SAP Procurement Type, Special Procurement Keys and BOM Item Categories

Procurement type and special procurement key on the MRP 2 view of the material master tell SAP whether to make, buy, transfer or subcontract. BOM item categories control how a line behaves in the BOM and MRP. This reference puts them in one table.

Download:
GroupKeyMeaningEffect in planning or BOM
Procurement type
E
In-house production
MRP creates planned orders
Procurement type
F
External procurement
MRP creates purchase requisitions or schedule lines
Procurement type
X
Both procurement types
Source decided by special procurement key, quota or order creation rules
Special procurement
10
Consignment
Purchase requisition for consignment info record; stock stays vendor-owned
Special procurement
20
Stock transfer
Requirement transferred to the supplying plant as a stock transport requisition
Special procurement
30
Subcontracting
Subcontract requisition; components are provided to the vendor
Special procurement
40
Production in another plant
Demand passed to the plant that produces the material
Special procurement
50
Phantom assembly
Assembly is not stocked; its components are exploded into the parent order
Special procurement
52
Direct production
Dependent requirements pass through without a separate order for the item
Special procurement
60
Phantom in planning
Treated as phantom during MRP, produced with its own order in execution
BOM item category
L
Stock item
Material with a master record; included in MRP and inventory management
BOM item category
N
Non-stock item
Free text part bought for the order, no stock managed
BOM item category
D
Document item
Links a document info record, e.g. a drawing, no quantity planning
BOM item category
T
Text item
Text line for information only
BOM item category
K
Class item
Selects materials by class characteristics
BOM item category
R
Variable-size item
Uses size formulas to calculate quantity
BOM item category
M
Intra material
Intermediate material used inside the BOM structure

These are standard delivered values. Special procurement keys are defined per plant in Customizing and can be changed or extended, so a key such as 60 may not exist in your system. Check the MRP 2 view of a sample material to see which keys are used.

Material master consistency scan

Optional: send us a material master extract and we will return a list of inconsistent procurement settings.

Optional. The tool and every export work without this. No spam.

Was this tool useful?

How to use this reference

Filter on a group (procurement type, special procurement, BOM item category) or search for words such as 'phantom' or 'subcontracting'. Compare your own materials against the keys when you suspect MRP is creating the wrong document, for example a purchase requisition for an item you intended to produce.

How MRP uses these settings

Procurement type E creates planned orders, F creates purchase requisitions and X relies on the special procurement key or quota arrangement. Key 30 turns a purchase into a subcontract order and brings the component supply into planning. A phantom (key 50) removes a level from stock but keeps the explosion, which is helpful for sub-assemblies that are never stored. Key 52 differs: it skips order creation for the item entirely.

  • Check the MRP group on the material before blaming the key.
  • A phantom needs a BOM; without one MRP cannot pass requirements on.
  • Stock transfer needs a supplying plant on the MRP 2 view.

Common mistakes

Two mistakes cause most trouble. First, setting X without a special procurement key or quota arrangement, so MRP cannot decide the source and produces unexpected documents. Second, using phantom keys on materials that should be stocked, which hides inventory and breaks costing. Review changes in a test plant with MD03 before changing live materials.

Frequently Asked Questions

What does procurement type X mean?

X means the material can be both produced in-house and procured externally. SAP then needs more information to choose, normally a special procurement key, a quota arrangement or order proposals set by the planner. Without it the result can be unpredictable.

What is the difference between phantom 50 and direct production 52?

A phantom assembly (50) is exploded straight through into the parent order without its own order and without stock. Direct production (52) means the item has no separate order creation in MRP and its requirements pass through to the lower levels, commonly used for repetitive manufacturing flows.

Which BOM item category should I use for a bought-in consumable?

Use L if the item has a material master and you want stock managed, and N only if you purchase it per order without stock management. If the item is a drawing or work instruction, D or T are correct.

Where is the special procurement key maintained?

On the MRP 2 view of the material master (MM01, MM02) in the Procurement section. The available keys are defined per plant in Customizing, so the list on screen is the authoritative one for your system.

Netray can scan your material master export and list materials whose procurement setup is inconsistent with their BOM and routing, as a quick data quality exercise.

Get ERP alerts and new tools

Support deadlines, release changes and new free tools for the ERP you run. A couple of emails a month at most.

Free. Unsubscribe with one click from any email.

ArchRay builder
Design the on-prem AI stack: model, GPUs, RAG pipeline, guardrails
See memory, speed and cost as you swap parts, then export the diagram. Free, in your browser.
Open the builder

Keep exploring