who checks what, when, and whether work may continue without them. This worksheet gives you the standard columns and hold, witness, review and surveillance levels in an editable table you can export to Excel.
| Step | Activity | Standard / procedure | Record | Frequency | Manufacturer | Customer | Third party | Planned hours (h) | |
|---|---|---|---|---|---|---|---|---|---|
Key: H = hold point (work cannot proceed without release), W = witness point (party is notified and may attend), R = records review, S = surveillance or spot check, - = not applicable. Confirm the notification period for witness and hold points in the contract.
Connect ITP steps to ERP routings
Optional: a short review of how quality hold points could appear on shop floor travelers.
Optional. The tool and every export work without this. No spam.
How to use this worksheet
Start from the example rows or clear them. For each fabrication step, enter the activity, the standard or procedure and the record produced. Pick the frequency and then the intervention level for the manufacturer, customer and third party. Total planned hours help you schedule inspector time. Export to Excel for the customer to mark up, then freeze the approved revision as part of the project quality plan.
Hold, witness, review and surveillance
A hold point means the manufacturer may not proceed until the named party releases the step, so it needs a clear notification period. A witness point is notified, but work can proceed if the party does not attend. A review point involves checking records, and surveillance is a random or periodic audit. Placing too many holds slows delivery, so reserve them for steps that cannot be inspected later such as fit-up, final NDE and pressure tests.
- Hold: stop until released
- Witness: notify, may proceed if no attendance
- Review: records only
- Surveillance: random check by the party
Common mistakes
Plans frequently list a step without the record that proves it was done, or reference a procedure by name with no revision. Another common issue is putting holds on activities where nothing is hidden by later work, which creates idle time. Align the ITP step numbers with the fabrication traveler or routing so each operation in the ERP points to the same quality step.
Frequently Asked Questions
What is the difference between an ITP and a QAP?
In practice they overlap, and the names vary by region. Both set out inspections, standards and records. ITP is common in oil and gas, QAP or quality assurance plan in pressure equipment and Indian practice.
Who approves the ITP?
Usually the manufacturer's quality lead prepares it, and the customer or third-party inspector approves it before fabrication starts. Any later change should be revised and re-approved.
How do I handle sub-suppliers?
Add rows for sub-supplier steps such as forgings or castings, and extend the plan to those suppliers with the same hold and witness notation. Flow the requirements down in the purchase order.
How many hold points is reasonable?
Enough to cover steps that cannot be verified later, and no more. Typical hold points include fit-up, pressure test and final release, but the contract and risk of the equipment decide.
If your ITP steps are separate from the routings in your ERP, we can discuss linking them so quality gates appear on the shop floor travelers automatically.
Related Tools
WPS Template (Welding Procedure Specification)
A fill-in WPS document with joint, base metal, filler, preheat, shielding, electrical parameters and technique, ready to export.
Quality & InspectionPositive Material Identification PMI Record Template
Document XRF alloy verification by heat number and component, with instrument details, acceptance basis and sign-off. Exports to PDF or Word.
Quality & InspectionCoating Dry Film Thickness Measurement Log Worksheet
Log DFT readings per spot, auto-calculate the average and minimum, and see the margin to the specified minimum thickness. Exports to Excel.
Industry TemplatesWellhead and Christmas Tree Factory Acceptance Test Template
Record assembly details, pressure tests, function tests and witness sign-off for a wellhead or tree FAT, then export it for the data book.
More Quality & Inspection tools
See all- SAP QM Process Capability Cp Cpk Calculator
- SAP QM Lot Rejection Rate, PPM and Sigma Level Calculator
- SAP QM Gauge R&R Study Calculator
- SAP QM Cp and Cpk Capability Calculator
- Job Shop Material Certification Log Worksheet
- Job Shop First Piece Inspection Sign-Off Template
- Job Shop Scrap and Rework Cost Calculator
- Master Data Audit Sample Size Calculator
- Data Quality Sigma Level Calculator
Keep exploring
Free tools
- Oil and Gas Equipment Preservation and Shipping ChecklistChecklist for releasing pressure equipment, valves and wellhead hardware for shipment with preservation, marking and documents verified.
- Hydrostatic Test Report Template for Vessels and PipingFill-in hydrostatic test certificate with test pressure, medium, gauge calibration, hold time, results and signatures, exportable to PDF or Word.
- Wellhead and Christmas Tree Factory Acceptance Test TemplateRecord assembly details, pressure tests, function tests and witness sign-off for a wellhead or tree FAT, then export it for the data book.
ERP fixes and how-tos
- NetSuite Quality Management: Incoming Inspection and QuarantineNetSuite has no full QMS, but inventory status, workflows and custom records give incoming inspection, quarantine and NCR tracking. Setup steps and limits.
- How to Release a Customer Order from Credit Hold in SyteLineFind why a SyteLine customer order is on credit hold, see who is authorized to release it, and set credit limits and days-past-due rules so it stops recurring.
- How to create an inspection plan in SAP QM (QP01)Create an inspection plan in SAP QM with QP01: header, operations, master inspection characteristics, sampling procedure and material assignment, plus a plan report.
Guides
- SyteLine Quality Hold and Release Process ConfigurationConfigure SyteLine quality hold and release processes for inventory control. Set up hold reasons, release workflows, and quarantine locations in CloudSuite Industrial.
- SyteLine Inspection Plan Setup and Configuration GuideConfigure SyteLine inspection plans with test criteria, sampling rules, and measurement specs. Set up receiving, in-process, and final inspection plans in CloudSuite.
- API Q1 Quality System Records for Valve and Pump ManufacturersRecords valve and pump makers need for API Q1 and Monogram audits: nonconformances, calibration, supplier control, traceability, and prep from ERP data.
AI on your ERP
- AI on Infor SyteLine for Oil and Gas Equipment ManufacturersAI on Infor SyteLine for oil and gas equipment: API Q1 and 6A traceability, MTRs, heat lots, ETO projects, and aftermarket parts. Private deployment.
- AI ERP for Oil and Gas Equipment Manufacturers: Heat Traceability, MTRs and AftermarketPrivate AI on your ERP for wellhead, valve, BOP and pressure equipment manufacturers: heat traceability, MTRs, NDE records, API Q1 and aftermarket service.
Manufacturing hubs
- Manufacturing in Houston, Texas: oil and gas equipment, petrochemical, valves and pumpsHouston manufacturing guide: oil and gas equipment, petrochemical, valves and pumps. Standards, ecosystem, ERP and quoting problems shops face, and where private AI helps.
- Forging Industry Association (FIA): forging processes, standards and ERP realitiesForging Industry Association (FIA): open die, closed die and ring rolling shops, standards, and the ERP, traceability, costing and private AI issues forgers face.