Epicor Kinetic Job Status Reference: Every Flag and What It Does
Epicor does not store one job status field. A job's state is the combination of several flags on the JobHead table, and getting the combination right is the difference between a trustworthy BAQ and one that lists closed jobs as open.
| Table.Field | Kind | What it means | Typically set by | Use in a BAQ or dashboard |
|---|---|---|---|---|
JobHead.JobNum | Key | Job number, unique within the company. | Job Entry on creation or MRP | Join key to JobOper, JobMtl, JobAsmbl together with Company. |
JobHead.PartNum | Attribute | Part the job produces. | Job Entry or MRP | Filter or group by finished part. |
JobHead.ProdQty | Quantity | Planned production quantity. | Job Entry or MRP | Compare with received quantity to find short-running jobs. |
JobHead.JobType | Attribute | Type of job such as manufacturing versus other job types your site uses. | Job Entry | Exclude non-manufacturing job types from shop floor dashboards. |
JobHead.JobEngineered | Flag | The job method has been engineered and approved so it can move toward release. | Engineer in Job Entry or Job Engineering | Find jobs waiting for engineering sign-off: Engineered = false. |
JobHead.JobReleased | Flag | Job is released to the shop floor, so labor and material can be reported against it. | Job Entry or Job Release process | Open shop floor work: Released = true and Closed = false. |
JobHead.JobFirm | Flag | Job is firmed so MRP treats it as a fixed supply instead of rescheduling it. | Planner in Job Entry | Separate firm supply from suggested supply in a planning view. |
JobHead.JobHeld | Flag | Job is on hold, normally blocking further activity until released from hold. | Planner or quality | Hold list for daily production meeting. |
JobHead.JobComplete | Flag | Production is finished. The job still holds costs until it is closed. | Shop floor completion or Job Entry | Completed but not closed: the WIP cleanup list. |
JobHead.JobClosed | Flag | Job is closed after the close job process. No further transactions are normally allowed. | Close Job process, usually month end | Exclude closed jobs from open work and WIP reports. |
JobHead.StartDate | Date | Scheduled job start date. | Scheduling engine or planner | Starts this week lists. |
JobHead.DueDate | Date | Scheduled job finish date. | Scheduling engine or planner | Late job report: DueDate < today and Complete = false. |
JobHead.ReqDueDate | Date | Required due date driven by demand. | Job Entry or MRP | Compare with DueDate to expose schedule slippage. |
JobOper.OpComplete | Flag | The operation is complete. | Labor entry or Job Entry | Find the current operation: first op where OpComplete = false. |
JobOper.RunQty | Quantity | Planned run quantity on the operation. | Job Entry | Operation load and throughput reports. |
JobMtl.IssuedComplete | Flag | Material requirement is fully issued. | Material issue transactions | Kitting readiness: released jobs with unissued material. |
JobMtl.IssuedQty | Quantity | Quantity issued so far to the job. | Issue Material | Compare with RequiredQty for shortages. |
Field names reflect the standard Epicor Kinetic data model. Confirm against your version in Data Dictionary Viewer, since custom fields and version changes can differ.
Job status dashboard review
Send us the BAQ behind your job status dashboard and we will review it for flag logic errors.
Optional. The tool and every export work without this. No spam.
How to use this reference
Search for the flag or field you need, then read the last column to see how it is normally used in a BAQ or dashboard. The lifecycle runs roughly Engineered, Released, Complete and then Closed, with Firm and Held as side states. A planner cares about Firm, a shop supervisor about Released and Held, and finance about Complete versus Closed. Start your BAQ from the audience's question and then choose the flags, rather than the other way around.
- Open shop floor work: Released true, Complete false, Closed false
- Waiting on engineering: Engineered false, Closed false
- WIP cleanup: Complete true, Closed false
- Planning view: group by Firm to separate fixed supply from suggestions
Complete is not Closed
The most common mistake is treating completion as the end of the job. A complete job has finished production but still carries WIP and variances until the close process runs. Finance usually closes jobs at period end, so the gap between Complete and Closed is your accrual and cleanup list. If a dashboard filters only on Closed, it will show finished jobs as open for weeks.
Firm and Held change how others see the job
Firm tells MRP not to move the job, which matters when planners wonder why a suggested date was ignored. Held blocks activity and is often used by quality. Neither is a replacement for the release flag, and each should be a visible column in any list that supervisors act on, because a hidden hold looks like a stalled shop.
Version and customization notes
Kinetic keeps adding fields and some sites add user-defined columns for their own statuses. Always confirm names in Data Dictionary Viewer before copying into a BAQ, and prefer calculated fields for a combined status label so one definition serves every report.
Frequently Asked Questions
Where is the job status field in Epicor Kinetic?
There is no single status field. State is derived from flags on JobHead such as JobEngineered, JobReleased, JobFirm, JobHeld, JobComplete and JobClosed. Many sites build a calculated field in a BAQ that turns the combination into one readable label for dashboards.
What is the difference between Complete and Closed on an Epicor job?
Complete means production is finished. Closed means the job has been through the close process, so costs are moved out of WIP and the job no longer accepts normal transactions. Many sites leave jobs complete until month end before closing them.
Why does MRP ignore a job I want moved?
Check the Firm flag. MRP treats firm jobs as fixed supply and does not reschedule them in the usual way. Unfirm the job in Job Entry if you want MRP to suggest changes, then rerun the planning process.
Can I add my own job status to Epicor?
You can add user-defined fields and use BPM or a BAQ calculated field to set or display a custom status. Keep it additive and do not overload the standard flags, since standard reports and processes rely on their normal meaning.
If your teams still build job status lists by hand, we can set up a read-only natural language layer over Epicor data that applies these flags consistently.
Related Tools
Epicor BAQ Query Template Generator
Fill in company, days back and status filters to get a starter SQL for an open jobs BAQ, plus a design checklist for the Query Builder.
EpicorEpicor REST API v2 URL Builder
Fill in server, instance, company and service to get a ready OData URL, a curl command and the required headers for the Epicor REST API v2.
EpicorEpicor MRP Run Checklist
A practical checklist for planners running Epicor MRP, with critical checks on part data, lead times, firm jobs and the review of suggestions.
EpicorEpicor BPM Directive Design Template
A fill-in design document for BPM method and data directives covering trigger, conditions, actions, testing and rollback.
More Epicor tools
See all- Epicor DMT Import Template Worksheet (Part and BOM)
- Epicor Kinetic Upgrade Checklist
- Epicor Security Group Design Worksheet
- Epicor Safety Stock and Reorder Point Calculator
- Epicor EOQ and Lot Sizing Calculator
- Epicor Resource Group Burden Rate Calculator
- Epicor Shop Floor OEE Calculator
- Epicor Job Cost Variance Worksheet
- Epicor Shop Floor Labor Reporting SOP Template
New to Epicor ERP? Start with the Epicor ERP guide and toolkit, or plan with Training Path Builder, ERP Certification Study Planner, Upgrade Path Planner.
Keep exploring
Free tools
- Epicor Job Lifecycle Flags ReferenceLookup table of the job status flags on Erp.JobHead and related tables, what they mean and how to use them in BAQs.
- Epicor Kinetic Database Tables ReferenceLook up the main Erp.* tables in Epicor Kinetic with what each holds and the columns that identify a row. Useful when writing BAQs and SQL.
- Epicor Kinetic Custom Report Inventory WorksheetAn editable register of custom reports, BAQs and dashboards to support upgrade testing and clean-up of unused items.
ERP fixes and how-tos
- Epicor Kinetic: Job Will Not Release in Job EntryEpicor Kinetic job will not release or the Released box will not stick? Walk through Engineered, Firm, unapproved revisions, method checks and the JobHead flags.
- How to Complete an Operation in Epicor Kinetic (Plus Time Entry and Corrective Action)Complete an operation in Epicor Kinetic through MES or Labor Entry, plus time and expense entry, customer managed inventory and corrective action, with what to check first.
- How to Issue Material in Epicor KineticIssue material to a job in Epicor Kinetic: direct and backflush options, substituting parts, the material queue, and what to check when issue fails.
AI on your ERP
- Getting Epicor Kinetic Data Ready for AI: Part Master, BAQs, UD Fields and Job DataHow to get Epicor Kinetic and ERP 10 data ready for AI: part master, revisions, UD fields, BAQs as definitions, labor and job data quality, security groups.
- AI for Epicor Kinetic Job Shops: Quote History, Job Variance and Schedule RiskPrivate AI for Epicor Kinetic job shops: quote-to-job history, JobHead and JobOper variance, subcontract delays and schedule risk, via REST and BAQs.
Integrations
- How to add AI agents to Epicor KineticHow to add AI agents to Epicor Kinetic: a tool layer over the REST v2 API and BAQs, MRP exception triage, PO expediting, and human approval before any write.
- How to add an AI chatbot to Epicor KineticAdd an AI chatbot to Epicor Kinetic: an internal assistant for planners and buyers or a customer portal bot, grounded in BAQs and runnable fully on-prem.