ISO 13485 Internal Audit Report Example With Findings

A good internal audit report is short, factual and traceable. This ISO 13485 internal audit report example shows how to state scope and criteria, record what was seen, grade findings and tie them to clauses so the quality manager can feed them into CAPA and management review.

Fill in

Live preview
Free, optional. Reopen it on any device.
Download:

ISO 13485 Internal Audit Report Example

Internal Audit Report IA-2026-04

Organization: Meridian Medical Components Inc. Audit date: 2026-09-16 Lead auditor: J. Rivera Auditee(s): Production manager, purchasing lead Audit criteria: ISO 13485 requirements, applicable regulatory requirements, the organization's quality manual and procedures

1. Scope and objective

Purchasing, supplier evaluation, incoming inspection and production of the infusion pump housing family (clauses 7.4, 7.5, 8.2.4, 8.3).

Objective: determine whether the processes in scope conform to planned arrangements, are effectively implemented and maintained, and meet the stated criteria.

2. Method

The audit was carried out by interview, observation of work and sampling of records. Samples were selected from the last 12 months. Auditor independence: the auditor does not work in the processes audited.

3. Positive observations

Complaint handling records were complete and traceable to CAPA. Calibration status labels were present and current on all gauges sampled. Device history records for the three lots sampled matched the production orders.

4. Findings

No.GradeDescriptionISO 13485 clauseDue date
1Major nonconformityTwo critical suppliers on the approved supplier list had no re-evaluation record in the last 24 months, although the procedure requires an annual review (clause 7.4.1).7.4.1
2Minor nonconformityCleaning station log for the molding area had three missing signatures in August (clause 6.4.1).6.4.1
3ObservationIncoming inspection work instruction WI-RI-03 refers to a gauge that was replaced; the instruction may confuse new inspectors.7.5.1No action required

5. Conclusion

Overall result: Partly effective, major finding raised.

The auditee must respond to each nonconformity with containment, root cause and corrective action, and the quality manager will track them to closure through the CAPA system. Effectiveness of the actions will be verified at follow-up.

6. Distribution and follow-up

Copies to: top management, process owners, quality manager. This report is an input to the next management review. Follow-up audit of findings 1 and 2 to be scheduled after the due dates.

7. Sign-off

Lead auditor / Date
Process owner / Date
Quality manager / Date

The example is fictional. Replace every field with your own audit evidence. Clause references are to the ISO 13485 structure; confirm them against your licensed copy of the standard and add any regulatory references (for example FDA QMSR or EU MDR) that apply to your scope.

Audit evidence on demand

Optional: ask how a private AI layer can retrieve records for auditors from your ERP and QMS.

Optional. The tool and every export work without this. No spam.

Was this tool useful?

How to use the example

Edit the fields with your audit details, then export the report to Word or PDF. Keep the findings text objective: say what the requirement is, what you saw and the evidence (record number, date, location). Avoid blame and avoid advice on the solution. Grade each finding using your own procedure, and give a due date for the response. Add the records sampled to your audit file so that the finding can be reproduced if challenged.

  • State the requirement, the evidence and the gap.
  • Cite the clause or procedure for every finding.
  • Separate nonconformities from observations.
  • Keep the report to a few pages.

What ISO 13485 expects from internal audits

Clause 8.2.4 requires internal audits at planned intervals to check that the quality management system conforms to the standard, regulatory requirements and the organization's own arrangements, and is effectively implemented and maintained. You need a documented procedure covering audit criteria, scope, frequency, methods, auditor selection for objectivity, and reporting. Management responsible for the audited area must act without undue delay to eliminate nonconformities and their causes, and follow-up must verify the actions. Results feed the management review.

Findings: grading and common mistakes

Most organizations use major and minor nonconformity grades plus an optional observation or opportunity. A major usually means a missing or systemic failure of a requirement, or a risk to product safety or compliance. A minor is an isolated lapse. Common mistakes are vague findings with no evidence, auditing only documents and not the work, mixing consultancy advice into the report, auditors reviewing their own processes, and no check that corrective actions worked. Plan the audit schedule by process risk and past results, not just by calendar.

  • Findings with no objective evidence.
  • Auditor not independent of the process.
  • Corrective action closed without effectiveness check.
  • Same findings repeated audit after audit.

Frequently Asked Questions

What should an ISO 13485 internal audit report include?

Scope, criteria, date, auditors and auditees, method, positive observations, findings with clause and evidence, an overall conclusion, distribution and follow-up dates. Sign-off by the lead auditor shows the report is complete.

How often must internal audits be done under ISO 13485?

At planned intervals defined in your audit procedure. Many companies cover all processes across a year, with higher-risk or problem areas audited more often. Regulators and notified bodies expect the plan to be risk based.

What is the difference between a major and minor nonconformity?

There is no single definition, so write yours in the audit procedure. A major usually means a system-level failure or a risk to safety or regulatory compliance, while a minor is an isolated lapse that does not undermine the system.

Can the quality manager audit their own area?

No. The standard asks for objectivity and impartiality, so auditors must not audit their own work. In small companies use a trained person from another area or an external auditor for the areas the quality manager owns.

Where audit evidence sits in an ERP, we can set up a private assistant on your own servers to pull the records an auditor asks for. This template stands on its own.

Get ERP alerts and new tools

Support deadlines, release changes and new free tools for the ERP you run. A couple of emails a month at most.

Free. Unsubscribe with one click from any email.

ArchRay builder
Design the on-prem AI stack: model, GPUs, RAG pipeline, guardrails
See memory, speed and cost as you swap parts, then export the diagram. Free, in your browser.
Open the builder

Keep exploring

Free tools

Guides

AI on your ERP